Reports Search Reports Spatial Search Risk-cases Search Risk-cases Graph Traversal
30 results found in 13 ms Page 1 of 3
Digital transformation in government
Support exemplars, provide consistent guidance... and do not lose focus As the NAO states: Government faces significant challenges in providing public services. While many government services are now available online, public administration is struggling to manage more complicated programmes and to improve the complex systems and processes that support public services.
Full description
National Audit Office , issued in 2017
Risk cases: 4
The Actıvıtıes Carrıed out wıthın the Framework of e-Transformatıon Turkey Project
'e-Transformation Turkey' Project Turkish SAI report presents a checklist of issues, which were spotted during the large scale e-Government transformation.
Full description
Turkish Court of Accounts , issued in 2006
Risk cases: 4
The Public Web Sites During a Period of Transmission to e-Government
Websites of e-Transformation Turkish auditors bring back their audit of 2006, in which they, among others reveiwed public websites during a period of transmission to e-Governmentbasics of the e-Transformation project.
Full description
Turkish Court of Accounts , issued in 2006
Risk cases: 6
Use of consultants and temporary staff
New skills needed in a longer term UK NAO: Used well, consultants and temporary staff can be an important source of specialist skills and capabilities that are uneconomic for departments to maintain in their permanent staff. Since 2009-10, the government has used spending controls to reduce its use of consultants and temporary staff, and by 2014-15 spending had fallen by £1.5 billion. However, spending has increased by between £400 million and £600 million since 2011-12, suggesting that this was more of a short-term reduction than a sustainable strategy. In the longer term, departments will need to develop workforce, skills and capacity plans to reduce their dependence on external skills. They will need to improve their strategic workforce planning to determine where they can deploy existing staff, where they need to recruit, and where they need to engage temporary resources. Without this, departments cannot demonstrate that they are achieving value for money from the use of consultants and temporary staff.
Full description
National Audit Office , issued in 2016
Risk cases: 7
Staff scheduling in government institutions
Scheduling irregular hours work Danish Rigsrevisionen shows in their study problems with staff scheduling in government institutions where employees are required to work irregular hours. Optimized staff scheduling contributed to reducing payroll costs. On the other hand, problems with rearrangement of work, recording working hours, optimisation of staffing levels and analysis of overtime triggers - add up to high costs of workforce. IT is not always used as ally either.
Full description
National Audit Office of Denmark , issued in 2015
Risk cases: 5
FEMA Needs to Address Management Weaknesses to Improve Its Systems
Controls in emergency management GAO audited the agency of the Department of Homeland Security, responsible for federal efforts to mitigate, respond to, and recover from disasters. American auditors recommend that the agency fully define its investment board’s roles and responsibilities and procedures for selecting and overseeing investments, update its strategic plan and complete plans for IT modernization, and establish time frames for completing workforce planning efforts. The agency should also establish policies and guidance for implementing key IT management controls.
Full description
General Accountability Office , issued in 2016
Risk cases: 4
State funds spent on development, operation and using of data centres services
The aim of the audit was to scrutinise the management of funds spent on building and operating the national data centre (hereinafter “STC1 data centre”), including the expenditure of selected ... organisational units of the state on buying hosting, server-housing and other related services. The audited period was between 2010 and 2014; where relevant, the preceding period was also scrutinised. Audited ... entities: Ministry of the Interior (“MoI”); Ministry of Finance (“MoF”); STÁTNÍ TISKÁRNA CENIN, state firm (state banknote printing firm, hereinafter “STC” or “the state firm”). The audit was conducted ... ... Risks steming from uncoordinated strategy ... supply of services, as well as opposite results of workforce reduction. ... SAI of Czech Republic analysed consequences of failures in strategic IT management at the state level. Lack of coordination and implementation rules reduced practical role of the ministry whose task ... was to guard high quality standards for all crucial IT systems in the state administration. Next consecquences were (among others) risk of uneconomical results of large IT investment and risk of inefficient
Full description
Supreme Audit Office of Czech Republic , issued in 2015
Risk cases: 7
Central government staff costs
Results of staff reductions The British NAO found that departments had significantly reduced numbers of their civil servants and of course salary costs at the same time. But they reduced staff numbers mainly by minimising recruitment, and the age profile of the civil service has changed. NAO pays a lot attention to what effect this has had on the future pipeline of talent and skills. It reminds also that the departments need long-term operating models to work efficiently with the staff reduced.
Full description
National Audit Office , issued in 2015
Risk cases: 5
Improving government’s planning and spending framework
Value for money vs. short-term planning NAO reviewed the UK government's progress in improving their planning and spending framework. The auditors found that the complex structure and lack of longer term perspective in planning form a significant obstacle to fully benefit from the framework.
Full description
National Audit Office , issued in 2018
Risk cases: 7
Identifying and meeting central government's skills requirements
Start with well managed responsibilities UK Departments have invested heavily in skills development. Government estimates that expenditure on formal training, including salary costs of departmental learning and development staff, was £275 million in 2009-10. NAO identified weaknesses of the system which start with devolved responsibilities, lead to: weak data, mis-profiled trainings, doubtful personal decisions, lack of well-targeted evaluation - and finish at more expensive buying-in and retaining key skills...
Full description
National Audit Office , issued in 2011
Risk cases: 6
30 results found. Page 1 of 3 next