Coordinated Audit on Information Technology Governance
IT governance needs awareness and SAIs' support The OLACEFS auditors found that the greatest challenge for the SAIs is to raise the awareness of the audit institutions about the importance of IT governance and the benefits that could be obtained by improving its degree of maturity. The audit was conducted by 11 SAIs and coordinated by TCU of Brasil. They concluded: 'It is important, even urgent, to invest resources to implement or enhance: the IT committees; the IT planning process; strategic IT planning; monitoring the IT contracting process; the business continuity plan; the designation of a responsible person or unit to manage security information; a risk management process; an asset inventory process; an information security committee; and a policy for access control.'
Full description
IT governance needs awareness and SAIs' support The OLACEFS auditors found that the greatest challenge for the SAIs is to raise the awareness of the audit institutions about the importance of IT governance and the benefits that could be obtained by improving its degree of maturity. The audit was conducted by 11 SAIs and coordinated by TCU of Brasil. They concluded: 'It is important, even urgent, to invest resources to implement or enhance: the IT committees; the IT planning process; strategic IT planning; monitoring the IT contracting process; the business continuity plan; the designation of a responsible person or unit to manage security information; a risk management process; an asset inventory process; an information security committee; and a policy for access control.'
Full description
Risk cases: 5
Audit on the broadband internet infrastructure access
of assumed financing was contracted, namely PLN 3.9 billion. By the end of 2015, Poland should complete the investment and account for the expenses. According to NIK there is a risk that the infrastructure ... Poland has been granted over PLN 4 billion from the European Regional Development Fund to build the broadband internet access infrastructure. As part of three operational programmes 90 percent ... construction will not be completed by the deadline and the EU funds may not be used to the full. ... ... Simpler regulations and better supervision needed ... Polish SAI audited a project, which aim had been to develop broadband internet network across the country. They revealed that legal obstacles, idleness and lack of supervision were the main causes ... of delays. Some of the projects are in danger of not being completed on time and some of the EU funds may not be fully used.
Full description
of assumed financing was contracted, namely PLN 3.9 billion. By the end of 2015, Poland should complete the investment and account for the expenses. According to NIK there is a risk that the infrastructure ... Poland has been granted over PLN 4 billion from the European Regional Development Fund to build the broadband internet access infrastructure. As part of three operational programmes 90 percent ... construction will not be completed by the deadline and the EU funds may not be used to the full. ... ... Simpler regulations and better supervision needed ... Polish SAI audited a project, which aim had been to develop broadband internet network across the country. They revealed that legal obstacles, idleness and lack of supervision were the main causes ... of delays. Some of the projects are in danger of not being completed on time and some of the EU funds may not be fully used.
Full description
Supreme Audit Office of Poland
, issued in 2015
Risk cases: 2
Audit of the key ICT project federal GEVER programme Federal Chancellery
procurement project). CHF 1.6 million was spent on these. The departments and Federal Chancellery (departments/FCh) had to choose one of the two products within three months of the contract being awarded. ... During the first stage, two new GEVER (electronic records and process management) products were procured in an open WTO tender within the framework of the two-product strategy (federal GEVER WTO ... ... Advanced process management system's cost-effectiveness and deadlines at risk ... Ever since 1990, sequential controls and file management have been part of the Federal Administration's IT landscape (GEVER business administration). Significant obstacles have to be overcome ... in order to ensure the successful creation and introduction of GEVER. Previous efforts did not have any widespread success and led to a diverse GEVER landscape. The federal GEVER project has now laid ... the foundations for simplification and centralisation.
Full description
procurement project). CHF 1.6 million was spent on these. The departments and Federal Chancellery (departments/FCh) had to choose one of the two products within three months of the contract being awarded. ... During the first stage, two new GEVER (electronic records and process management) products were procured in an open WTO tender within the framework of the two-product strategy (federal GEVER WTO ... ... Advanced process management system's cost-effectiveness and deadlines at risk ... Ever since 1990, sequential controls and file management have been part of the Federal Administration's IT landscape (GEVER business administration). Significant obstacles have to be overcome ... in order to ensure the successful creation and introduction of GEVER. Previous efforts did not have any widespread success and led to a diverse GEVER landscape. The federal GEVER project has now laid ... the foundations for simplification and centralisation.
