Reports Search Reports Spatial Search Risk-cases Search Risk-cases Graph Traversal
16 results found in 10 ms Page 1 of 2
Performance Audit of the Georgian Government electronic Procurement system
State procurement is one of the key components of public financial management. Its share in state budget is approximately 25 percent. Effective management of state procurements is an important sphere ... and fraud, which in return supports the successful implementation of country’s anti-corruption policy. To develop such environment, the system must provide confidentiality, integrity and availability ... of existing data through effective procurement policies and procedures. <br /> Having considered aforementioned factors, SAO conducted performance audit of the Georgian electronic Government Procurement system ... ... Electronic procurement system - how effective are management and control mechanisms? ... SAI Georgia analyzed the electronic Government Procurement system. In their report they focus on compliance and security problems, which may harm the business goals and overall mission of the system.
Full description
State Audit Office Of Georgia , issued in 2016
Risk cases: 5
Performance Audit of Public Debt Management Information Systems
The usage and development of the information technologies in public financial management is an important priority of the country at the phase of intensive implementation of electronic governance ... implemented by the Public Debt and External Financing Department of the MOF. Hereby, the audit team also to assessed systems’ data integrity and security. In the course of the audit, the audit team also studied ... (E-Governance). The fact that information systems play crucial role in the business processes of the Ministry of Finance affects the state and the public in general. <br/> Bearing in mind the role and importance ... ... More effective IT governance needed ... Importance of effective performance of public debt management e-systems may be explained by the world’s increased dependence on such systems. In parallel with the performance audit of debt management ... information systems of the Ministry Of Finance of Georgia, Supreme Audit Institutions of 11 countries also studied this topic, both in terms of systems’ performance and their practical application by local ... financial institutions. Audit conducted by the State Audit Office of Georgia has revealed security and governance shortcomings related to management and usage of these systems.
Full description
State Audit Office Of Georgia , issued in 2014
Risk cases: 5
Managing the risk of legacy ICT to public service delivery
within a business function but superseded by newer and more effective technologies or changed business needs"). ... The cross-government report describes the case studies from four public services (state pension, Value Added Tax collection, prescription payment and consumer credit licensing services) selected ... to illustrate the range of approaches that small and large government bodies are taking to address the issues arising from legacy ICT (defined as "systems and applications that have been operationally embedded ... Possible approaches to the problem of 'legacy ICT' ... UK’s government experience in managing the risks connected to legacy ICT provides valuable insight for others facing the same problem and are considering transforming their services.
Full description
National Audit Office , issued in 2013
Risk cases: 3
Audit of the key ICT project federal GEVER programme Federal Chancellery
During the first stage, two new GEVER (electronic records and process management) products were procured in an open WTO tender within the framework of the two-product strategy (federal GEVER WTO ... procurement project). CHF 1.6 million was spent on these. The departments and Federal Chancellery (departments/FCh) had to choose one of the two products within three months of the contract being awarded. ... ... Advanced process management system's cost-effectiveness and deadlines at risk ... in order to ensure the successful creation and introduction of GEVER. Previous efforts did not have any widespread success and led to a diverse GEVER landscape. The federal GEVER project has now laid ... Ever since 1990, sequential controls and file management have been part of the Federal Administration's IT landscape (GEVER business administration). Significant obstacles have to be overcome ... the foundations for simplification and centralisation.
Full description
Swiss Federal Audit Office , issued in 2015
Risk cases: 2
Effectiveness of the Tax Administration of the Republic of Slovenia in the execution of modernisation projects of the Slovenian duty information system and decreasing the number of duty sub-accounts
of the European Union budget. In order to improve its operations, the Tax Authority decided to modernise the Slovenian duties’ collection information system. It used this opportunity to implement also a second ... some improvements and had also enabled implementation of the second project - decreasing the number of government duty sub-accounts. Despite these successes, the combined projects of modernisation ... The Tax Administration of the Republic of Slovenia (hereinafter: the Tax Administration) is responsible for collecting taxes, fees and other compulsory levies (hereinafter: duties ... ... Shaky coordination of investments in important systems ... Slovenian SAI traced a series of problems in management of crucial IT investments in tax administration. Apart from promising goals, unclear business case gave a start to many problems at next stages ... of the project, involving additional spendings, delays and errors in data processing.
