Report on the government’s processing of confidential data on persons and companies
Rigsrevisionen has examined how eight government institutions process confidential data on persons and companies in 11 selected IT systems. The report is based on IT audits carried out in connection ... with the annual audit in the spring 2014. The purpose of the audit was to assess whether confidential data on persons and companies are adequately protected by the government institutions. ... ... Inadequate protection of confidential data ... If a government institution does not protect confidential data to the extent necessary, the risk that third parties get unauthorized access to the data is very high. In opinion of the Danish SAI ... , inadequate protection of confidential data may also erode the citizens’ and companies’ confidence in government data security. That may eventually become a barrier for the continued efforts to implement ... e-government and make government administration more efficient.
Full description
Rigsrevisionen has examined how eight government institutions process confidential data on persons and companies in 11 selected IT systems. The report is based on IT audits carried out in connection ... with the annual audit in the spring 2014. The purpose of the audit was to assess whether confidential data on persons and companies are adequately protected by the government institutions. ... ... Inadequate protection of confidential data ... If a government institution does not protect confidential data to the extent necessary, the risk that third parties get unauthorized access to the data is very high. In opinion of the Danish SAI ... , inadequate protection of confidential data may also erode the citizens’ and companies’ confidence in government data security. That may eventually become a barrier for the continued efforts to implement ... e-government and make government administration more efficient.
Full description
National Audit Office of Denmark
, issued in 2014
Risk cases: 2
Federal Agencies Need to Address Aging Legacy Systems
Be aware of legacy IT risks The US government spends about 75 percent of the total amount budgeted for information technology on operations and maintenance. GAO reviewed Office of Management and Budget and 26 agencies, covering years 2010 through 2017 and recommends to develop a goal for spending measure and finalize guidance to identify and prioritize legacy IT needing to be modernized or replaced.
Full description
Be aware of legacy IT risks The US government spends about 75 percent of the total amount budgeted for information technology on operations and maintenance. GAO reviewed Office of Management and Budget and 26 agencies, covering years 2010 through 2017 and recommends to develop a goal for spending measure and finalize guidance to identify and prioritize legacy IT needing to be modernized or replaced.
Full description
General Accountability Office
, issued in 2016
Risk cases: 3
The National Offender Management Information System (NOMIS)
This report examines the reasons for the delays and cost increases to the original integrated information system and, since the moratorium imposed by the Minister of State in order to seek options ... for project’s cost reduction, the aims of the revised National Offender Management Service (NOMS) and the progress made, the impact of the delays and rescoping on the costs and benefits achieved, and NOMS ... ’ fitness to deliver. The aim of one integrated information system (C-NOMIS i.e. National Offender Management Information System) was to improve information sharing about offenders; address the lack ... Rescoping necessary, but not fully successful ... An initiative to build a single offender management IT system for the prison and probation services has not delivered value for money. The NAO investigation found the project had been hampered ... by poor management leading to a three-year delay, a doubling in project costs and reductions in scope and benefits.
Full description
This report examines the reasons for the delays and cost increases to the original integrated information system and, since the moratorium imposed by the Minister of State in order to seek options ... for project’s cost reduction, the aims of the revised National Offender Management Service (NOMS) and the progress made, the impact of the delays and rescoping on the costs and benefits achieved, and NOMS ... ’ fitness to deliver. The aim of one integrated information system (C-NOMIS i.e. National Offender Management Information System) was to improve information sharing about offenders; address the lack ... Rescoping necessary, but not fully successful ... An initiative to build a single offender management IT system for the prison and probation services has not delivered value for money. The NAO investigation found the project had been hampered ... by poor management leading to a three-year delay, a doubling in project costs and reductions in scope and benefits.
Full description
National Audit Office
, issued in 2009
Risk cases: 4