Reports Search Reports Spatial Search Risk-cases Search Risk-cases Graph Traversal
3 results found in 3 ms Page 1 of 1
Preparations and realization of the State A-levels
The aim of the audit was to scrutinise the utilisation of the state budget and EU budget funds that had been spent on preparing and implementing the State A-levels examinations. The auditing ... operation was performed from May to November 2011. The audited period extended from January 1, 2005, to June 30, 2011; where relevant, the data from the previous period and the period until the end ... of the auditing operation were also scrutinized. Among the audited bodies were the Ministry of Education, the Education Result Survey Centre, and the National Institute for Further Education. The auditing operation ... ... Begin with good strategy ... Analyzing problems of state examinations system, Czech Republic SAI found that commonplace strategy effected in shortsighted planning, poor procurement and disadvantageous contracting.
Full description
Supreme Audit Office of Czech Republic , issued in 2011
Risk cases: 4
The management of the State Property and Funds while Information Systems Building for the Ministry of Defence
The aim of the audit was to examine management during process of extension and modernization of the current information systems and at building of new information systems for the needs ... of the Ministry of Defence or the Army of the Czech Republic. Operating of information systems is inseparably linked with the communication infrastructure, thus the technological shift to ICT was reviewed also ... in this connection. The stationary ICT systems are determined to support management of the Ministry of Defence in period of peace. They are also supposed as a tool of crisis management. The auditing operation covered ... ... Information systems not balanced with infrastructure ... Both organizational changes and inflexibility produce unbalanced plans which cause deiscrepancies between IS and infrastructure.
Full description
Supreme Audit Office , issued in 2005
Risk cases: 2
State funds spent on development, operation and using of data centres services
The aim of the audit was to scrutinise the management of funds spent on building and operating the national data centre (hereinafter “STC1 data centre”), including the expenditure of selected ... organisational units of the state on buying hosting, server-housing and other related services. The audited period was between 2010 and 2014; where relevant, the preceding period was also scrutinised. Audited ... entities: Ministry of the Interior (“MoI”); Ministry of Finance (“MoF”); STÁTNÍ TISKÁRNA CENIN, state firm (state banknote printing firm, hereinafter “STC” or “the state firm”). The audit was conducted ... ... Risks steming from uncoordinated strategy ... SAI of Czech Republic analysed consequences of failures in strategic IT management at the state level. Lack of coordination and implementation rules reduced practical role of the ministry whose task ... was to guard high quality standards for all crucial IT systems in the state administration. Next consecquences were (among others) risk of uneconomical results of large IT investment and risk of inefficient ... supply of services, as well as opposite results of workforce reduction.
Full description
Supreme Audit Office of Czech Republic , issued in 2015
Risk cases: 7
3 results found. Page 1 of 1