Traffic Ticketing information system
The audit included two areas of focus - the environment surrounding the Traffic Ticketing Information System - the System (designed to input, process, manage and collect payment for the traffic ... tickets) and also the internal environment of the System that guarantees the quality of its performance and safety. ... Security can hinder effectiveness ... SAI of Kuwait analysed system supporting collection of the traffic tickets - data input, processing and management. What was found was lack of basic safety measures, that hindered the effectiveness ... of the system.
Full description
The audit included two areas of focus - the environment surrounding the Traffic Ticketing Information System - the System (designed to input, process, manage and collect payment for the traffic ... tickets) and also the internal environment of the System that guarantees the quality of its performance and safety. ... Security can hinder effectiveness ... SAI of Kuwait analysed system supporting collection of the traffic tickets - data input, processing and management. What was found was lack of basic safety measures, that hindered the effectiveness ... of the system.
Full description
State Audit Bureau of Kuwait
, issued in 2014
Risk cases: 3
Parallel Audit on Biometric Passports - Overall Results (anonymised)
and implementing the regulation on standards for security features and biometrics in passports and travel documents issued by the member states. The aim is to develop and maintain efficient and secure biometric ... A biometric passport (or ePassport) contains biometric information which serves to authenticate the identity of travellers. Biometric passport management is the process of establishing ... passport production procedures (see page 5). ... EUROSAI ITWG: Parallel Audit on Biometric Passports ... Swiss SAI summed up results of audits concluded in seven countries (Belgium, Latvia, Lithuania, Norway, Portugal, Switzerland). The evaluation of the reported results showed that the overall passport ... process is generally under control while a couple of high-risk findings were identified in the non-process-specific assessments. In the non-process-specific assessments, most of the countries found ... deficiencies and weaknesses related to the IS/IT system and the IT management. Medium risks have been identified in the area of laws and regulations, cost-benefit realisation and transparency, as well
Full description
and implementing the regulation on standards for security features and biometrics in passports and travel documents issued by the member states. The aim is to develop and maintain efficient and secure biometric ... A biometric passport (or ePassport) contains biometric information which serves to authenticate the identity of travellers. Biometric passport management is the process of establishing ... passport production procedures (see page 5). ... EUROSAI ITWG: Parallel Audit on Biometric Passports ... Swiss SAI summed up results of audits concluded in seven countries (Belgium, Latvia, Lithuania, Norway, Portugal, Switzerland). The evaluation of the reported results showed that the overall passport ... process is generally under control while a couple of high-risk findings were identified in the non-process-specific assessments. In the non-process-specific assessments, most of the countries found ... deficiencies and weaknesses related to the IS/IT system and the IT management. Medium risks have been identified in the area of laws and regulations, cost-benefit realisation and transparency, as well
Full description
Swiss Federal Audit Office
, issued in 2015
Risk cases: 4
Prevention Activities Against Traffic Accidents
Performance Audit Studies covering certain IT Issues related to Prevention Activities Against Traffic Accidents. It aims to contribute to the continuous improvement of prevention activities against ... traffic accidents, which are dramatically leading to loss of life and property. Examination and evaluation of the Traffic Information Systems (TIS) under the traffic control headline. TIS' main purpose ... is to conduct the traffic control activities efficiently with the help of systematic data. Objective of this audit was to contribute to the continuous improvement of prevention activities against traffic ... ... ... You need a way more than IT, to make an IT system successful ... SAI of Turkey examined the Traffic Information Systems and found out that not only IT infrastructure determined the audited IT project's outcomes. There were also non-IT issues that decided: low ... quality of driving education, poor technical infrastruture, as well as lack of monitoring and coordination at prioritization stage.
