Building and Implementing the Phoenix Pay System
Expensive IT project became a failure Phoenix project (development of states pay system) was an incomprehensible failure of project management and oversight. Phoenix executives prioritized certain aspects, such as schedule and budget, over other critical ones, such as functionality and security. Phoenix executives did not understand the importance of warnings that the Miramichi Pay Centre, departments and agencies, and the new system were not ready. They did not provide complete and accurate information to deputy ministers and associate deputy ministers of departments and agencies, including the Deputy Minister of Public Services and Procurement, when briefing them on Phoenix readiness for implementation.
Full description
Expensive IT project became a failure Phoenix project (development of states pay system) was an incomprehensible failure of project management and oversight. Phoenix executives prioritized certain aspects, such as schedule and budget, over other critical ones, such as functionality and security. Phoenix executives did not understand the importance of warnings that the Miramichi Pay Centre, departments and agencies, and the new system were not ready. They did not provide complete and accurate information to deputy ministers and associate deputy ministers of departments and agencies, including the Deputy Minister of Public Services and Procurement, when briefing them on Phoenix readiness for implementation.
Full description
Office of theAuditor Generalof Canada
, issued in 2018
Risk cases: 3
Management and protection of assets in the field of the information-communication technologies at the ME SR
) with emphasis on the use of the information technology (IT) services provided by the third parties. The vast amount of irregularities was found, especially many cases of failure to comply with the standards ... The Supreme Audit office of the Slovak Republic (SAO SR) has conducted the audit at the Ministry of Environment of the Slovak Republic (ME SR) for the audit period 2011 and 2012 to examine ... the compliance with the generally binding legal regulations and the general statues in the field of the information-communication technologies (ICT) and the information systems of the public administration (ISPA ... ... Started from contracting, ended in security ... The perceptive and filled with findings audit - conducted by the Slovak SAI - discovered the list of issues which started in careless contracting procedures, failure to update the development concept ... and ended in exposing the organization to high security risks.
Full description
) with emphasis on the use of the information technology (IT) services provided by the third parties. The vast amount of irregularities was found, especially many cases of failure to comply with the standards ... The Supreme Audit office of the Slovak Republic (SAO SR) has conducted the audit at the Ministry of Environment of the Slovak Republic (ME SR) for the audit period 2011 and 2012 to examine ... the compliance with the generally binding legal regulations and the general statues in the field of the information-communication technologies (ICT) and the information systems of the public administration (ISPA ... ... Started from contracting, ended in security ... The perceptive and filled with findings audit - conducted by the Slovak SAI - discovered the list of issues which started in careless contracting procedures, failure to update the development concept ... and ended in exposing the organization to high security risks.
Full description
Supreme Audit Office of the Slovak Republic
, issued in 2012
Risk cases: 4
Results of the development of the state’s information systems
The National Audit Office has repeatedly audited the management and development of the state’s information technology (IT) area in the last ten years. The last audit was performed in 2005. After that ... , several measures have been implemented in the state to organise the development better and to guarantee that the systems are compatible. This audit gives an opinion of the results of development project ... management and the state’s coordination mechanism in this process. ... ... Success and failure depend on preparation ... Conclusions of performance IT audit based on a sample of government projects: business portal, land register, e-police, fire safety monitoring system, childcare information system and the document ... management system of the Defence Forces. Key problems and discussion with auditees are presented.
Full description
The National Audit Office has repeatedly audited the management and development of the state’s information technology (IT) area in the last ten years. The last audit was performed in 2005. After that ... , several measures have been implemented in the state to organise the development better and to guarantee that the systems are compatible. This audit gives an opinion of the results of development project ... management and the state’s coordination mechanism in this process. ... ... Success and failure depend on preparation ... Conclusions of performance IT audit based on a sample of government projects: business portal, land register, e-police, fire safety monitoring system, childcare information system and the document ... management system of the Defence Forces. Key problems and discussion with auditees are presented.
Full description
National Audit Office of Estonia
, issued in 2010
Risk cases: 3
IT Police Systems
and effectiveness of their work. Audit explained the reason of failure in the case of E-police station project and success in the case of CSS. Although some irregularities occurred in both cases, careful planning ... Implementation by the Polish Police of two IT projects (E-police station and Command Support System - CSS) was audited. Both systems were to relieve the Police officers and increase the quality ... and organization of the project turned out to make the difference. Accordance with the public procurement law was not part of the audit as a separate investigation in that matter was carried by respective Polish ... ... A textbook example of how not to implement the IT projects ... Polish NIK compared the implementation of two flagship IT projects of the Police HQ: successful 'Command Support System' and problematic 'E-police station'. List of interesting problems appeared...
