Preparations and realization of the State A-levels
The aim of the audit was to scrutinise the utilisation of the state budget and EU budget funds that had been spent on preparing and implementing the State A-levels examinations. The auditing ... of the auditing operation were also scrutinized. Among the audited bodies were the Ministry of Education, the Education Result Survey Centre, and the National Institute for Further Education. The auditing operation ... operation was performed from May to November 2011. The audited period extended from January 1, 2005, to June 30, 2011; where relevant, the data from the previous period and the period until the end ... ... Begin with good strategy ... Analyzing problems of state examinations system, Czech Republic SAI found that commonplace strategy effected in shortsighted planning, poor procurement and disadvantageous contracting.
Full description
Supreme Audit Office of Czech Republic , issued in 2011
Risk cases: 4
Effectiveness of internal controls in the protection of personal data in national databases
The NAO analysed seven national databases in order to find out how the legitimate use of personal data is ensured. In accordance with the Personal Data Protection Act, the agencies who run databases ... must ensure that personal data is protected from abuse. The information system of the database must function appropriately, incl. be reliable and safe. Log files must be retained of all instances ... of viewing, amending, deleting, transmitting of data, etc. These files must allow ex-post determination of who did what, why, when and using which data. In its audit the NAO focused on the functioning ... ... Basic controls analysis can fail in data protection ... Estonian SAI analyzed personal data safety. Main finding were: poor log analysis and unprotected data.
Full description
National Audit Office of Estonia , issued in 2008
Risk cases: 2
Evaluation of the effectiveness of implementation and compliance with regulatory enactments and the legal framework of the project “E-government Portfolio”
The objective of the audit is to evaluate the effectiveness of implementation and compliance with regulatory enactments and the legal framework of the project “Egovernment Portfolio” of the national ... programme of the European Regional Development Fund (hereinafter: ERDF) of the European Union (hereinafter: EU), “Development and improvement of the infrastructural foundation for electronic governance”. ... ... Funds to absorb but no efficient project methodology? Be prepared for troubles ... Wide list of problems that can be met when more care is received by 'absorb funds' objective than by clear vision what and how can be improved. SAI Latvia's analysis shows how dangerous it can ... be for both effectiveness and financial management.
Full description
State Audit Office of Latvia , issued in 2010
Risk cases: 3
THE CYBER SECURITY ENVIRONMENT IN LITHUANIA
The purpose of the audit was to assess whether cyber security is being ensured in Lithuania. In view of this goal, we assessed whether: (1) an effective cyber security system has been set up; (2 ... ) cyber security is ensured in public establishments. During the audit, the SAI Lithuania analysed current regulation, strategic planning and management practices in the field of cyber security ... and electronic information security as well as the funds allocated and used in this area. The SAI evaluated whether the cyber security and electronic information security objectives detailed in planning documents ... ... Cyber-security is much more than preventing incidents ... SAI Lithuania determined that the issue of ensuring and increasing cyber security and resilience has not been effectively addressed at the national level. The focus has primarily been on reacting ... to and preventing incidents in cyber space, which means that traditional issues related to electronic information security (confidentiality, integrity, accessibility) have been neglected, and from 2015, not enough ... attention has been paid to development, legislation, improvement of organisational structure, etc. in this field.
Full description
National Audit Office of the Republic of Lithuania , issued in 2015
Risk cases: 6
Management and implementation of 1BestariNet
Solution. 1BestariNet serves as a major catalyst for internet penetration in Malaysia as well as the projected increase in national income. AUDIT OBJECTIVE: The audit was carried out to evaluate whether ... 1BestariNet Service Project (1BestariNet) is an initiative undertaken by the Malaysian Ministry of Education (MOE) to replace and enhance ICT connectivity in schools. It is an enhancement ... to the SchoolNet service which terminated on 31 December 2010 with emphasis on end-to-end solutions (E2E) network services together with Virtual Learning Environment (VLE). Under this project, 10,000 primary ... ... To answer big risks in IT systems development you need all levels of organisation ... Audit of 1BestariNet is presented by the Malaysian National Audit Department together with other IT projects reviewed. A result is this concise and instructive list of lessons learnt and failures ... to be avoided. To maximize performance and minimize vendor lock-in you need a lot of concerted effort by top and line management, as well as users ready to work with new tools.
