Evaluation of the effectiveness of implementation and compliance with regulatory enactments and the legal framework of the project “E-government Portfolio”
The objective of the audit is to evaluate the effectiveness of implementation and compliance with regulatory enactments and the legal framework of the project “Egovernment Portfolio” of the national ... programme of the European Regional Development Fund (hereinafter: ERDF) of the European Union (hereinafter: EU), “Development and improvement of the infrastructural foundation for electronic governance”. ... ... Funds to absorb but no efficient project methodology? Be prepared for troubles ... Wide list of problems that can be met when more care is received by 'absorb funds' objective than by clear vision what and how can be improved. SAI Latvia's analysis shows how dangerous it can ... be for both effectiveness and financial management.
Full description
The objective of the audit is to evaluate the effectiveness of implementation and compliance with regulatory enactments and the legal framework of the project “Egovernment Portfolio” of the national ... programme of the European Regional Development Fund (hereinafter: ERDF) of the European Union (hereinafter: EU), “Development and improvement of the infrastructural foundation for electronic governance”. ... ... Funds to absorb but no efficient project methodology? Be prepared for troubles ... Wide list of problems that can be met when more care is received by 'absorb funds' objective than by clear vision what and how can be improved. SAI Latvia's analysis shows how dangerous it can ... be for both effectiveness and financial management.
Full description
State Audit Office of Latvia
, issued in 2010
Risk cases: 3
Material–technical supply of the State Police
The main aim of the audit was to obtain assurance about whether the State budget funds allocated for material–technical supply of functions of the State Police were legitimate and efficient ... . The audit included inspections performed at the State Police, the Ministry of the Interior and the Information Centre and focused on: the Biometric data processing system and the Criminal Procedure ... information system. ... ... Essential role of pre-project evaluation ... SAI of Latvia reveals chain of events that lead to unsuccessful implemenation of two important IS of the State police. What started with an absence of the strategy ended up with budget, time ... overruns and an IS not ready for effiecient use.
Full description
The main aim of the audit was to obtain assurance about whether the State budget funds allocated for material–technical supply of functions of the State Police were legitimate and efficient ... . The audit included inspections performed at the State Police, the Ministry of the Interior and the Information Centre and focused on: the Biometric data processing system and the Criminal Procedure ... information system. ... ... Essential role of pre-project evaluation ... SAI of Latvia reveals chain of events that lead to unsuccessful implemenation of two important IS of the State police. What started with an absence of the strategy ended up with budget, time ... overruns and an IS not ready for effiecient use.
Full description
State Audit Office of the Republic of Latvia
, issued in 2013
Risk cases: 6
Has Public Administration Used All Opportunities for Efficient Management of ICT Infrastructure?
Efficient Management of ICT Infrastructure Centralised management of ICT services and infrastructure would allow the institutions to optimise in long run their resources – financial, human, material and technical. However, we observed during the audit that the move towards ICT centralisation and single data centres has ceased. The different ministries and even the institutions subordinated to the same ministry do not cooperate sufficiently with each other regarding the ICT management, maintenance, and infrastructure placement. They rather choose to maintain their own, sometimes even several, data centres.
Full description
Efficient Management of ICT Infrastructure Centralised management of ICT services and infrastructure would allow the institutions to optimise in long run their resources – financial, human, material and technical. However, we observed during the audit that the move towards ICT centralisation and single data centres has ceased. The different ministries and even the institutions subordinated to the same ministry do not cooperate sufficiently with each other regarding the ICT management, maintenance, and infrastructure placement. They rather choose to maintain their own, sometimes even several, data centres.
Full description
State Audit Office of the Republic of Latvia
, issued in 2019
Risk cases: 3