Reports Search Reports Spatial Search Risk-cases Search Risk-cases Graph Traversal
36 results found in 9 ms Page 1 of 4
VAT risk assessment - better use made of information generated by inspections on company premise
Tax inspections may add up to the VAT risk assessment, but... The audit by the German BRH shows that general tax inspections on company premises can also reveal facts that may be relevant for VAT risk assessment. 'However, this information cannot be adequately used for VAT risk assessment because it is not available in electronic format.'
Full description
Bundesrechnungshof , issued in 2016
Risk cases: 1
Coordinated Audit on Information Technology Governance
IT governance needs awareness and SAIs' support The OLACEFS auditors found that the greatest challenge for the SAIs is to raise the awareness of the audit institutions about the importance of IT governance and the benefits that could be obtained by improving its degree of maturity. The audit was conducted by 11 SAIs and coordinated by TCU of Brasil. They concluded: 'It is important, even urgent, to invest resources to implement or enhance: the IT committees; the IT planning process; strategic IT planning; monitoring the IT contracting process; the business continuity plan; the designation of a responsible person or unit to manage security information; a risk management process; an asset inventory process; an information security committee; and a policy for access control.'
Full description
Latin American andCaribbean Organization of Supreme Audit Institutions , issued in 2015
Risk cases: 5
Federal Agencies Need to Address Aging Legacy Systems
Be aware of legacy IT risks The US government spends about 75 percent of the total amount budgeted for information technology on operations and maintenance. GAO reviewed Office of Management and Budget and 26 agencies, covering years 2010 through 2017 and recommends to develop a goal for spending measure and finalize guidance to identify and prioritize legacy IT needing to be modernized or replaced.
Full description
General Accountability Office , issued in 2016
Risk cases: 3
Correlations between the operational risks of companies in the majority ownership of local governments and the financial situation of the local governments
Risks related to local governments-owned companies The Hungarian SAI analysed four risk areas, taking 19 aspects and the specificities of Hungary’s settlement patterns into consideration. The four areas defined were the following: performance of public tasks, exercise of proprietary rights, financial stability of local governments, and short and medium-term stability of the financial management of companies.
Full description
State Audit Office of Hungary , issued in 2017
Risk cases: 1
Management of Police Information Resources
Police tasks of the necessary data are processed departmental registers, information systems, automated data processing systems and networks where information is stored, processed and transferred ... to the classified information. The police department has all of these information resources, so the audit focused on the activities and actions of the Department to ensure planning and organizing of the recourses ... , monitoring, evaluation and coordination and other aspects of registers and IS strategic management. The audited period was 2012-2014. For the analysis, there were used previous data and data of 2015 ... ... Fundamentals of IT organisation ... Review by SAI Lithuania makes readers aware that nowadays it is difficult to develop a larger IT system without whole conceptual infrastracture: planning composed into strategy of the organisation ... and well understood architecture of information. Well functioning IT management structures, which on the other hand may sound trivial, were proved here as the key to success.
Full description
National Audit Office of the Republic of Lithuania , issued in 2015
Risk cases: 4
Opportunities Exist for FAA to Improve Airport Terminal Area Safety Efforts
Inefficient use of data The US GAO examined various issues related to runway safety and to update its prior work on airport terminal areas. Their findings point at inefficient use of data, which may lead to more risk and to inefficient targeting their limited resources.
Full description
US Government Accountability Office , issued in 2019
Risk cases: 3
Cost-intensive data centres stood idle for years
Idle data centres As found by the German SAI, some of costly Federal data centres stood largely idle. The Ministry failed to adequately assess the project risks. The Ministry needs to avoid similar shortcomings in the proposed federal IT consolidation project.
Full description
Bundesrechnungshof , issued in 2016
Risk cases: 1
Conflicts of interest
First, recognise the conflicts of interest are a real risk the British NAO gathered a significant amount of intelligence on conflicts, particularly in the health and education sectors. These are areas of government where services are increasingly commissioned and delivered by parties at arm’s-length to departments. Conflicts of interest can occur naturally as a product of the way a system is designed and most often arise from operational situations.
Full description
National Audit Office , issued in 2015
Risk cases: 8
Federal Human Resources Data
Internal control weaknesses may put mission at risk GAO audited the Enterprise Human Resources Integration payroll data warehose. The American auditors pointed at problems that may impede 'leverage of these data to meet its mission and allow others to make full use' of them. The critical internal contols areas to be improved in this cas are: completeness, accuracy, and validity of information, authorization, documentation, monitoring, results' evaluation.
Full description
General Accountability Office , issued in 2016
Risk cases: 2
Housing in England: overview
Efforts to support housing Even if housebuilding in England has not kept pace with need and there has been a reduction in social rented homes, significant advantages can be enjoyed: an increase in home ownership and in the number of private rented homes. The quality of housing improved in recent years too. The National Audit Office has reviewed critical elements of the housing being one of the government's key priorities. Looking for risks, they found that a potential conflict of objectives can lead to tensions in delivery.
Full description
National Audit Office , issued in 2017
Risk cases: 2
36 results found. Page 1 of 4 next