Reports Search Reports Spatial Search Risk-cases Search Risk-cases Graph Traversal
17 results found in 8 ms Page 1 of 2
Building and Implementing the Phoenix Pay System
Expensive IT project became a failure Phoenix project (development of states pay system) was an incomprehensible failure of project management and oversight. Phoenix executives prioritized certain aspects, such as schedule and budget, over other critical ones, such as functionality and security. Phoenix executives did not understand the importance of warnings that the Miramichi Pay Centre, departments and agencies, and the new system were not ready. They did not provide complete and accurate information to deputy ministers and associate deputy ministers of departments and agencies, including the Deputy Minister of Public Services and Procurement, when briefing them on Phoenix readiness for implementation.
Full description
Office of theAuditor Generalof Canada , issued in 2018
Risk cases: 3
The National Offender Management Information System (NOMIS)
for project’s cost reduction, the aims of the revised National Offender Management Service (NOMS) and the progress made, the impact of the delays and rescoping on the costs and benefits achieved, and NOMS ... This report examines the reasons for the delays and cost increases to the original integrated information system and, since the moratorium imposed by the Minister of State in order to seek options ... ’ fitness to deliver. The aim of one integrated information system (C-NOMIS i.e. National Offender Management Information System) was to improve information sharing about offenders; address the lack ... Rescoping necessary, but not fully successful ... An initiative to build a single offender management IT system for the prison and probation services has not delivered value for money. The NAO investigation found the project had been hampered ... by poor management leading to a three-year delay, a doubling in project costs and reductions in scope and benefits.
Full description
National Audit Office , issued in 2009
Risk cases: 4
Report to on the user-friendliness and user involvement in the development of e-government services in Denmark
The e-government user-friendliness requirements are divided into five overall categories: language, design and flow, data and functionality, and accessibility. 1) The objective of the study ... is to provide an assessment of the authorities’ efforts to ensure that e-government services are user-friendly. The report answers the following questions: - Have the authorities involved the users ... in the development of the e-government services? - Have the authorities conducted post-launch assessments of the user-friendliness of the e-government services, and do the contracts with the suppliers of the solutions ... ... User-friendliness of public services should be consistenty required and tested ... The Danish Rigsrevisionen is of the opinion that the user-friendliness of the services can be improved if the authorities meet all the requirements of the Danish Agency for Digitisation concerning ... the matter. The audit covered user-friendliness related problems in case of five systems, before and after the launch. The systems take-up was also considered, as well as communicating with citizens who ... are unable to use digital services.
Full description
National Audit Office of Denmark , issued in 2013
Risk cases: 2
Protection of automatically processed personal data
of the Interior, Information Society Development Committee under the Ministry of Transport and Communications, and public establishment Central Project Management Agency. ... Over the past few years, a number of legal, management, supervision, information, and methodological issues related to the protection of personal data have piled up. As they have not been fully ... resolved,the National Audit Office conducted an audit to assess the efficiency of the protection and supervision of automatically processed personal data and to check whether: - the regulation of personal data ... ... Data protection needs a long term strategy ... Rapid development of information and communication technology continuously brings about issues of personal data protection. Due to lack of long-term vision in this area they are frequently ... not addressed by the existing legislation. Moreover, SAI of Lithuania revealed failures in organization and control of personal data protection by public sector.
Full description
National Audit Office of the Republic of Lithuania , issued in 2013
Risk cases: 2
IT Support in the Judicial Chain
The Swedish National Audit Office has examined how well agencies in the judicial chain have handled known flaws in their IT support and whether the Government’s control mechanisms have provided ... the agencies with sufficient prerequisites to expand and improve IT support. ... ... Needed: good conditions by government, better steering and control by authorities ... Despite many years’ of work to modernize the IT support within the judiciary, there are still many deficiencies. The Government has not given the authorities good conditions enough to lead the work ... . The authorities, in their turn, need to improve their steering and control, as well as interact to a much higher degree.
Full description
Swedish National Audit Office , issued in 2011
Risk cases: 3
Federal Human Resources Data
Internal control weaknesses may put mission at risk GAO audited the Enterprise Human Resources Integration payroll data warehose. The American auditors pointed at problems that may impede 'leverage of these data to meet its mission and allow others to make full use' of them. The critical internal contols areas to be improved in this cas are: completeness, accuracy, and validity of information, authorization, documentation, monitoring, results' evaluation.
Full description
General Accountability Office , issued in 2016
Risk cases: 2
Has Public Administration Used All Opportunities for Efficient Management of ICT Infrastructure?
Efficient Management of ICT Infrastructure Centralised management of ICT services and infrastructure would allow the institutions to optimise in long run their resources – financial, human, material and technical. However, we observed during the audit that the move towards ICT centralisation and single data centres has ceased. The different ministries and even the institutions subordinated to the same ministry do not cooperate sufficiently with each other regarding the ICT management, maintenance, and infrastructure placement. They rather choose to maintain their own, sometimes even several, data centres.
Full description
State Audit Office of the Republic of Latvia , issued in 2019
Risk cases: 3
Performance Audit of the Management of ICT in the Criminal Justice Sector
The Norwegian OAG has assesed how the Ministry of Justice and Public Security has discharged its responsibility for effiecient case processing through developing and applying Information ... and Communications Technology (ICT) in the criminal justice sector ... ... Unclear signals from a Ministry weaken development of ICT in the justice chain ... Points by SAI Norway: development of an overall rolling action plan based on the current ICT (Information and Communication Technology) strategy for the justice sector, performance-oriented ... reporting from the subordinate agencies, ensuring that the new ICT Police System takes into account other sub-sectors need for electronic interaction.
Full description
Office of the Auditor General of Norway , issued in 2012
Risk cases: 2
Homeland Security. Oversight of Neglected Human Resources Information Technology Investment Is Needed
Human resources IT investments get stuck in management's lack of interest Although the Human Resources Information Technology (HRIT) investment was initiated about 12 years ago with the intent to consolidate, integrate, and modernize the department's human resources IT infrastructure, the Department of Homeland Security (DHS) has made very limited progress in achieving these goals. HRIT's minimally involved executive steering committee during a time when significant problems were occurring was a key factor in the lack of progress. This is particularly problematic given that the department's ability to efficiently and effectively carry out its mission is significantly hampered by its fragmented human resources. DHS's ineffective management of HRIT, such as the lack of an updated schedule and a life-cycle cost estimate, also contributed to the neglect this investment has experienced. DHS will be limited in efficiently tracking and reporting accurate, comprehensive performance and learning management data across the organization, and could risk further implementation delays.
Full description
US Government Accountability Office , issued in 2016
Risk cases: 1
Use of consultants and temporary staff
New skills needed in a longer term UK NAO: Used well, consultants and temporary staff can be an important source of specialist skills and capabilities that are uneconomic for departments to maintain in their permanent staff. Since 2009-10, the government has used spending controls to reduce its use of consultants and temporary staff, and by 2014-15 spending had fallen by £1.5 billion. However, spending has increased by between £400 million and £600 million since 2011-12, suggesting that this was more of a short-term reduction than a sustainable strategy. In the longer term, departments will need to develop workforce, skills and capacity plans to reduce their dependence on external skills. They will need to improve their strategic workforce planning to determine where they can deploy existing staff, where they need to recruit, and where they need to engage temporary resources. Without this, departments cannot demonstrate that they are achieving value for money from the use of consultants and temporary staff.
Full description
National Audit Office , issued in 2016
Risk cases: 7
17 results found. Page 1 of 2 next