Telecommunication solutions in the Institutions of Bosnia and Herzegovina
Strategies need systemic analysis Bosnia and Herzegovina state auditors analysed a set of strategies related to telecom solutions across the BiH administration. They found that lack of a systemic approach and of analytical support reduced abilities of the organistations to make full use of the up-to-date technologies.
Full description
Strategies need systemic analysis Bosnia and Herzegovina state auditors analysed a set of strategies related to telecom solutions across the BiH administration. They found that lack of a systemic approach and of analytical support reduced abilities of the organistations to make full use of the up-to-date technologies.
Full description
Audit Office of the Institutions of Bosnia and Herzegovina
, issued in 2014
Risk cases: 3
VA ACQUISITION MANAGEMENT: Supply Chain Management and COVID-19 Response
Pandemic points up weaknesses of procurement solutions US Department of Veterans Affairs acquires hundreds of millions of dollars-worth of medical supplies each year. The Medical-Surgical Prime Vendor-Next Generation (MSPV-NG) is one of its key initiatives to modrnize its processes. GAO auditor pointed in their previous audits that the approach lacked an effective medical supply procurement strategy, clinician involvement, and reliable data systems. In time of the pandemic, the problem seems even more difficult to deal with.
Full description
Pandemic points up weaknesses of procurement solutions US Department of Veterans Affairs acquires hundreds of millions of dollars-worth of medical supplies each year. The Medical-Surgical Prime Vendor-Next Generation (MSPV-NG) is one of its key initiatives to modrnize its processes. GAO auditor pointed in their previous audits that the approach lacked an effective medical supply procurement strategy, clinician involvement, and reliable data systems. In time of the pandemic, the problem seems even more difficult to deal with.
Full description
US Government Accountability Office
, issued in 2019
Risk cases: 4
The rural broadband programme
Intervention in a noncompetitive market The British NAO's audit report of 2013 concerns ambitious yet delayed UK government programme, which objective was to have the best superfast broadband network in Europe by 2015. The report focuses on one of the programme's main problems: rural areas, where commercial providers had no plans to invest, because of lower returns.
Full description
Intervention in a noncompetitive market The British NAO's audit report of 2013 concerns ambitious yet delayed UK government programme, which objective was to have the best superfast broadband network in Europe by 2015. The report focuses on one of the programme's main problems: rural areas, where commercial providers had no plans to invest, because of lower returns.
Full description
National Audit Office
, issued in 2013
Risk cases: 7