Full description
Swiss Federal Audit Office
, issued in 2015
Risk cases: 2
State funds spent on development, operation and using of data centres services
The aim of the audit was to scrutinise the management of funds spent on building and operating the national data centre (hereinafter “STC1 data centre”), including the expenditure of selected ... organisational units of the state on buying hosting, server-housing and other related services. The audited period was between 2010 and 2014; where relevant, the preceding period was also scrutinised. Audited ... entities: Ministry of the Interior (“MoI”); Ministry of Finance (“MoF”); STÁTNÍ TISKÁRNA CENIN, state firm (state banknote printing firm, hereinafter “STC” or “the state firm”). The audit was conducted ... ... Risks steming from uncoordinated strategy ... SAI of Czech Republic analysed consequences of failures in strategic IT management at the state level. Lack of coordination and implementation rules reduced practical role of the ministry whose task ... was to guard high quality standards for all crucial IT systems in the state administration. Next consecquences were (among others) risk of uneconomical results of large IT investment and risk of inefficient ... supply of services, as well as opposite results of workforce reduction.
Full description
The aim of the audit was to scrutinise the management of funds spent on building and operating the national data centre (hereinafter “STC1 data centre”), including the expenditure of selected ... organisational units of the state on buying hosting, server-housing and other related services. The audited period was between 2010 and 2014; where relevant, the preceding period was also scrutinised. Audited ... entities: Ministry of the Interior (“MoI”); Ministry of Finance (“MoF”); STÁTNÍ TISKÁRNA CENIN, state firm (state banknote printing firm, hereinafter “STC” or “the state firm”). The audit was conducted ... ... Risks steming from uncoordinated strategy ... SAI of Czech Republic analysed consequences of failures in strategic IT management at the state level. Lack of coordination and implementation rules reduced practical role of the ministry whose task ... was to guard high quality standards for all crucial IT systems in the state administration. Next consecquences were (among others) risk of uneconomical results of large IT investment and risk of inefficient ... supply of services, as well as opposite results of workforce reduction.
Full description
Supreme Audit Office of Czech Republic
, issued in 2015
Risk cases: 7
Steps Needed to Identify Acquisition Training Needs for Non-Acquisition Personnel
Non-Acquisition staff can be crucial for acquisition Despite from hundreds of billions of dollars spent annually to acquire products and services, the US Department of Defense does not full information about staff to be trained. The information is needed about the non-acquisition staff, who can play crucial role in particular acquisitions. As GAO underlines, their identification is necessary to fully understand the training needs and... budget.
Full description
Non-Acquisition staff can be crucial for acquisition Despite from hundreds of billions of dollars spent annually to acquire products and services, the US Department of Defense does not full information about staff to be trained. The information is needed about the non-acquisition staff, who can play crucial role in particular acquisitions. As GAO underlines, their identification is necessary to fully understand the training needs and... budget.
Full description
US Government Accountability Office
, issued in 2019
Risk cases: 4
The Shared Services Centre
The necessary environment for the efficient management of the Shared Service Center is lacking The department's administration of the Shared Services Centre (SSC) has been effective for sharing resources between the departments and delivering selected back-office services to a small client base. However, the governance arrangements established to oversight the SSC have not positioned it well for the future and the departments have not yet determined if the arrangement is efficient and resulting in savings. ANAO found instances where the advisory board of SSC was not consulted or involved in decisions relating to the strategic direction, financial arrangements and expenditure priorities. Information reported to the board did not focus on areas of strategic importance and the quality and completeness of this information could be improved. The mechanisms established for setting out responsibilities and obligations and ensuring transparency for services delivered by the SSC was weak. Service standards and levels were not fixed and can change. The delineation of responsibilities between the SSC and its clients was not clear and there was no commitment by the SSC to certify the quality of its control framework.
Full description
The necessary environment for the efficient management of the Shared Service Center is lacking The department's administration of the Shared Services Centre (SSC) has been effective for sharing resources between the departments and delivering selected back-office services to a small client base. However, the governance arrangements established to oversight the SSC have not positioned it well for the future and the departments have not yet determined if the arrangement is efficient and resulting in savings. ANAO found instances where the advisory board of SSC was not consulted or involved in decisions relating to the strategic direction, financial arrangements and expenditure priorities. Information reported to the board did not focus on areas of strategic importance and the quality and completeness of this information could be improved. The mechanisms established for setting out responsibilities and obligations and ensuring transparency for services delivered by the SSC was weak. Service standards and levels were not fixed and can change. The delineation of responsibilities between the SSC and its clients was not clear and there was no commitment by the SSC to certify the quality of its control framework.
