Reports Search Reports Spatial Search Risk-cases Search Risk-cases Graph Traversal
27 results found in 9 ms Page 1 of 3
Federal Agencies Need to Address Aging Legacy Systems
Be aware of legacy IT risks The US government spends about 75 percent of the total amount budgeted for information technology on operations and maintenance. GAO reviewed Office of Management and Budget and 26 agencies, covering years 2010 through 2017 and recommends to develop a goal for spending measure and finalize guidance to identify and prioritize legacy IT needing to be modernized or replaced.
Full description
General Accountability Office , issued in 2016
Risk cases: 3
Federal Human Resources Data
Internal control weaknesses may put mission at risk GAO audited the Enterprise Human Resources Integration payroll data warehose. The American auditors pointed at problems that may impede 'leverage of these data to meet its mission and allow others to make full use' of them. The critical internal contols areas to be improved in this cas are: completeness, accuracy, and validity of information, authorization, documentation, monitoring, results' evaluation.
Full description
General Accountability Office , issued in 2016
Risk cases: 2
Digital transformation in government
Support exemplars, provide consistent guidance... and do not lose focus As the NAO states: Government faces significant challenges in providing public services. While many government services are now available online, public administration is struggling to manage more complicated programmes and to improve the complex systems and processes that support public services.
Full description
National Audit Office , issued in 2017
Risk cases: 4
Staff scheduling in government institutions
Scheduling irregular hours work Danish Rigsrevisionen shows in their study problems with staff scheduling in government institutions where employees are required to work irregular hours. Optimized staff scheduling contributed to reducing payroll costs. On the other hand, problems with rearrangement of work, recording working hours, optimisation of staffing levels and analysis of overtime triggers - add up to high costs of workforce. IT is not always used as ally either.
Full description
National Audit Office of Denmark , issued in 2015
Risk cases: 5
FEMA Needs to Address Management Weaknesses to Improve Its Systems
Controls in emergency management GAO audited the agency of the Department of Homeland Security, responsible for federal efforts to mitigate, respond to, and recover from disasters. American auditors recommend that the agency fully define its investment board’s roles and responsibilities and procedures for selecting and overseeing investments, update its strategic plan and complete plans for IT modernization, and establish time frames for completing workforce planning efforts. The agency should also establish policies and guidance for implementing key IT management controls.
Full description
General Accountability Office , issued in 2016
Risk cases: 4
Open Data Trend Report 2015
How to activate the open data policy The Dutch SAI looks for ways to improve open data practice in the Netherlands. They point at experience of two leading countries: UK and US, and advise to: prepare a concrete action plan, to increase number of mandatory published data, to develop government-wide data inventory and to put open data to work.
Full description
Netherlands Court of Audits , issued in 2015
Risk cases: 4
Conflicts of interest
First, recognise the conflicts of interest are a real risk the British NAO gathered a significant amount of intelligence on conflicts, particularly in the health and education sectors. These are areas of government where services are increasingly commissioned and delivered by parties at arm’s-length to departments. Conflicts of interest can occur naturally as a product of the way a system is designed and most often arise from operational situations.
Full description
National Audit Office , issued in 2015
Risk cases: 8
Information security work at nine agencies
Difficulties in achieving appropriate IT security Together with the Swedish NAO we assume that the picture that emerges at the agencies audited applies also to most of the other agencies in the public administration. The information security work is not given high enough priority in relation to the risks that exist. This applies to both the Government, which should have been clearer in its directions to agencies on this matter, and to agency managements, which did not give priority to the work of information security to the extent required. Much indicates that it is difficult for many agencies to achieve an appropriate level of information security work.
Full description
Swedish National Audit Office , issued in 2016
Risk cases: 4
Opportunities Exist for FAA to Improve Airport Terminal Area Safety Efforts
Inefficient use of data The US GAO examined various issues related to runway safety and to update its prior work on airport terminal areas. Their findings point at inefficient use of data, which may lead to more risk and to inefficient targeting their limited resources.
Full description
US Government Accountability Office , issued in 2019
Risk cases: 3
Homeland Security. Oversight of Neglected Human Resources Information Technology Investment Is Needed
Human resources IT investments get stuck in management's lack of interest Although the Human Resources Information Technology (HRIT) investment was initiated about 12 years ago with the intent to consolidate, integrate, and modernize the department's human resources IT infrastructure, the Department of Homeland Security (DHS) has made very limited progress in achieving these goals. HRIT's minimally involved executive steering committee during a time when significant problems were occurring was a key factor in the lack of progress. This is particularly problematic given that the department's ability to efficiently and effectively carry out its mission is significantly hampered by its fragmented human resources. DHS's ineffective management of HRIT, such as the lack of an updated schedule and a life-cycle cost estimate, also contributed to the neglect this investment has experienced. DHS will be limited in efficiently tracking and reporting accurate, comprehensive performance and learning management data across the organization, and could risk further implementation delays.
Full description
US Government Accountability Office , issued in 2016
Risk cases: 1
27 results found. Page 1 of 3 next