3
results found in
3 ms
Page 1
of 1
Information security work at nine agencies
Difficulties in achieving appropriate IT security Together with the Swedish NAO we assume that the picture that emerges at the agencies audited applies also to most of the other agencies in the public administration. The information security work is not given high enough priority in relation to the risks that exist. This applies to both the Government, which should have been clearer in its directions to agencies on this matter, and to agency managements, which did not give priority to the work of information security to the extent required. Much indicates that it is difficult for many agencies to achieve an appropriate level of information security work.
Full description
Difficulties in achieving appropriate IT security Together with the Swedish NAO we assume that the picture that emerges at the agencies audited applies also to most of the other agencies in the public administration. The information security work is not given high enough priority in relation to the risks that exist. This applies to both the Government, which should have been clearer in its directions to agencies on this matter, and to agency managements, which did not give priority to the work of information security to the extent required. Much indicates that it is difficult for many agencies to achieve an appropriate level of information security work.
Full description
Swedish National Audit Office
, issued in 2016
Risk cases: 4
Prevention Activities Against Traffic Accidents
Performance Audit Studies covering certain IT Issues related to Prevention Activities Against Traffic Accidents. It aims to contribute to the continuous improvement of prevention activities against ... traffic accidents, which are dramatically leading to loss of life and property. Examination and evaluation of the Traffic Information Systems (TIS) under the traffic control headline. TIS' main purpose ... is to conduct the traffic control activities efficiently with the help of systematic data. Objective of this audit was to contribute to the continuous improvement of prevention activities against traffic ... ... ... You need a way more than IT, to make an IT system successful ... SAI of Turkey examined the Traffic Information Systems and found out that not only IT infrastructure determined the audited IT project's outcomes. There were also non-IT issues that decided: low ... quality of driving education, poor technical infrastruture, as well as lack of monitoring and coordination at prioritization stage.
Full description
Performance Audit Studies covering certain IT Issues related to Prevention Activities Against Traffic Accidents. It aims to contribute to the continuous improvement of prevention activities against ... traffic accidents, which are dramatically leading to loss of life and property. Examination and evaluation of the Traffic Information Systems (TIS) under the traffic control headline. TIS' main purpose ... is to conduct the traffic control activities efficiently with the help of systematic data. Objective of this audit was to contribute to the continuous improvement of prevention activities against traffic ... ... ... You need a way more than IT, to make an IT system successful ... SAI of Turkey examined the Traffic Information Systems and found out that not only IT infrastructure determined the audited IT project's outcomes. There were also non-IT issues that decided: low ... quality of driving education, poor technical infrastruture, as well as lack of monitoring and coordination at prioritization stage.
Full description
Turkish Court of Accounts
, issued in 2008
Risk cases: 4
The National Offender Management Information System (NOMIS)
This report examines the reasons for the delays and cost increases to the original integrated information system and, since the moratorium imposed by the Minister of State in order to seek options ... for project’s cost reduction, the aims of the revised National Offender Management Service (NOMS) and the progress made, the impact of the delays and rescoping on the costs and benefits achieved, and NOMS ... ’ fitness to deliver. The aim of one integrated information system (C-NOMIS i.e. National Offender Management Information System) was to improve information sharing about offenders; address the lack ... Rescoping necessary, but not fully successful ... An initiative to build a single offender management IT system for the prison and probation services has not delivered value for money. The NAO investigation found the project had been hampered ... by poor management leading to a three-year delay, a doubling in project costs and reductions in scope and benefits.
Full description
This report examines the reasons for the delays and cost increases to the original integrated information system and, since the moratorium imposed by the Minister of State in order to seek options ... for project’s cost reduction, the aims of the revised National Offender Management Service (NOMS) and the progress made, the impact of the delays and rescoping on the costs and benefits achieved, and NOMS ... ’ fitness to deliver. The aim of one integrated information system (C-NOMIS i.e. National Offender Management Information System) was to improve information sharing about offenders; address the lack ... Rescoping necessary, but not fully successful ... An initiative to build a single offender management IT system for the prison and probation services has not delivered value for money. The NAO investigation found the project had been hampered ... by poor management leading to a three-year delay, a doubling in project costs and reductions in scope and benefits.
Full description
National Audit Office
, issued in 2009
Risk cases: 4
3
results found.
Page 1
of 1