Reports Search Reports Spatial Search Risk-cases Search Risk-cases Graph Traversal
5 results found in 3 ms Page 1 of 1
State aid for IT projects in social and health care
In 2000-2009 about 180 million euros in national and European Union funds went to finance information technology projects in social and health care, not including the costs of developing national ... and Health. All in all approximately 250 million euros was tied to development projects carried out as national measures in 2000-2010, not including the self-funded portion of aid or loans granted ... to enterprises by Tekes or financing granted by the Finnish Innovation Fund (Sitra) for IT projects in social and health care. ... Difficult coordination of IT projects ... Finish Audit Office analyzed results of poor cooperation between authorities on national and local level in social and health care projects: difficult integration of information systems and poor ... coordination of the financing information technology projects, including double financing.
Full description
National Audit Office of Finland , issued in 2011
Risk cases: 3
Business Continuity Management
Business Continuity Management is a process whereby all necessary measures are taken to ensure that a company can accomplish its core tasks on time even in extraordinary situations. The Swiss Federal ... Audit Office (SFAO) previously carried out a cross-section audit in 2009 on the BCM measures at nine administrative units of the central Federal Administration. This year’s audit focused ... on the decentralised Federal Administration as well as the Swiss Federal Railways (rail transport and ticket sales) and Swiss Post (PostFinance, Swiss Post Solutions, PostBus). ... ... A cross-section audit on business continuity management (BCM) ... The audit points, among others, at a necessary but difficult process chain: Policy - Analysis - Strategy - Planning - Training.
Full description
Swiss Federal Audit Office , issued in 2010
Risk cases: 1
IT security in the Federal Administration
The SFAO has audited the Admin PKI – the basic infrastructure and offering for the issuing of digital certificates – within the Federal Office of Information Technology, Systems and Telecommunication ... (FOITT). The examination concentrated on assessing the development and current operation as well as future prospects. Admin PKI refers to all processes and the hardware and software needed for issuing ... certificates of different grades. ... Technical and organizational deficiencies work together against data security ... Only minor deficiencies were revealed in the Windows environment but only in case of Microsoft products.Providers' lack of both assertiveness and synergy adds to 'the great unknown' of authonomous ... entities' networks.
Full description
Swiss Federal Audit Office , issued in 2011
Risk cases: 4
Lessons learned from government ICT-projects
This audit has been performed on request of the Dutch parliament. Some newspapers mentioned government losses of four to five billion euro's on a yearly bases. These news items caused the parliament ... to request this audit. The audit has been performed in only 5 months time and consisted of the re-use of earlier performed audits. We have 'recycled' earlier findings about ICT-projects. ... 'Expensive' does not always mean 'High Quality', so... do not feed the spiral ... Excellent analysis of systemic errors commited when designing Government IT projects. The report aims at the essence of problems which are encountered far from information technologies - in: politics ... , business, psychology... Do not be mislead by date of report, it is evergreen for all who really want to know why IT projects fail.
Full description
Netherlands Court of Audits , issued in 2007
Risk cases: 3
Software Developement Effective Practices and Federal Chalenges in Applying Agile Methods
To identify effective practices in applying Agile for software developement solutions and federal challenges in implementing Agile techniques. ... Agile project approach in government practice ... Useful products delivered in a short time are basis for often applauded features of agile project approach. Applied by many private companies, it tends as well to be more and more popular among state ... administrations. American GAO reviewed set of agile projects and revealed - apart from advantages - a set of commonly occurring problems: poor team work, lack of time and deficit of customers’ trust.
Full description
General Accountability Office , issued in 2012
Risk cases: 4
5 results found. Page 1 of 1