Identifying and meeting central government's skills requirements
Start with well managed responsibilities UK Departments have invested heavily in skills development. Government estimates that expenditure on formal training, including salary costs of departmental learning and development staff, was £275 million in 2009-10. NAO identified weaknesses of the system which start with devolved responsibilities, lead to: weak data, mis-profiled trainings, doubtful personal decisions, lack of well-targeted evaluation - and finish at more expensive buying-in and retaining key skills...
Full description
National Audit Office , issued in 2011
Risk cases: 6
Building and Implementing the Phoenix Pay System
Expensive IT project became a failure Phoenix project (development of states pay system) was an incomprehensible failure of project management and oversight. Phoenix executives prioritized certain aspects, such as schedule and budget, over other critical ones, such as functionality and security. Phoenix executives did not understand the importance of warnings that the Miramichi Pay Centre, departments and agencies, and the new system were not ready. They did not provide complete and accurate information to deputy ministers and associate deputy ministers of departments and agencies, including the Deputy Minister of Public Services and Procurement, when briefing them on Phoenix readiness for implementation.
Full description
Office of theAuditor Generalof Canada , issued in 2018
Risk cases: 3
Central government staff costs
Results of staff reductions The British NAO found that departments had significantly reduced numbers of their civil servants and of course salary costs at the same time. But they reduced staff numbers mainly by minimising recruitment, and the age profile of the civil service has changed. NAO pays a lot attention to what effect this has had on the future pipeline of talent and skills. It reminds also that the departments need long-term operating models to work efficiently with the staff reduced.
Full description
National Audit Office , issued in 2015
Risk cases: 5
Has Public Administration Used All Opportunities for Efficient Management of ICT Infrastructure?
Efficient Management of ICT Infrastructure Centralised management of ICT services and infrastructure would allow the institutions to optimise in long run their resources – financial, human, material and technical. However, we observed during the audit that the move towards ICT centralisation and single data centres has ceased. The different ministries and even the institutions subordinated to the same ministry do not cooperate sufficiently with each other regarding the ICT management, maintenance, and infrastructure placement. They rather choose to maintain their own, sometimes even several, data centres.
Full description
State Audit Office of the Republic of Latvia , issued in 2019
Risk cases: 3
The effectiveness of Official Development Assistance expenditure
Need of more coordination and transparency The audit of the UK's Official Development Assistance revealed among others: fragmented responsibilities and difficulties in review and reporting. These led to difficulties in assessment of effectiveness of the assistance and of progress in implementing the UK Aid Strategy.
Full description
National Audit Office , issued in 2019
Risk cases: 4
Australian Taxation Office: Administration of Australian Business Number Registrations
More elligibility and data integrity needed The Australian Business Number (ABN) and Australian Business Register initiatives were implemented as part of theGovernment's comprehensive reform of the taxation system in 2000. Their introduction involved challenging issues of technology and governance , including the imperative to process and register significant numbers of applications in a short time. Overall, the Australian SAI concluded that the ABN registration process is operating effectively. However, matters relating to the eligibility of some ABN applicants need to be reviewed. Further, some data integrity issues remain outstanding.
Full description
The Australian National Audit Office , issued in 2003