11
results found in
8 ms
Page 1
of 2
Report to on the user-friendliness and user involvement in the development of e-government services in Denmark
in the development of the e-government services? - Have the authorities conducted post-launch assessments of the user-friendliness of the e-government services, and do the contracts with the suppliers of the solutions ... The e-government user-friendliness requirements are divided into five overall categories: language, design and flow, data and functionality, and accessibility. 1) The objective of the study ... is to provide an assessment of the authorities’ efforts to ensure that e-government services are user-friendly. The report answers the following questions: - Have the authorities involved the users ... ... User-friendliness of public services should be consistenty required and tested ... The Danish Rigsrevisionen is of the opinion that the user-friendliness of the services can be improved if the authorities meet all the requirements of the Danish Agency for Digitisation concerning ... the matter. The audit covered user-friendliness related problems in case of five systems, before and after the launch. The systems take-up was also considered, as well as communicating with citizens who ... are unable to use digital services.
Full description
in the development of the e-government services? - Have the authorities conducted post-launch assessments of the user-friendliness of the e-government services, and do the contracts with the suppliers of the solutions ... The e-government user-friendliness requirements are divided into five overall categories: language, design and flow, data and functionality, and accessibility. 1) The objective of the study ... is to provide an assessment of the authorities’ efforts to ensure that e-government services are user-friendly. The report answers the following questions: - Have the authorities involved the users ... ... User-friendliness of public services should be consistenty required and tested ... The Danish Rigsrevisionen is of the opinion that the user-friendliness of the services can be improved if the authorities meet all the requirements of the Danish Agency for Digitisation concerning ... the matter. The audit covered user-friendliness related problems in case of five systems, before and after the launch. The systems take-up was also considered, as well as communicating with citizens who ... are unable to use digital services.
Full description
National Audit Office of Denmark
, issued in 2013
Risk cases: 2
Homeland Security. Oversight of Neglected Human Resources Information Technology Investment Is Needed
Human resources IT investments get stuck in management's lack of interest Although the Human Resources Information Technology (HRIT) investment was initiated about 12 years ago with the intent to consolidate, integrate, and modernize the department's human resources IT infrastructure, the Department of Homeland Security (DHS) has made very limited progress in achieving these goals. HRIT's minimally involved executive steering committee during a time when significant problems were occurring was a key factor in the lack of progress. This is particularly problematic given that the department's ability to efficiently and effectively carry out its mission is significantly hampered by its fragmented human resources. DHS's ineffective management of HRIT, such as the lack of an updated schedule and a life-cycle cost estimate, also contributed to the neglect this investment has experienced. DHS will be limited in efficiently tracking and reporting accurate, comprehensive performance and learning management data across the organization, and could risk further implementation delays.
Full description
Human resources IT investments get stuck in management's lack of interest Although the Human Resources Information Technology (HRIT) investment was initiated about 12 years ago with the intent to consolidate, integrate, and modernize the department's human resources IT infrastructure, the Department of Homeland Security (DHS) has made very limited progress in achieving these goals. HRIT's minimally involved executive steering committee during a time when significant problems were occurring was a key factor in the lack of progress. This is particularly problematic given that the department's ability to efficiently and effectively carry out its mission is significantly hampered by its fragmented human resources. DHS's ineffective management of HRIT, such as the lack of an updated schedule and a life-cycle cost estimate, also contributed to the neglect this investment has experienced. DHS will be limited in efficiently tracking and reporting accurate, comprehensive performance and learning management data across the organization, and could risk further implementation delays.
Full description
US Government Accountability Office
, issued in 2016
Risk cases: 1
Use of consultants and temporary staff
New skills needed in a longer term UK NAO: Used well, consultants and temporary staff can be an important source of specialist skills and capabilities that are uneconomic for departments to maintain in their permanent staff. Since 2009-10, the government has used spending controls to reduce its use of consultants and temporary staff, and by 2014-15 spending had fallen by £1.5 billion. However, spending has increased by between £400 million and £600 million since 2011-12, suggesting that this was more of a short-term reduction than a sustainable strategy. In the longer term, departments will need to develop workforce, skills and capacity plans to reduce their dependence on external skills. They will need to improve their strategic workforce planning to determine where they can deploy existing staff, where they need to recruit, and where they need to engage temporary resources. Without this, departments cannot demonstrate that they are achieving value for money from the use of consultants and temporary staff.
Full description
New skills needed in a longer term UK NAO: Used well, consultants and temporary staff can be an important source of specialist skills and capabilities that are uneconomic for departments to maintain in their permanent staff. Since 2009-10, the government has used spending controls to reduce its use of consultants and temporary staff, and by 2014-15 spending had fallen by £1.5 billion. However, spending has increased by between £400 million and £600 million since 2011-12, suggesting that this was more of a short-term reduction than a sustainable strategy. In the longer term, departments will need to develop workforce, skills and capacity plans to reduce their dependence on external skills. They will need to improve their strategic workforce planning to determine where they can deploy existing staff, where they need to recruit, and where they need to engage temporary resources. Without this, departments cannot demonstrate that they are achieving value for money from the use of consultants and temporary staff.