Full description
and effectiveness of their work. Audit explained the reason of failure in the case of E-police station project and success in the case of CSS. Although some irregularities occurred in both cases, careful planning ... Implementation by the Polish Police of two IT projects (E-police station and Command Support System - CSS) was audited. Both systems were to relieve the Police officers and increase the quality ... and organization of the project turned out to make the difference. Accordance with the public procurement law was not part of the audit as a separate investigation in that matter was carried by respective Polish ... ... A textbook example of how not to implement the IT projects ... Polish NIK compared the implementation of two flagship IT projects of the Police HQ: successful 'Command Support System' and problematic 'E-police station'. List of interesting problems appeared...
Full description
Supreme Audit Office of Poland
, issued in 2013
Risk cases: 5
Management and protection of assets in the field of the information-communication technologies at the AO SR
The Supreme Audit office of the Slovak Republic (SAO SR) has executed the audit at the Antimonopoly Office of the Slovak Republic (AO SR) for the audit period 2010 and 2011 to verify the operation ... and security of the information-communication technologies (ICT) and the information systems of the public administration (ISPA) as well as the state assets administration, the economy and disposal ... with the state assets, the compliance with the generally binding legal regulations and the general statues in the field of the ISPA. There were 24 irregularities found, mainly in the field of the protection ... ... ... Failure to comply with the law leads to unnecessary jeopardizing of data security ... The audit in the field of the information systems of the public administration (ISPA) executed by the Supreme Audit Office of the Slovak Republic at the Antimonopoly Office of the Slovak Republic (AO ... SR) exposed several deficiencies related to the information systems and the data security as a consequence of a lawbreaking.
Full description
The Supreme Audit office of the Slovak Republic (SAO SR) has executed the audit at the Antimonopoly Office of the Slovak Republic (AO SR) for the audit period 2010 and 2011 to verify the operation ... and security of the information-communication technologies (ICT) and the information systems of the public administration (ISPA) as well as the state assets administration, the economy and disposal ... with the state assets, the compliance with the generally binding legal regulations and the general statues in the field of the ISPA. There were 24 irregularities found, mainly in the field of the protection ... ... ... Failure to comply with the law leads to unnecessary jeopardizing of data security ... The audit in the field of the information systems of the public administration (ISPA) executed by the Supreme Audit Office of the Slovak Republic at the Antimonopoly Office of the Slovak Republic (AO ... SR) exposed several deficiencies related to the information systems and the data security as a consequence of a lawbreaking.
Full description
Supreme Audit Office of the Slovak Republic
, issued in 2011
Risk cases: 4
Protection of automatically processed personal data
Over the past few years, a number of legal, management, supervision, information, and methodological issues related to the protection of personal data have piled up. As they have not been fully ... resolved,the National Audit Office conducted an audit to assess the efficiency of the protection and supervision of automatically processed personal data and to check whether: - the regulation of personal data ... protection conforms to the data processing practices; - personal data is properly processed at public sector bodies; - the State Data Protection Inspectorate (SDPI) performs sufficient supervision ... ... Data protection needs a long term strategy ... not addressed by the existing legislation. Moreover, SAI of Lithuania revealed failures in organization and control of personal data protection by public sector. ... Rapid development of information and communication technology continuously brings about issues of personal data protection. Due to lack of long-term vision in this area they are frequently
Full description
Over the past few years, a number of legal, management, supervision, information, and methodological issues related to the protection of personal data have piled up. As they have not been fully ... resolved,the National Audit Office conducted an audit to assess the efficiency of the protection and supervision of automatically processed personal data and to check whether: - the regulation of personal data ... protection conforms to the data processing practices; - personal data is properly processed at public sector bodies; - the State Data Protection Inspectorate (SDPI) performs sufficient supervision ... ... Data protection needs a long term strategy ... not addressed by the existing legislation. Moreover, SAI of Lithuania revealed failures in organization and control of personal data protection by public sector. ... Rapid development of information and communication technology continuously brings about issues of personal data protection. Due to lack of long-term vision in this area they are frequently
Full description
National Audit Office of the Republic of Lithuania
, issued in 2013
Risk cases: 2
State funds spent on development, operation and using of data centres services
The aim of the audit was to scrutinise the management of funds spent on building and operating the national data centre (hereinafter “STC1 data centre”), including the expenditure of selected ... organisational units of the state on buying hosting, server-housing and other related services. The audited period was between 2010 and 2014; where relevant, the preceding period was also scrutinised. Audited ... entities: Ministry of the Interior (“MoI”); Ministry of Finance (“MoF”); STÁTNÍ TISKÁRNA CENIN, state firm (state banknote printing firm, hereinafter “STC” or “the state firm”). The audit was conducted ... ... Risks steming from uncoordinated strategy ... SAI of Czech Republic analysed consequences of failures in strategic IT management at the state level. Lack of coordination and implementation rules reduced practical role of the ministry whose task ... was to guard high quality standards for all crucial IT systems in the state administration. Next consecquences were (among others) risk of uneconomical results of large IT investment and risk of inefficient ... supply of services, as well as opposite results of workforce reduction.
