The effectiveness of Official Development Assistance expenditure
Need of more coordination and transparency The audit of the UK's Official Development Assistance revealed among others: fragmented responsibilities and difficulties in review and reporting. These led to difficulties in assessment of effectiveness of the assistance and of progress in implementing the UK Aid Strategy.
Full description
National Audit Office , issued in 2019
Risk cases: 4
Evaluation of the effectiveness of implementation and compliance with regulatory enactments and the legal framework of the project “E-government Portfolio”
The objective of the audit is to evaluate the effectiveness of implementation and compliance with regulatory enactments and the legal framework of the project “Egovernment Portfolio” of the national ... programme of the European Regional Development Fund (hereinafter: ERDF) of the European Union (hereinafter: EU), “Development and improvement of the infrastructural foundation for electronic governance”. ... ... Funds to absorb but no efficient project methodology? Be prepared for troubles ... Wide list of problems that can be met when more care is received by 'absorb funds' objective than by clear vision what and how can be improved. SAI Latvia's analysis shows how dangerous it can ... be for both effectiveness and financial management.
Full description
State Audit Office of Latvia , issued in 2010
Risk cases: 3
Cyber Attacks: Securing Agencies’ICT Systems
posture of the selected agencies, based on their implementation of the four mandated mitigation strategies and IT general controls. In the government sector, the Australian Signals Directorate (ASD) has ... agencies compliance with the four mandatory ICT security strategies and related controls in the Australian Government Information Security Manual (ISM). The audit also considered the overall ICT security ... Operations Centre response. The audit's focus was, among others, application of top four of the ASD's list of 35 mitigation strategies against cyber intrusions. Contact person: Alex Doyle ... ... Cyber-security strategy needs consistent implementation and periodic reviews ... List of 35 mitigation controls against cyber intrusions are a basic tool of information security strategy of the Australian Government. Top four are: 1. application whitelisting, 2. patching ... application, 3. patching operating systems, 4. minimising administrative privileges. Analysis by the ANAO helps to fill gaps and to direct next steps.
Full description
The Australian National Audit Office , issued in 2014
Risk cases: 3
Audit of the procurement of ICT products with the potential to be standard products
ICT procurement system reviewed SFAO points out what is critical in ICT procurement. Requirements management is extremely important, as well as procurement strategies for relevant product groups. Legal rules should protect investments and support competition, but they can still be insufficient without appropriate reporting - if you want your system to adapt to changes.
Full description
Swiss Federal Audit Office , issued in 2015
Risk cases: 4
State funds spent on development, operation and using of data centres services
The aim of the audit was to scrutinise the management of funds spent on building and operating the national data centre (hereinafter “STC1 data centre”), including the expenditure of selected ... organisational units of the state on buying hosting, server-housing and other related services. The audited period was between 2010 and 2014; where relevant, the preceding period was also scrutinised. Audited ... entities: Ministry of the Interior (“MoI”); Ministry of Finance (“MoF”); STÁTNÍ TISKÁRNA CENIN, state firm (state banknote printing firm, hereinafter “STC” or “the state firm”). The audit was conducted ... ... Risks steming from uncoordinated strategy ... SAI of Czech Republic analysed consequences of failures in strategic IT management at the state level. Lack of coordination and implementation rules reduced practical role of the ministry whose task ... was to guard high quality standards for all crucial IT systems in the state administration. Next consecquences were (among others) risk of uneconomical results of large IT investment and risk of inefficient ... supply of services, as well as opposite results of workforce reduction.
Full description
Supreme Audit Office of Czech Republic , issued in 2015
Risk cases: 7
Whether Disclosure of the Public Sector Data Is Ensured
Strategy more important than declarations Why open data are so dificult to become reality? Lithuania possesses the elements required to disclose data but lacks a strategic approach. The report by SAI Lithuania reviews all critical elements of this problem. Most of them look like a pattern reproduced by other countries. And one important thing: the SAI Lithuania opened their own data - exactly on the day of publication of the audit report!