Full description
National Audit Office
, issued in 2016
Risk cases: 7
Good Practice in Annual Reports 2016-17
Reporting: a real skill The Building Public Trust Awards, sponsored by PwC, have been running for 15 years and the British NAO co-sponsors the public sector award. The Good Practices in annual reports 2016-2017 present eye-opening examples of how to make complex reports easily understandable and how to clearly outline goals and achievement of them.
Full description
Reporting: a real skill The Building Public Trust Awards, sponsored by PwC, have been running for 15 years and the British NAO co-sponsors the public sector award. The Good Practices in annual reports 2016-2017 present eye-opening examples of how to make complex reports easily understandable and how to clearly outline goals and achievement of them.
Full description
National Audit Office
, issued in 2018
Risk cases: 4
Identifying and meeting central government's skills requirements
Start with well managed responsibilities UK Departments have invested heavily in skills development. Government estimates that expenditure on formal training, including salary costs of departmental learning and development staff, was £275 million in 2009-10. NAO identified weaknesses of the system which start with devolved responsibilities, lead to: weak data, mis-profiled trainings, doubtful personal decisions, lack of well-targeted evaluation - and finish at more expensive buying-in and retaining key skills...
Full description
Start with well managed responsibilities UK Departments have invested heavily in skills development. Government estimates that expenditure on formal training, including salary costs of departmental learning and development staff, was £275 million in 2009-10. NAO identified weaknesses of the system which start with devolved responsibilities, lead to: weak data, mis-profiled trainings, doubtful personal decisions, lack of well-targeted evaluation - and finish at more expensive buying-in and retaining key skills...
Full description
National Audit Office
, issued in 2011
Risk cases: 6
The effectiveness of Official Development Assistance expenditure
Need of more coordination and transparency The audit of the UK's Official Development Assistance revealed among others: fragmented responsibilities and difficulties in review and reporting. These led to difficulties in assessment of effectiveness of the assistance and of progress in implementing the UK Aid Strategy.
Full description
Need of more coordination and transparency The audit of the UK's Official Development Assistance revealed among others: fragmented responsibilities and difficulties in review and reporting. These led to difficulties in assessment of effectiveness of the assistance and of progress in implementing the UK Aid Strategy.
Full description
National Audit Office
, issued in 2019
Risk cases: 4
Federal Human Resources Data
Internal control weaknesses may put mission at risk GAO audited the Enterprise Human Resources Integration payroll data warehose. The American auditors pointed at problems that may impede 'leverage of these data to meet its mission and allow others to make full use' of them. The critical internal contols areas to be improved in this cas are: completeness, accuracy, and validity of information, authorization, documentation, monitoring, results' evaluation.
Full description
Internal control weaknesses may put mission at risk GAO audited the Enterprise Human Resources Integration payroll data warehose. The American auditors pointed at problems that may impede 'leverage of these data to meet its mission and allow others to make full use' of them. The critical internal contols areas to be improved in this cas are: completeness, accuracy, and validity of information, authorization, documentation, monitoring, results' evaluation.
Full description
General Accountability Office
, issued in 2016
Risk cases: 2
Building and Implementing the Phoenix Pay System
Expensive IT project became a failure Phoenix project (development of states pay system) was an incomprehensible failure of project management and oversight. Phoenix executives prioritized certain aspects, such as schedule and budget, over other critical ones, such as functionality and security. Phoenix executives did not understand the importance of warnings that the Miramichi Pay Centre, departments and agencies, and the new system were not ready. They did not provide complete and accurate information to deputy ministers and associate deputy ministers of departments and agencies, including the Deputy Minister of Public Services and Procurement, when briefing them on Phoenix readiness for implementation.
Full description
Expensive IT project became a failure Phoenix project (development of states pay system) was an incomprehensible failure of project management and oversight. Phoenix executives prioritized certain aspects, such as schedule and budget, over other critical ones, such as functionality and security. Phoenix executives did not understand the importance of warnings that the Miramichi Pay Centre, departments and agencies, and the new system were not ready. They did not provide complete and accurate information to deputy ministers and associate deputy ministers of departments and agencies, including the Deputy Minister of Public Services and Procurement, when briefing them on Phoenix readiness for implementation.
Full description
Office of theAuditor Generalof Canada
, issued in 2018
Risk cases: 3
Open Data Trend Report 2015
How to activate the open data policy The Dutch SAI looks for ways to improve open data practice in the Netherlands. They point at experience of two leading countries: UK and US, and advise to: prepare a concrete action plan, to increase number of mandatory published data, to develop government-wide data inventory and to put open data to work.
Full description
How to activate the open data policy The Dutch SAI looks for ways to improve open data practice in the Netherlands. They point at experience of two leading countries: UK and US, and advise to: prepare a concrete action plan, to increase number of mandatory published data, to develop government-wide data inventory and to put open data to work.
Full description
Netherlands Court of Audits
, issued in 2015
Risk cases: 4
Homelessness
Homelessness grows despite increased spendings to reduce it British NAO analyses the root-causes of unsuccessful effort to reduce homelessness in England. They point at a side effect of the Goverment reform of welfare reform and at lack of full impact assessment.
Full description
Homelessness grows despite increased spendings to reduce it British NAO analyses the root-causes of unsuccessful effort to reduce homelessness in England. They point at a side effect of the Goverment reform of welfare reform and at lack of full impact assessment.
Full description
National Audit Office
, issued in 2016
Risk cases: 3