Full description
Performance Audit Studies covering certain IT Issues related to Prevention Activities Against Traffic Accidents. It aims to contribute to the continuous improvement of prevention activities against ... traffic accidents, which are dramatically leading to loss of life and property. Examination and evaluation of the Traffic Information Systems (TIS) under the traffic control headline. TIS' main purpose ... is to conduct the traffic control activities efficiently with the help of systematic data. Objective of this audit was to contribute to the continuous improvement of prevention activities against traffic ... ... ... You need a way more than IT, to make an IT system successful ... SAI of Turkey examined the Traffic Information Systems and found out that not only IT infrastructure determined the audited IT project's outcomes. There were also non-IT issues that decided: low ... quality of driving education, poor technical infrastruture, as well as lack of monitoring and coordination at prioritization stage.
Full description
Turkish Court of Accounts
, issued in 2008
Risk cases: 4
The National Offender Management Information System (NOMIS)
This report examines the reasons for the delays and cost increases to the original integrated information system and, since the moratorium imposed by the Minister of State in order to seek options ... for project’s cost reduction, the aims of the revised National Offender Management Service (NOMS) and the progress made, the impact of the delays and rescoping on the costs and benefits achieved, and NOMS ... ’ fitness to deliver. The aim of one integrated information system (C-NOMIS i.e. National Offender Management Information System) was to improve information sharing about offenders; address the lack ... Rescoping necessary, but not fully successful ... An initiative to build a single offender management IT system for the prison and probation services has not delivered value for money. The NAO investigation found the project had been hampered ... by poor management leading to a three-year delay, a doubling in project costs and reductions in scope and benefits.
Full description
This report examines the reasons for the delays and cost increases to the original integrated information system and, since the moratorium imposed by the Minister of State in order to seek options ... for project’s cost reduction, the aims of the revised National Offender Management Service (NOMS) and the progress made, the impact of the delays and rescoping on the costs and benefits achieved, and NOMS ... ’ fitness to deliver. The aim of one integrated information system (C-NOMIS i.e. National Offender Management Information System) was to improve information sharing about offenders; address the lack ... Rescoping necessary, but not fully successful ... An initiative to build a single offender management IT system for the prison and probation services has not delivered value for money. The NAO investigation found the project had been hampered ... by poor management leading to a three-year delay, a doubling in project costs and reductions in scope and benefits.
Full description
National Audit Office
, issued in 2009
Risk cases: 4
Performance Audit of the Management of ICT in the Criminal Justice Sector
The Norwegian OAG has assesed how the Ministry of Justice and Public Security has discharged its responsibility for effiecient case processing through developing and applying Information ... and Communications Technology (ICT) in the criminal justice sector ... ... Unclear signals from a Ministry weaken development of ICT in the justice chain ... Points by SAI Norway: development of an overall rolling action plan based on the current ICT (Information and Communication Technology) strategy for the justice sector, performance-oriented ... reporting from the subordinate agencies, ensuring that the new ICT Police System takes into account other sub-sectors need for electronic interaction.
Full description
The Norwegian OAG has assesed how the Ministry of Justice and Public Security has discharged its responsibility for effiecient case processing through developing and applying Information ... and Communications Technology (ICT) in the criminal justice sector ... ... Unclear signals from a Ministry weaken development of ICT in the justice chain ... Points by SAI Norway: development of an overall rolling action plan based on the current ICT (Information and Communication Technology) strategy for the justice sector, performance-oriented ... reporting from the subordinate agencies, ensuring that the new ICT Police System takes into account other sub-sectors need for electronic interaction.
Full description
Office of the Auditor General of Norway
, issued in 2012
Risk cases: 2
Federal Agencies Need to Address Aging Legacy Systems
Be aware of legacy IT risks The US government spends about 75 percent of the total amount budgeted for information technology on operations and maintenance. GAO reviewed Office of Management and Budget and 26 agencies, covering years 2010 through 2017 and recommends to develop a goal for spending measure and finalize guidance to identify and prioritize legacy IT needing to be modernized or replaced.
Full description
Be aware of legacy IT risks The US government spends about 75 percent of the total amount budgeted for information technology on operations and maintenance. GAO reviewed Office of Management and Budget and 26 agencies, covering years 2010 through 2017 and recommends to develop a goal for spending measure and finalize guidance to identify and prioritize legacy IT needing to be modernized or replaced.
Full description
General Accountability Office