54
results found in
12 ms
Page 1
of 6
Analysis of Trends in SAI Japan’s Findings
Analysis of IT audit cases by Board of Audit of Japan in years 2004-12. ... Not used IT systems and overpaid 'ghost' services ... Wrap-up of almost a decade of SAI of Japan's IT related audits results in a form of list of most often found problems. On the top of the list are unwanted or overpaid IT systems and too expensive ... maintanance. It makes you thinking: if one of the world technology leaders could find this, what could we find in our country...
Full description
Analysis of IT audit cases by Board of Audit of Japan in years 2004-12. ... Not used IT systems and overpaid 'ghost' services ... Wrap-up of almost a decade of SAI of Japan's IT related audits results in a form of list of most often found problems. On the top of the list are unwanted or overpaid IT systems and too expensive ... maintanance. It makes you thinking: if one of the world technology leaders could find this, what could we find in our country...
Full description
Board of Audit of Japan
, issued in 2014
Risk cases: 3
Performance Audit of the Georgian Government electronic Procurement system
. The audit was aimed to identify system’s shortcomings and issue recommendations to eliminate them. To accomplish audit objectives, the auditors assessed the performance of Ge-GP system’s management ... and control mechanisms. Electronic system’s management compliance to relevant laws and regulations has also been studied in the course of the audit. ... of interest for the State Audit Office. Considering the fact that since 2010 major part of public procurements is being conducted electronically and there is no alternative tool, uninterrupted provision ... ... Electronic procurement system - how effective are management and control mechanisms? ... SAI Georgia analyzed the electronic Government Procurement system. In their report they focus on compliance and security problems, which may harm the business goals and overall mission of the system.
Full description
. The audit was aimed to identify system’s shortcomings and issue recommendations to eliminate them. To accomplish audit objectives, the auditors assessed the performance of Ge-GP system’s management ... and control mechanisms. Electronic system’s management compliance to relevant laws and regulations has also been studied in the course of the audit. ... of interest for the State Audit Office. Considering the fact that since 2010 major part of public procurements is being conducted electronically and there is no alternative tool, uninterrupted provision ... ... Electronic procurement system - how effective are management and control mechanisms? ... SAI Georgia analyzed the electronic Government Procurement system. In their report they focus on compliance and security problems, which may harm the business goals and overall mission of the system.
Full description
State Audit Office Of Georgia
, issued in 2016
Risk cases: 5
Coordinated Audit on Information Technology Governance
IT governance needs awareness and SAIs' support The OLACEFS auditors found that the greatest challenge for the SAIs is to raise the awareness of the audit institutions about the importance of IT governance and the benefits that could be obtained by improving its degree of maturity. The audit was conducted by 11 SAIs and coordinated by TCU of Brasil. They concluded: 'It is important, even urgent, to invest resources to implement or enhance: the IT committees; the IT planning process; strategic IT planning; monitoring the IT contracting process; the business continuity plan; the designation of a responsible person or unit to manage security information; a risk management process; an asset inventory process; an information security committee; and a policy for access control.'
Full description
IT governance needs awareness and SAIs' support The OLACEFS auditors found that the greatest challenge for the SAIs is to raise the awareness of the audit institutions about the importance of IT governance and the benefits that could be obtained by improving its degree of maturity. The audit was conducted by 11 SAIs and coordinated by TCU of Brasil. They concluded: 'It is important, even urgent, to invest resources to implement or enhance: the IT committees; the IT planning process; strategic IT planning; monitoring the IT contracting process; the business continuity plan; the designation of a responsible person or unit to manage security information; a risk management process; an asset inventory process; an information security committee; and a policy for access control.'
Full description
Risk cases: 5
Audit of the key ICT project federal GEVER programme Federal Chancellery
During the first stage, two new GEVER (electronic records and process management) products were procured in an open WTO tender within the framework of the two-product strategy (federal GEVER WTO ... procurement project). CHF 1.6 million was spent on these. The departments and Federal Chancellery (departments/FCh) had to choose one of the two products within three months of the contract being awarded. ... ... Advanced process management system's cost-effectiveness and deadlines at risk ... Ever since 1990, sequential controls and file management have been part of the Federal Administration's IT landscape (GEVER business administration). Significant obstacles have to be overcome ... in order to ensure the successful creation and introduction of GEVER. Previous efforts did not have any widespread success and led to a diverse GEVER landscape. The federal GEVER project has now laid ... the foundations for simplification and centralisation.
