Reports Search Reports Spatial Search Risk-cases Search Risk-cases Graph Traversal
18 results found in 10 ms Page 1 of 2
Has Public Administration Used All Opportunities for Efficient Management of ICT Infrastructure?
Efficient Management of ICT Infrastructure Centralised management of ICT services and infrastructure would allow the institutions to optimise in long run their resources – financial, human, material and technical. However, we observed during the audit that the move towards ICT centralisation and single data centres has ceased. The different ministries and even the institutions subordinated to the same ministry do not cooperate sufficiently with each other regarding the ICT management, maintenance, and infrastructure placement. They rather choose to maintain their own, sometimes even several, data centres.
Full description
State Audit Office of the Republic of Latvia , issued in 2019
Risk cases: 3
THE CYBER SECURITY ENVIRONMENT IN LITHUANIA
) cyber security is ensured in public establishments. During the audit, the SAI Lithuania analysed current regulation, strategic planning and management practices in the field of cyber security ... and electronic information security as well as the funds allocated and used in this area. The SAI evaluated whether the cyber security and electronic information security objectives detailed in planning documents ... The purpose of the audit was to assess whether cyber security is being ensured in Lithuania. In view of this goal, we assessed whether: (1) an effective cyber security system has been set up; (2 ... ... Cyber-security is much more than preventing incidents ... SAI Lithuania determined that the issue of ensuring and increasing cyber security and resilience has not been effectively addressed at the national level. The focus has primarily been on reacting ... to and preventing incidents in cyber space, which means that traditional issues related to electronic information security (confidentiality, integrity, accessibility) have been neglected, and from 2015, not enough ... attention has been paid to development, legislation, improvement of organisational structure, etc. in this field.
Full description
National Audit Office of the Republic of Lithuania , issued in 2015
Risk cases: 6
The management of the State Property and Funds while Information Systems Building for the Ministry of Defence
The aim of the audit was to examine management during process of extension and modernization of the current information systems and at building of new information systems for the needs ... in this connection. The stationary ICT systems are determined to support management of the Ministry of Defence in period of peace. They are also supposed as a tool of crisis management. The auditing operation covered ... of the Ministry of Defence or the Army of the Czech Republic. Operating of information systems is inseparably linked with the communication infrastructure, thus the technological shift to ICT was reviewed also ... ... Information systems not balanced with infrastructure ... Both organizational changes and inflexibility produce unbalanced plans which cause deiscrepancies between IS and infrastructure.
Full description
Supreme Audit Office , issued in 2005
Risk cases: 2
Information Technology Cost Estimation Agencies Need to Address Significant Weakness in Policies and Practices
and agencies have appropriately implement costestimating policies an procedures(four caracteristics of a reliable cost estimation: comprehensive, well-documented, accurate, credible). ... To estimate reliable cost for the sucess of an IT program by providing the basis for the informed decision making and realistic budget information. To assess the extent to which selected departments ... IT cost estimation ... Check out what may go wrong with the information technology cost estimation. Results of the US GAO audit can help to identify high risk areas: comprehensiveness of estimations, their documentation ... , lack of adequacy and inadequate implementation.
Full description
General Accountability Office , issued in 2012
Risk cases: 4
VETERANS’ HEALTH CARE - Preliminary Observations on VHA’s Claims Processing Delays and Efforts to Improve the Timeliness of Payments to Community Providers
in geographic location, performance, and workload); reviewed VHA documents and 156 claims from those 4 locations; and interviewed officials from VHA, Medicare, TRICARE, and selected community providers and state ... Due to increases in expenditures and utilization of VA care in the community services in recent years, VHA has had difficulty processing claims in a timely manner. In planning to consolidate its ... existing VA care in the community programs, as required by law, the agency said it will examine strategies for improving the timeliness and accuracy of its payments to community providers.<br ... Data processing hold back by technology limitation, workload and administrative burden ... US GAO analyzed all factors of slower processing and user unfriendliness that occur sometimes to the veterans healthcare. The main focus is data processing - and it has been proved that it can ... be failing not only because of technology, but also because of work-process design, staff and organisation.
Full description
General Accountability Office , issued in 2016
Risk cases: 6
Building and Implementing the Phoenix Pay System
Expensive IT project became a failure Phoenix project (development of states pay system) was an incomprehensible failure of project management and oversight. Phoenix executives prioritized certain aspects, such as schedule and budget, over other critical ones, such as functionality and security. Phoenix executives did not understand the importance of warnings that the Miramichi Pay Centre, departments and agencies, and the new system were not ready. They did not provide complete and accurate information to deputy ministers and associate deputy ministers of departments and agencies, including the Deputy Minister of Public Services and Procurement, when briefing them on Phoenix readiness for implementation.
Full description
Office of theAuditor Generalof Canada , issued in 2018
Risk cases: 3
The Shared Services Centre
The necessary environment for the efficient management of the Shared Service Center is lacking The department's administration of the Shared Services Centre (SSC) has been effective for sharing resources between the departments and delivering selected back-office services to a small client base. However, the governance arrangements established to oversight the SSC have not positioned it well for the future and the departments have not yet determined if the arrangement is efficient and resulting in savings. ANAO found instances where the advisory board of SSC was not consulted or involved in decisions relating to the strategic direction, financial arrangements and expenditure priorities. Information reported to the board did not focus on areas of strategic importance and the quality and completeness of this information could be improved. The mechanisms established for setting out responsibilities and obligations and ensuring transparency for services delivered by the SSC was weak. Service standards and levels were not fixed and can change. The delineation of responsibilities between the SSC and its clients was not clear and there was no commitment by the SSC to certify the quality of its control framework.
Full description
The Australian National Audit Office , issued in 2016
Risk cases: 2
Australian Taxation Office: Administration of Australian Business Number Registrations
More elligibility and data integrity needed The Australian Business Number (ABN) and Australian Business Register initiatives were implemented as part of theGovernment's comprehensive reform of the taxation system in 2000. Their introduction involved challenging issues of technology and governance , including the imperative to process and register significant numbers of applications in a short time. Overall, the Australian SAI concluded that the ABN registration process is operating effectively. However, matters relating to the eligibility of some ABN applicants need to be reviewed. Further, some data integrity issues remain outstanding.
Full description
The Australian National Audit Office , issued in 2003
Risk cases: 3
Open Data Trend Report 2015
How to activate the open data policy The Dutch SAI looks for ways to improve open data practice in the Netherlands. They point at experience of two leading countries: UK and US, and advise to: prepare a concrete action plan, to increase number of mandatory published data, to develop government-wide data inventory and to put open data to work.
Full description
Netherlands Court of Audits , issued in 2015
Risk cases: 4
Data security and positions with access to confidential information
This government wide audit on information security and positions with access to confidential information has been performed at all ministries ans for each ministry also at one of the agencies ... . The 2007 Civil Service Data Information Security Decree (in Dutch: VIR 2007) is the legal foundation of the first part of this audit (data security). The Security Screening Act (in Dutch: WVO ... ) is the foundation of the second part (positions with access to confidential information). Only four of the organizations we have audited show an acceptible level of compliance with the 2007 Civil Service Data ... ... Shortcomings in information security and in positions with access to confidential information ... Surprising weaknesses were revealed by the NCA in its Government-wide operational audit performed as part of the 2011 audit into the state of central government accounts: Poor quality of data ... protection policy and poor protection of information systems. Also, non vetted positions with access to confidential information.
Full description
Netherlands Court of Audits , issued in 2012
Risk cases: 3
18 results found. Page 1 of 2 next