Reports Search Reports Spatial Search Risk-cases Search Risk-cases Graph Traversal
11 results found in 8 ms Page 1 of 2
Information Technology Cost Estimation Agencies Need to Address Significant Weakness in Policies and Practices
and agencies have appropriately implement costestimating policies an procedures(four caracteristics of a reliable cost estimation: comprehensive, well-documented, accurate, credible). ... To estimate reliable cost for the sucess of an IT program by providing the basis for the informed decision making and realistic budget information. To assess the extent to which selected departments ... IT cost estimation ... Check out what may go wrong with the information technology cost estimation. Results of the US GAO audit can help to identify high risk areas: comprehensiveness of estimations, their documentation ... , lack of adequacy and inadequate implementation.
Full description
General Accountability Office , issued in 2012
Risk cases: 4
Products sold on the European market: unravelling the system of CE marking
Problems with general picture The Netherlands National Court of Audit was interested in finding out whether anyone keeps track of all the actors involved in the process of system of European Union product markings. The interest was aroused by an observation that the vast majority of the questions raised about the system were prompted by incidents and that the questioners did not generally appear to be interested in the operation of the system as a whole...
Full description
The Netherlands Court of Audit , issued in 2017
Risk cases: 5
Protection of automatically processed personal data
Over the past few years, a number of legal, management, supervision, information, and methodological issues related to the protection of personal data have piled up. As they have not been fully ... resolved,the National Audit Office conducted an audit to assess the efficiency of the protection and supervision of automatically processed personal data and to check whether: - the regulation of personal data ... protection conforms to the data processing practices; - personal data is properly processed at public sector bodies; - the State Data Protection Inspectorate (SDPI) performs sufficient supervision ... ... Data protection needs a long term strategy ... Rapid development of information and communication technology continuously brings about issues of personal data protection. Due to lack of long-term vision in this area they are frequently ... not addressed by the existing legislation. Moreover, SAI of Lithuania revealed failures in organization and control of personal data protection by public sector.
Full description
National Audit Office of the Republic of Lithuania , issued in 2013
Risk cases: 2
Use of consultants and temporary staff
New skills needed in a longer term UK NAO: Used well, consultants and temporary staff can be an important source of specialist skills and capabilities that are uneconomic for departments to maintain in their permanent staff. Since 2009-10, the government has used spending controls to reduce its use of consultants and temporary staff, and by 2014-15 spending had fallen by £1.5 billion. However, spending has increased by between £400 million and £600 million since 2011-12, suggesting that this was more of a short-term reduction than a sustainable strategy. In the longer term, departments will need to develop workforce, skills and capacity plans to reduce their dependence on external skills. They will need to improve their strategic workforce planning to determine where they can deploy existing staff, where they need to recruit, and where they need to engage temporary resources. Without this, departments cannot demonstrate that they are achieving value for money from the use of consultants and temporary staff.
Full description
National Audit Office , issued in 2016
Risk cases: 7
Whether Disclosure of the Public Sector Data Is Ensured
Strategy more important than declarations Why open data are so dificult to become reality? Lithuania possesses the elements required to disclose data but lacks a strategic approach. The report by SAI Lithuania reviews all critical elements of this problem. Most of them look like a pattern reproduced by other countries. And one important thing: the SAI Lithuania opened their own data - exactly on the day of publication of the audit report!
Full description
National Audit Office of the Republic of Lithuania , issued in 2016
Risk cases: 9
The National Offender Management Information System (NOMIS)
This report examines the reasons for the delays and cost increases to the original integrated information system and, since the moratorium imposed by the Minister of State in order to seek options ... for project’s cost reduction, the aims of the revised National Offender Management Service (NOMS) and the progress made, the impact of the delays and rescoping on the costs and benefits achieved, and NOMS ... ’ fitness to deliver. The aim of one integrated information system (C-NOMIS i.e. National Offender Management Information System) was to improve information sharing about offenders; address the lack ... Rescoping necessary, but not fully successful ... An initiative to build a single offender management IT system for the prison and probation services has not delivered value for money. The NAO investigation found the project had been hampered ... by poor management leading to a three-year delay, a doubling in project costs and reductions in scope and benefits.
Full description
National Audit Office , issued in 2009
Risk cases: 4
The effectiveness of Official Development Assistance expenditure
Need of more coordination and transparency The audit of the UK's Official Development Assistance revealed among others: fragmented responsibilities and difficulties in review and reporting. These led to difficulties in assessment of effectiveness of the assistance and of progress in implementing the UK Aid Strategy.
Full description
National Audit Office , issued in 2019
Risk cases: 4
OMB and Agencies Need to Focus Continued Attention on Implementing Reform Law
How to invest efficiently in IT IT investments are large and growing position in annual budgets. Historically, they have frequently failed, incurred cost overruns and schedule slippages, or contributed little to mission-related outcomes. GAO recommendations focus on the oversight and execution of the data center consolidation initiative, the accuracy and reliability of the IT Dashboard, and incremental development policies.
Full description
General Accountability Office , issued in 2016
Risk cases: 3
Homeland Security. Oversight of Neglected Human Resources Information Technology Investment Is Needed
Human resources IT investments get stuck in management's lack of interest Although the Human Resources Information Technology (HRIT) investment was initiated about 12 years ago with the intent to consolidate, integrate, and modernize the department's human resources IT infrastructure, the Department of Homeland Security (DHS) has made very limited progress in achieving these goals. HRIT's minimally involved executive steering committee during a time when significant problems were occurring was a key factor in the lack of progress. This is particularly problematic given that the department's ability to efficiently and effectively carry out its mission is significantly hampered by its fragmented human resources. DHS's ineffective management of HRIT, such as the lack of an updated schedule and a life-cycle cost estimate, also contributed to the neglect this investment has experienced. DHS will be limited in efficiently tracking and reporting accurate, comprehensive performance and learning management data across the organization, and could risk further implementation delays.
Full description
US Government Accountability Office , issued in 2016
Risk cases: 1
Building and Implementing the Phoenix Pay System
Expensive IT project became a failure Phoenix project (development of states pay system) was an incomprehensible failure of project management and oversight. Phoenix executives prioritized certain aspects, such as schedule and budget, over other critical ones, such as functionality and security. Phoenix executives did not understand the importance of warnings that the Miramichi Pay Centre, departments and agencies, and the new system were not ready. They did not provide complete and accurate information to deputy ministers and associate deputy ministers of departments and agencies, including the Deputy Minister of Public Services and Procurement, when briefing them on Phoenix readiness for implementation.
Full description
Office of theAuditor Generalof Canada , issued in 2018
Risk cases: 3
11 results found. Page 1 of 2 next