Full description
During the first stage, two new GEVER (electronic records and process management) products were procured in an open WTO tender within the framework of the two-product strategy (federal GEVER WTO ... procurement project). CHF 1.6 million was spent on these. The departments and Federal Chancellery (departments/FCh) had to choose one of the two products within three months of the contract being awarded. ... ... Advanced process management system's cost-effectiveness and deadlines at risk ... Ever since 1990, sequential controls and file management have been part of the Federal Administration's IT landscape (GEVER business administration). Significant obstacles have to be overcome ... in order to ensure the successful creation and introduction of GEVER. Previous efforts did not have any widespread success and led to a diverse GEVER landscape. The federal GEVER project has now laid ... the foundations for simplification and centralisation.
Full description
Swiss Federal Audit Office
, issued in 2015
Risk cases: 2
Audit on the broadband internet infrastructure access
Poland has been granted over PLN 4 billion from the European Regional Development Fund to build the broadband internet access infrastructure. As part of three operational programmes 90 percent ... of assumed financing was contracted, namely PLN 3.9 billion. By the end of 2015, Poland should complete the investment and account for the expenses. According to NIK there is a risk that the infrastructure ... construction will not be completed by the deadline and the EU funds may not be used to the full. ... ... Simpler regulations and better supervision needed ... Polish SAI audited a project, which aim had been to develop broadband internet network across the country. They revealed that legal obstacles, idleness and lack of supervision were the main causes ... of delays. Some of the projects are in danger of not being completed on time and some of the EU funds may not be fully used.
Full description
Poland has been granted over PLN 4 billion from the European Regional Development Fund to build the broadband internet access infrastructure. As part of three operational programmes 90 percent ... of assumed financing was contracted, namely PLN 3.9 billion. By the end of 2015, Poland should complete the investment and account for the expenses. According to NIK there is a risk that the infrastructure ... construction will not be completed by the deadline and the EU funds may not be used to the full. ... ... Simpler regulations and better supervision needed ... Polish SAI audited a project, which aim had been to develop broadband internet network across the country. They revealed that legal obstacles, idleness and lack of supervision were the main causes ... of delays. Some of the projects are in danger of not being completed on time and some of the EU funds may not be fully used.
Full description
Supreme Audit Office of Poland
, issued in 2015
Risk cases: 2
Audit of the procurement of ICT products with the potential to be standard products
ICT procurement system reviewed SFAO points out what is critical in ICT procurement. Requirements management is extremely important, as well as procurement strategies for relevant product groups. Legal rules should protect investments and support competition, but they can still be insufficient without appropriate reporting - if you want your system to adapt to changes.
Full description
ICT procurement system reviewed SFAO points out what is critical in ICT procurement. Requirements management is extremely important, as well as procurement strategies for relevant product groups. Legal rules should protect investments and support competition, but they can still be insufficient without appropriate reporting - if you want your system to adapt to changes.
Full description
Swiss Federal Audit Office
, issued in 2015
Risk cases: 4
The National Government Service Centre – Has administration become more effective?