Full description
National Audit Department of Malaysia , issued in 2013
Risk cases: 4
Data security and positions with access to confidential information
) is the foundation of the second part (positions with access to confidential information). Only four of the organizations we have audited show an acceptible level of compliance with the 2007 Civil Service Data ... Information Security Decree, eight organizations show scope for improvement and nine organizations show an unsatisfactory level of compliance with the 2007 Civil Service Data Information Security Decree. When ... This government wide audit on information security and positions with access to confidential information has been performed at all ministries ans for each ministry also at one of the agencies ... ... Shortcomings in information security and in positions with access to confidential information ... Surprising weaknesses were revealed by the NCA in its Government-wide operational audit performed as part of the 2011 audit into the state of central government accounts: Poor quality of data ... protection policy and poor protection of information systems. Also, non vetted positions with access to confidential information.
Full description
Netherlands Court of Audits , issued in 2012
Risk cases: 3
The protection of research data at the Danish universities
The protection of research data at the Danish universities It is Rigsrevisionen’s assessment that the five largest universities are not adequately protecting their research data against unknown IT equipment. As a result, foreign actors may relatively easy gain unauthorized access to the universities’ research data.This is not considered satisfactory by Rigsrevisionen. The study shows that the five largest universities have defined guidelines for researchers’ use of software and hardware centrally, but that they have failed to centralise efforts to maintain a satisfactory level of security for research data. This is due mainly to the fact that, at some universities, researchers are allowed to bring their own devices,and at all the universities, researchers are allowed to have local administrator privileges, which gives them access to install software. Additionally, all five universities know of incidents where unknown hardware has been connected to their network.
Full description
National Audit Office of Denmark , issued in 2018
Risk cases: 3
The Shared Services Centre
The necessary environment for the efficient management of the Shared Service Center is lacking The department's administration of the Shared Services Centre (SSC) has been effective for sharing resources between the departments and delivering selected back-office services to a small client base. However, the governance arrangements established to oversight the SSC have not positioned it well for the future and the departments have not yet determined if the arrangement is efficient and resulting in savings. ANAO found instances where the advisory board of SSC was not consulted or involved in decisions relating to the strategic direction, financial arrangements and expenditure priorities. Information reported to the board did not focus on areas of strategic importance and the quality and completeness of this information could be improved. The mechanisms established for setting out responsibilities and obligations and ensuring transparency for services delivered by the SSC was weak. Service standards and levels were not fixed and can change. The delineation of responsibilities between the SSC and its clients was not clear and there was no commitment by the SSC to certify the quality of its control framework.
Full description
The Australian National Audit Office , issued in 2016
Risk cases: 2
The effectiveness of Official Development Assistance expenditure
Need of more coordination and transparency The audit of the UK's Official Development Assistance revealed among others: fragmented responsibilities and difficulties in review and reporting. These led to difficulties in assessment of effectiveness of the assistance and of progress in implementing the UK Aid Strategy.
Full description
National Audit Office , issued in 2019
Risk cases: 4
Whether Disclosure of the Public Sector Data Is Ensured
Strategy more important than declarations Why open data are so dificult to become reality? Lithuania possesses the elements required to disclose data but lacks a strategic approach. The report by SAI Lithuania reviews all critical elements of this problem. Most of them look like a pattern reproduced by other countries. And one important thing: the SAI Lithuania opened their own data - exactly on the day of publication of the audit report!
Full description
National Audit Office of the Republic of Lithuania , issued in 2016
Risk cases: 9
28 results found. Page 1 of 3 next