Reports Search Reports Spatial Search Risk-cases Search Risk-cases Graph Traversal
62 results found in 9 ms Page 1 of 7
Auditing the National Rationing System
The audit was to investigate the data quality, validity and reliability of two sub-systems (Ration Card and Ration Distribution) of a National Rationing System (Ration System) with the comparison ... to the rules and regulations in order to make an assessment of soundness of the Ration system and its related operations. ... Unreliable databases trigger all kinds of possible problems ... Ministry responsible for functioning of the National Rationing System developed to automate and optimize the delivery of essential subsidized commodities to eligible beneficiaries and providing state ... with reliable information fails its job.
Full description
State Audit Bureau of Kuwait , issued in 2014
Risk cases: 4
Traffic Ticketing information system
The audit included two areas of focus - the environment surrounding the Traffic Ticketing Information System - the System (designed to input, process, manage and collect payment for the traffic ... tickets) and also the internal environment of the System that guarantees the quality of its performance and safety. ... Security can hinder effectiveness ... SAI of Kuwait analysed system supporting collection of the traffic tickets - data input, processing and management. What was found was lack of basic safety measures, that hindered the effectiveness ... of the system.
Full description
State Audit Bureau of Kuwait , issued in 2014
Risk cases: 3
Municipalities’ internal control system – Audit of the establishment and operation of the internal control system of municipalities – on the audit of Rudabánya
Incomplete internal control The SAI Hungary published the compliance audit of the establishment and operation of the internal control system, as well as certain investment decisions, their implementation and accounting at the Local Government of Rudabánya. Apart from positive findings, some accounting irregularities and insufficient controls established to ensure organisational integrity were pointed out.
Full description
State Audit Office of Hungary , issued in 2018
Risk cases: 2
Individual Operation System Development Projects
Audit of modernization of Patent Operation MGT Systems. The modernization's main aim was to replace existing multi-system structure of patents management with one consolidated and up-to-technology IS. ... No results without good management ... SAI of Japan, among its audits presents one which is concerned with stopped development of consolidated IT system for patents management.
Full description
Board of Audit of Japan , issued in 2012
Risk cases: 1
Building and Implementing the Phoenix Pay System
Expensive IT project became a failure Phoenix project (development of states pay system) was an incomprehensible failure of project management and oversight. Phoenix executives prioritized certain aspects, such as schedule and budget, over other critical ones, such as functionality and security. Phoenix executives did not understand the importance of warnings that the Miramichi Pay Centre, departments and agencies, and the new system were not ready. They did not provide complete and accurate information to deputy ministers and associate deputy ministers of departments and agencies, including the Deputy Minister of Public Services and Procurement, when briefing them on Phoenix readiness for implementation.
Full description
Office of theAuditor Generalof Canada , issued in 2018
Risk cases: 3
Federal Agencies Need to Address Aging Legacy Systems
Be aware of legacy IT risks The US government spends about 75 percent of the total amount budgeted for information technology on operations and maintenance. GAO reviewed Office of Management and Budget and 26 agencies, covering years 2010 through 2017 and recommends to develop a goal for spending measure and finalize guidance to identify and prioritize legacy IT needing to be modernized or replaced.
Full description
General Accountability Office , issued in 2016
Risk cases: 3
FEMA Needs to Address Management Weaknesses to Improve Its Systems
Controls in emergency management GAO audited the agency of the Department of Homeland Security, responsible for federal efforts to mitigate, respond to, and recover from disasters. American auditors recommend that the agency fully define its investment board’s roles and responsibilities and procedures for selecting and overseeing investments, update its strategic plan and complete plans for IT modernization, and establish time frames for completing workforce planning efforts. The agency should also establish policies and guidance for implementing key IT management controls.
Full description
General Accountability Office , issued in 2016
Risk cases: 4
Finally updating the central information system for VAT control
IT system to support combating VAT frauds German Bundesrechnungshof demanded to update the IT system, which plays crucial role in the European system of fighting fraud related to the Value Added Tax (VAT). This BRH's case shows that reminding about appropriate follow-up can be as important as the very recommendation.
Full description
Bundesrechnungshof , issued in 2014
Risk cases: 1
General and Creation Control of the Information Systems of the Ministry of Foreign Affairs
The objective of the audit was to assess general and creation control of the information systems of the Ministry of Foreign Affairs. Since the beginning of 2009, the Ministry of Foreign Affairs has ... achieved considerable progress in the management of the information systems. The auditors reviewed and assessed all key elements of the process. ... Overview of problems - area by area ... SAI Lithuania looked into all critical elements of a Ministry's information system, starting from IT architecture, through information security to automation of data processing.
Full description
National Audit Office of the Republic of Lithuania , issued in 2013
Risk cases: 4
Results of the development of the state’s information systems
, several measures have been implemented in the state to organise the development better and to guarantee that the systems are compatible. This audit gives an opinion of the results of development project ... The National Audit Office has repeatedly audited the management and development of the state’s information technology (IT) area in the last ten years. The last audit was performed in 2005. After that ... management and the state’s coordination mechanism in this process. ... ... Success and failure depend on preparation ... Conclusions of performance IT audit based on a sample of government projects: business portal, land register, e-police, fire safety monitoring system, childcare information system and the document ... management system of the Defence Forces. Key problems and discussion with auditees are presented.
Full description
National Audit Office of Estonia , issued in 2010
Risk cases: 3
62 results found. Page 1 of 7 next