Full description
The Australian National Audit Office
, issued in 2016
Risk cases: 2
Cost-intensive data centres stood idle for years
Idle data centres As found by the German SAI, some of costly Federal data centres stood largely idle. The Ministry failed to adequately assess the project risks. The Ministry needs to avoid similar shortcomings in the proposed federal IT consolidation project.
Full description
Idle data centres As found by the German SAI, some of costly Federal data centres stood largely idle. The Ministry failed to adequately assess the project risks. The Ministry needs to avoid similar shortcomings in the proposed federal IT consolidation project.
Full description
Bundesrechnungshof
, issued in 2016
Risk cases: 1
Australian Taxation Office: Administration of Australian Business Number Registrations
More elligibility and data integrity needed The Australian Business Number (ABN) and Australian Business Register initiatives were implemented as part of theGovernment's comprehensive reform of the taxation system in 2000. Their introduction involved challenging issues of technology and governance , including the imperative to process and register significant numbers of applications in a short time. Overall, the Australian SAI concluded that the ABN registration process is operating effectively. However, matters relating to the eligibility of some ABN applicants need to be reviewed. Further, some data integrity issues remain outstanding.
Full description
More elligibility and data integrity needed The Australian Business Number (ABN) and Australian Business Register initiatives were implemented as part of theGovernment's comprehensive reform of the taxation system in 2000. Their introduction involved challenging issues of technology and governance , including the imperative to process and register significant numbers of applications in a short time. Overall, the Australian SAI concluded that the ABN registration process is operating effectively. However, matters relating to the eligibility of some ABN applicants need to be reviewed. Further, some data integrity issues remain outstanding.
Full description
The Australian National Audit Office
, issued in 2003
Risk cases: 3
The National Government Service Centre – Has administration become more effective?
The purpose of this audit has been to investigate whether the Service Centre has made administrative operational support functions taken over from client agencies more effective, and to find ... explanations for the results so far achieved by the Service Centre. The audit has also aspired to illustrate how agencies that do not subscribe to the services regard their potential for doing so ... . These viewpoints have been analysed with a special focus on the conditions that applied to the Service Centre when it was formed and the measures taken by the Government and the Service Centre in the first years. ... ... Has Swedish public administration become more effective? ... The Service Centre – payroll and financial administration IT system for Swedish public agencies under the government – has achieved the target of a subscription rate of 25 per cent of the total ... number of state employees. However, subscription to the Service Centre was initially slower than the Government had predicted and meant lower revenues than expected in autumn 2013. The Service Centre ... then introduced a rigorous review of its expenditure, for example for some planned development initiatives for internal procedures and support systems.<br/>The Swedish NAO noted that the Government’s steering
Full description
The purpose of this audit has been to investigate whether the Service Centre has made administrative operational support functions taken over from client agencies more effective, and to find ... explanations for the results so far achieved by the Service Centre. The audit has also aspired to illustrate how agencies that do not subscribe to the services regard their potential for doing so ... . These viewpoints have been analysed with a special focus on the conditions that applied to the Service Centre when it was formed and the measures taken by the Government and the Service Centre in the first years. ... ... Has Swedish public administration become more effective? ... The Service Centre – payroll and financial administration IT system for Swedish public agencies under the government – has achieved the target of a subscription rate of 25 per cent of the total ... number of state employees. However, subscription to the Service Centre was initially slower than the Government had predicted and meant lower revenues than expected in autumn 2013. The Service Centre ... then introduced a rigorous review of its expenditure, for example for some planned development initiatives for internal procedures and support systems.<br/>The Swedish NAO noted that the Government’s steering
Full description
Swedish National Audit Office
, issued in 2016
Risk cases: 2
Conflicts of interest
First, recognise the conflicts of interest are a real risk the British NAO gathered a significant amount of intelligence on conflicts, particularly in the health and education sectors. These are areas of government where services are increasingly commissioned and delivered by parties at arm’s-length to departments. Conflicts of interest can occur naturally as a product of the way a system is designed and most often arise from operational situations.
Full description
First, recognise the conflicts of interest are a real risk the British NAO gathered a significant amount of intelligence on conflicts, particularly in the health and education sectors. These are areas of government where services are increasingly commissioned and delivered by parties at arm’s-length to departments. Conflicts of interest can occur naturally as a product of the way a system is designed and most often arise from operational situations.
Full description
National Audit Office
, issued in 2015
Risk cases: 8