The purpose of this audit has been to investigate whether the Service Centre has made administrative operational support functions taken over from client agencies more effective, and to find ... explanations for the results so far achieved by the Service Centre. The audit has also aspired to illustrate how agencies that do not subscribe to the services regard their potential for doing so ... . These viewpoints have been analysed with a special focus on the conditions that applied to the Service Centre when it was formed and the measures taken by the Government and the Service Centre in the first years. ... ... Has Swedish public administration become more effective? ... then introduced a rigorous review of its expenditure, for example for some planned development initiatives for internal procedures and support systems.<br/>The Swedish NAO noted that the Government’s steering ... of agencies' subscription to the Service Centre’s services was limited to start with. For example, the Service Centre’s operational targets for subscription did not refer to agency size, which is important ... The Service Centre – payroll and financial administration IT system for Swedish public agencies under the government – has achieved the target of a subscription rate of 25 per cent of the total
Full description
The purpose of this audit has been to investigate whether the Service Centre has made administrative operational support functions taken over from client agencies more effective, and to find ... explanations for the results so far achieved by the Service Centre. The audit has also aspired to illustrate how agencies that do not subscribe to the services regard their potential for doing so ... . These viewpoints have been analysed with a special focus on the conditions that applied to the Service Centre when it was formed and the measures taken by the Government and the Service Centre in the first years. ... ... Has Swedish public administration become more effective? ... then introduced a rigorous review of its expenditure, for example for some planned development initiatives for internal procedures and support systems.<br/>The Swedish NAO noted that the Government’s steering ... of agencies' subscription to the Service Centre’s services was limited to start with. For example, the Service Centre’s operational targets for subscription did not refer to agency size, which is important ... The Service Centre – payroll and financial administration IT system for Swedish public agencies under the government – has achieved the target of a subscription rate of 25 per cent of the total
Full description
Swedish National Audit Office
, issued in 2016
Risk cases: 2
Open Government Data - Are all exceptions to the principle of cost-free access and reuse legitimate?
models for all existing fee regimes applied to the use of public data, notably by auditing the relevant costs and revenue" and has entrusted to me the task of providing input for that assessment.<br ... /> In order to address this issue, the commission has endeavoured to base its considerations on:<br/> - the work done on a regular basis over the last twenty or so years by Government on issues relating ... The United Kingdom, a country seen, like the United States, as a pioneer in open public data, has estimated at £6.8bn (€7,9bn) the revenue in 2010 and 2011 generated for British society by open ... ... Open data strategy should decide the costs problem ... French Cour des comptes presents analysis on implementation of the open data practice across the administration. Massive savings are expected, when public access to large amounts of highquality data ... is made easy. France is among the pioneers and countries making the most rapid progress in this domain. Charges for the reuse of the public information has been identified as the main problem.
Full description
models for all existing fee regimes applied to the use of public data, notably by auditing the relevant costs and revenue" and has entrusted to me the task of providing input for that assessment.<br ... /> In order to address this issue, the commission has endeavoured to base its considerations on:<br/> - the work done on a regular basis over the last twenty or so years by Government on issues relating ... The United Kingdom, a country seen, like the United States, as a pioneer in open public data, has estimated at £6.8bn (€7,9bn) the revenue in 2010 and 2011 generated for British society by open ... ... Open data strategy should decide the costs problem ... French Cour des comptes presents analysis on implementation of the open data practice across the administration. Massive savings are expected, when public access to large amounts of highquality data ... is made easy. France is among the pioneers and countries making the most rapid progress in this domain. Charges for the reuse of the public information has been identified as the main problem.
Full description
Cour des comptes
, issued in 2013
Risk cases: 1
Correlations between the operational risks of companies in the majority ownership of local governments and the financial situation of the local governments
Risks related to local governments-owned companies The Hungarian SAI analysed four risk areas, taking 19 aspects and the specificities of Hungary’s settlement patterns into consideration. The four areas defined were the following: performance of public tasks, exercise of proprietary rights, financial stability of local governments, and short and medium-term stability of the financial management of companies.
Full description
Risks related to local governments-owned companies The Hungarian SAI analysed four risk areas, taking 19 aspects and the specificities of Hungary’s settlement patterns into consideration. The four areas defined were the following: performance of public tasks, exercise of proprietary rights, financial stability of local governments, and short and medium-term stability of the financial management of companies.
Full description
State Audit Office of Hungary
, issued in 2017
Risk cases: 1
Conflicts of interest
First, recognise the conflicts of interest are a real risk the British NAO gathered a significant amount of intelligence on conflicts, particularly in the health and education sectors. These are areas of government where services are increasingly commissioned and delivered by parties at arm’s-length to departments. Conflicts of interest can occur naturally as a product of the way a system is designed and most often arise from operational situations.
Full description
First, recognise the conflicts of interest are a real risk the British NAO gathered a significant amount of intelligence on conflicts, particularly in the health and education sectors. These are areas of government where services are increasingly commissioned and delivered by parties at arm’s-length to departments. Conflicts of interest can occur naturally as a product of the way a system is designed and most often arise from operational situations.
Full description
National Audit Office
, issued in 2015
Risk cases: 8