Full description
Court of Audit of the Republic of Slovenia , issued in 2014
Risk cases: 7
Maintenance efficiency in the rail network
The primary objective of railway politics is to contribute to ensure that users of the transport service have good railway options. The Norwegian National Rail Administration is organised under ... the Ministry of Transport and Communications, and its responsibilities include operation, maintenance and development of the State's railway infrastructure. The maintenance activities must safeguard safety ... , fixed assets and operational stability of the railway system. The most important objective for the maintenance is to reduce the scope of operational interruptions, and to facilitate better punctuality ... ... Rail network maintenance - negative balance of costs and results ... SAI Norway evaluated efficiency of the railway maintenance and found that its costs increased nearly 110 per cent in years 2006–2014. Negative development in uptime and regularity dominated the first ... part of the examined period, from 2006 to 2011. It turned positive from 2011, but in 2014 results were still worse than in 2006. The results have lagged behind the Ministry's target figures for most ... of the period.
Full description
Office of the Auditor General of Norway , issued in 2016
Risk cases: 2
The Board of Audit and Inspection (BAI) conducted an audit on the information systems in the area of service delivery to improve the system’s efficiency and convenience.
Korea was recognized as an Information Technology (IT) powerhouse by the international community of the UN in 2010. Such an achievement is attributable to the significant investments that the Korean ... government has commissioned toward improving the country’s information infrastructure within a short period of time.<br/> The government is investing 1 trillion won every year in an e-government project ... for citizens in the welfare and employment sectors by utilizing the renewed information infrastructure.<br/> However, the information system of some government ministries proved to have overlapping functions ... Enormous IT investments require tremendous coordination ... and the speed, the information technologies are implemented with, cause some problems to be tackled. The SAI Korea turns special atention to two of them: overlapping functionalities and interconnectivity issues. ... Korean government is investing 1 trillion won in e-government projectsevery year. Thus, the country has earned a reputation for the IT powerhouse. Apart from undeniable advantages, the huge scale
Full description
Board of Audit and Inspection of Korea , issued in 2011
Risk cases: 3
State funds spent on development, operation and using of data centres services
The aim of the audit was to scrutinise the management of funds spent on building and operating the national data centre (hereinafter “STC1 data centre”), including the expenditure of selected ... organisational units of the state on buying hosting, server-housing and other related services. The audited period was between 2010 and 2014; where relevant, the preceding period was also scrutinised. Audited ... entities: Ministry of the Interior (“MoI”); Ministry of Finance (“MoF”); STÁTNÍ TISKÁRNA CENIN, state firm (state banknote printing firm, hereinafter “STC” or “the state firm”). The audit was conducted ... ... Risks steming from uncoordinated strategy ... SAI of Czech Republic analysed consequences of failures in strategic IT management at the state level. Lack of coordination and implementation rules reduced practical role of the ministry whose task ... was to guard high quality standards for all crucial IT systems in the state administration. Next consecquences were (among others) risk of uneconomical results of large IT investment and risk of inefficient ... supply of services, as well as opposite results of workforce reduction.
Full description
Supreme Audit Office of Czech Republic , issued in 2015
Risk cases: 7
Management and protection of assets in the field of the information-communication technologies at the ME SR
The Supreme Audit office of the Slovak Republic (SAO SR) has conducted the audit at the Ministry of Environment of the Slovak Republic (ME SR) for the audit period 2011 and 2012 to examine ... the compliance with the generally binding legal regulations and the general statues in the field of the information-communication technologies (ICT) and the information systems of the public administration (ISPA ... ) with emphasis on the use of the information technology (IT) services provided by the third parties. The vast amount of irregularities was found, especially many cases of failure to comply with the standards ... ... Started from contracting, ended in security ... The perceptive and filled with findings audit - conducted by the Slovak SAI - discovered the list of issues which started in careless contracting procedures, failure to update the development concept ... and ended in exposing the organization to high security risks.
Full description
Supreme Audit Office of the Slovak Republic , issued in 2012
Risk cases: 4
The National Offender Management Information System (NOMIS)
This report examines the reasons for the delays and cost increases to the original integrated information system and, since the moratorium imposed by the Minister of State in order to seek options ... for project’s cost reduction, the aims of the revised National Offender Management Service (NOMS) and the progress made, the impact of the delays and rescoping on the costs and benefits achieved, and NOMS ... ’ fitness to deliver. The aim of one integrated information system (C-NOMIS i.e. National Offender Management Information System) was to improve information sharing about offenders; address the lack ... Rescoping necessary, but not fully successful ... An initiative to build a single offender management IT system for the prison and probation services has not delivered value for money. The NAO investigation found the project had been hampered ... by poor management leading to a three-year delay, a doubling in project costs and reductions in scope and benefits.
Full description
National Audit Office , issued in 2009
Risk cases: 4
16 results found. Page 1 of 2 next