Reports Search Reports Spatial Search Risk-cases Search Risk-cases Graph Traversal
26 results found in 9 ms Page 1 of 3
The Board of Audit and Inspection (BAI) conducted an audit on the information systems in the area of service delivery to improve the system’s efficiency and convenience.
Korea was recognized as an Information Technology (IT) powerhouse by the international community of the UN in 2010. Such an achievement is attributable to the significant investments that the Korean ... government has commissioned toward improving the country’s information infrastructure within a short period of time.<br/> The government is investing 1 trillion won every year in an e-government project ... for citizens in the welfare and employment sectors by utilizing the renewed information infrastructure.<br/> However, the information system of some government ministries proved to have overlapping functions ... Enormous IT investments require tremendous coordination ... Korean government is investing 1 trillion won in e-government projectsevery year. Thus, the country has earned a reputation for the IT powerhouse. Apart from undeniable advantages, the huge scale ... and the speed, the information technologies are implemented with, cause some problems to be tackled. The SAI Korea turns special atention to two of them: overlapping functionalities and interconnectivity issues.
Full description
Board of Audit and Inspection of Korea , issued in 2011
Risk cases: 3
OMB and Agencies Need to Focus Continued Attention on Implementing Reform Law
How to invest efficiently in IT IT investments are large and growing position in annual budgets. Historically, they have frequently failed, incurred cost overruns and schedule slippages, or contributed little to mission-related outcomes. GAO recommendations focus on the oversight and execution of the data center consolidation initiative, the accuracy and reliability of the IT Dashboard, and incremental development policies.
Full description
General Accountability Office , issued in 2016
Risk cases: 3
Electronic Health Records - VA Needs to Identify and Report Existing System Costs
Difficulties after 30 years of decentralized development The US Department of Veterans Affairs provides health care services to approximately 9 million veterans and their families. However, the IT system they use is more than 30 years old, is costly to maintain, and does not fully support exchanging health data. The US GAO, analyzed the system's modenization plans and found serious problems with definition and cost estimation.
Full description
US Government Accountability Office , issued in 2019
Risk cases: 3
Ministry of Education realized corrective measures incorrectly
, and high schools, as well as some other educational facilities. (See the complete list of chosen schools enclosed to the audit report.). ... The audited bodies were Ministry of Education (ME), Ministry of Informatics (MI), Institute for Educational Information, regional authorities of Liberec and Plzeň, and 42 chosen primary, secondary ... ... Educational project managed ineffectively ... Several problems - from documentation to ineffectiveness - in designing and financing were found by the Czech SAI in a government program: the Funding Conception for Communication Services at Schools.
Full description
Supreme Audit Office , issued in 2007
Risk cases: 2
Online fraud
Uneven response to online fraud This type of fraud can affect everyone, but yet it is not a strategic priority for local police forces and the response from industry is uneven. UK NAO underlines: For too long, as a low-value but high-volume crime, online fraud has been overlooked by government, law enforcement and industry. It is a crime that can affect everyone. Fraud is now the most commonly experienced crime in England and Wales, is growing rapidly and demands an urgent response. Yet fraud is not a strategic priority for local police forces, and the response from industry is uneven.
Full description
National Audit Office , issued in 2017
Risk cases: 6
Conflicts of interest
First, recognise the conflicts of interest are a real risk the British NAO gathered a significant amount of intelligence on conflicts, particularly in the health and education sectors. These are areas of government where services are increasingly commissioned and delivered by parties at arm’s-length to departments. Conflicts of interest can occur naturally as a product of the way a system is designed and most often arise from operational situations.
Full description
National Audit Office , issued in 2015
Risk cases: 8
Improved Planning and Performance Measures Are Needed to Help Ensure Successful Technology Modernization
Massive modernization effort needs coordination Social security issues can touch lives of many. Information technology in this area are increasingly costly and difficult to maintain. GAO is recommending to develop comprehensive metrics to effectively gauge modernization progress; complete comprehensive strategic planning, including its enterprise architecture; and define the new roles and responsibilities to help ensure effective oversight.
Full description
General Accountability Office , issued in 2012
Risk cases: 3
Federal Human Resources Data
Internal control weaknesses may put mission at risk GAO audited the Enterprise Human Resources Integration payroll data warehose. The American auditors pointed at problems that may impede 'leverage of these data to meet its mission and allow others to make full use' of them. The critical internal contols areas to be improved in this cas are: completeness, accuracy, and validity of information, authorization, documentation, monitoring, results' evaluation.
Full description
General Accountability Office , issued in 2016
Risk cases: 2
Management and implementation of 1BestariNet
and secondary public schools in Malaysia are equipped with high-speed 4G Internet access and a virtual learning platform, providing high-speed internet connectivity and access to a world-class Integrated Learning ... 1BestariNet Service Project (1BestariNet) is an initiative undertaken by the Malaysian Ministry of Education (MOE) to replace and enhance ICT connectivity in schools. It is an enhancement ... to the SchoolNet service which terminated on 31 December 2010 with emphasis on end-to-end solutions (E2E) network services together with Virtual Learning Environment (VLE). Under this project, 10,000 primary ... ... To answer big risks in IT systems development you need all levels of organisation ... Audit of 1BestariNet is presented by the Malaysian National Audit Department together with other IT projects reviewed. A result is this concise and instructive list of lessons learnt and failures ... to be avoided. To maximize performance and minimize vendor lock-in you need a lot of concerted effort by top and line management, as well as users ready to work with new tools.
Full description
National Audit Department of Malaysia , issued in 2013
Risk cases: 4
The Shared Services Centre
The necessary environment for the efficient management of the Shared Service Center is lacking The department's administration of the Shared Services Centre (SSC) has been effective for sharing resources between the departments and delivering selected back-office services to a small client base. However, the governance arrangements established to oversight the SSC have not positioned it well for the future and the departments have not yet determined if the arrangement is efficient and resulting in savings. ANAO found instances where the advisory board of SSC was not consulted or involved in decisions relating to the strategic direction, financial arrangements and expenditure priorities. Information reported to the board did not focus on areas of strategic importance and the quality and completeness of this information could be improved. The mechanisms established for setting out responsibilities and obligations and ensuring transparency for services delivered by the SSC was weak. Service standards and levels were not fixed and can change. The delineation of responsibilities between the SSC and its clients was not clear and there was no commitment by the SSC to certify the quality of its control framework.
Full description
The Australian National Audit Office , issued in 2016
Risk cases: 2
26 results found. Page 1 of 3 next