Full description
National Audit Office of the Republic of Lithuania , issued in 2016
Risk cases: 9
Use of European Union funds in promoting information society
Audit Office is of the opinion that the state is too focussed on financing the IT developments aimed at the state when distributing aid for the implementation of the National Information Society ... has not been transparent and the state’s supervision of the implementation of the projects has been regarded as a formality. ... The National Audit Office audited the use of the aid allocated from the structural funds of the European Union (hereinafter EU aid) in the information technology (IT) area of the state. The National ... Riigikontroll auditeeris Euroopa Liidu struktuurifondidest ehk tõukefondidest eraldatud toetuste (edaspidi ELi toetusraha) kasutamist riigi infotehnoloogia (IT) valdkonnas. Uuriti, kas raha jagamine ... infoühiskonna arendamise eesmärgil on olnud tasakaalustatud ja läbipaistev ning kas toetuste jagamise üle tehakse piisavat järelevalvet. Riigikontrolli hinnangul on riik infoühiskonna arengukava rakendamiseks ... toetuste jagamisel keskendunud liiga riigile suunatud IT-arenduste rahastamisele ning jätnud tagaplaanile ettevõtete konkurentsivõime parandamisele ja kolmandale sektorile suunatud IT arendusprojektide ... Balance needed for success of Information Society Development Plan ... , true suppervision and measurement of progress are listed by the Estonian SAI as next key elements necessary to keep balanced development of strategy for Information Society. ... 50% of aid has been granted primarily for the development of information systems of state agencies, i.e. as much as the other two target groups - business and citizens - put together. Information
Full description
National Audit Office of Estonia , issued in 2012
Risk cases: 2
Audit of the key ICT project federal GEVER programme Federal Chancellery
During the first stage, two new GEVER (electronic records and process management) products were procured in an open WTO tender within the framework of the two-product strategy (federal GEVER WTO ... procurement project). CHF 1.6 million was spent on these. The departments and Federal Chancellery (departments/FCh) had to choose one of the two products within three months of the contract being awarded. ... ... Advanced process management system's cost-effectiveness and deadlines at risk ... Ever since 1990, sequential controls and file management have been part of the Federal Administration's IT landscape (GEVER business administration). Significant obstacles have to be overcome ... in order to ensure the successful creation and introduction of GEVER. Previous efforts did not have any widespread success and led to a diverse GEVER landscape. The federal GEVER project has now laid ... the foundations for simplification and centralisation.
Full description
Swiss Federal Audit Office , issued in 2015
Risk cases: 2
Use of consultants and temporary staff
New skills needed in a longer term UK NAO: Used well, consultants and temporary staff can be an important source of specialist skills and capabilities that are uneconomic for departments to maintain in their permanent staff. Since 2009-10, the government has used spending controls to reduce its use of consultants and temporary staff, and by 2014-15 spending had fallen by £1.5 billion. However, spending has increased by between £400 million and £600 million since 2011-12, suggesting that this was more of a short-term reduction than a sustainable strategy. In the longer term, departments will need to develop workforce, skills and capacity plans to reduce their dependence on external skills. They will need to improve their strategic workforce planning to determine where they can deploy existing staff, where they need to recruit, and where they need to engage temporary resources. Without this, departments cannot demonstrate that they are achieving value for money from the use of consultants and temporary staff.
Full description
National Audit Office , issued in 2016
Risk cases: 7
Information Technology Cost Estimation Agencies Need to Address Significant Weakness in Policies and Practices
and agencies have appropriately implement costestimating policies an procedures(four caracteristics of a reliable cost estimation: comprehensive, well-documented, accurate, credible). ... To estimate reliable cost for the sucess of an IT program by providing the basis for the informed decision making and realistic budget information. To assess the extent to which selected departments ... IT cost estimation ... , lack of adequacy and inadequate implementation. ... Check out what may go wrong with the information technology cost estimation. Results of the US GAO audit can help to identify high risk areas: comprehensiveness of estimations, their documentation
Full description
General Accountability Office , issued in 2012
Risk cases: 4
44 results found. Page 1 of 5 next