Full description
The aim of the audit was to scrutinise the management of funds spent on building and operating the national data centre (hereinafter “STC1 data centre”), including the expenditure of selected ... organisational units of the state on buying hosting, server-housing and other related services. The audited period was between 2010 and 2014; where relevant, the preceding period was also scrutinised. Audited ... entities: Ministry of the Interior (“MoI”); Ministry of Finance (“MoF”); STÁTNÍ TISKÁRNA CENIN, state firm (state banknote printing firm, hereinafter “STC” or “the state firm”). The audit was conducted ... ... Risks steming from uncoordinated strategy ... SAI of Czech Republic analysed consequences of failures in strategic IT management at the state level. Lack of coordination and implementation rules reduced practical role of the ministry whose task ... was to guard high quality standards for all crucial IT systems in the state administration. Next consecquences were (among others) risk of uneconomical results of large IT investment and risk of inefficient ... supply of services, as well as opposite results of workforce reduction.
Full description
Supreme Audit Office of Czech Republic
, issued in 2015
Risk cases: 7
Management and implementation of 1BestariNet
1BestariNet Service Project (1BestariNet) is an initiative undertaken by the Malaysian Ministry of Education (MOE) to replace and enhance ICT connectivity in schools. It is an enhancement ... to the SchoolNet service which terminated on 31 December 2010 with emphasis on end-to-end solutions (E2E) network services together with Virtual Learning Environment (VLE). Under this project, 10,000 primary ... and secondary public schools in Malaysia are equipped with high-speed 4G Internet access and a virtual learning platform, providing high-speed internet connectivity and access to a world-class Integrated Learning ... ... To answer big risks in IT systems development you need all levels of organisation ... Audit of 1BestariNet is presented by the Malaysian National Audit Department together with other IT projects reviewed. A result is this concise and instructive list of lessons learnt and failures ... to be avoided. To maximize performance and minimize vendor lock-in you need a lot of concerted effort by top and line management, as well as users ready to work with new tools.
Full description
1BestariNet Service Project (1BestariNet) is an initiative undertaken by the Malaysian Ministry of Education (MOE) to replace and enhance ICT connectivity in schools. It is an enhancement ... to the SchoolNet service which terminated on 31 December 2010 with emphasis on end-to-end solutions (E2E) network services together with Virtual Learning Environment (VLE). Under this project, 10,000 primary ... and secondary public schools in Malaysia are equipped with high-speed 4G Internet access and a virtual learning platform, providing high-speed internet connectivity and access to a world-class Integrated Learning ... ... To answer big risks in IT systems development you need all levels of organisation ... Audit of 1BestariNet is presented by the Malaysian National Audit Department together with other IT projects reviewed. A result is this concise and instructive list of lessons learnt and failures ... to be avoided. To maximize performance and minimize vendor lock-in you need a lot of concerted effort by top and line management, as well as users ready to work with new tools.
Full description
National Audit Department of Malaysia
, issued in 2013
Risk cases: 4
The National Offender Management Information System (NOMIS)
This report examines the reasons for the delays and cost increases to the original integrated information system and, since the moratorium imposed by the Minister of State in order to seek options ... for project’s cost reduction, the aims of the revised National Offender Management Service (NOMS) and the progress made, the impact of the delays and rescoping on the costs and benefits achieved, and NOMS ... ’ fitness to deliver. The aim of one integrated information system (C-NOMIS i.e. National Offender Management Information System) was to improve information sharing about offenders; address the lack ... Rescoping necessary, but not fully successful ... An initiative to build a single offender management IT system for the prison and probation services has not delivered value for money. The NAO investigation found the project had been hampered ... by poor management leading to a three-year delay, a doubling in project costs and reductions in scope and benefits.
Full description
This report examines the reasons for the delays and cost increases to the original integrated information system and, since the moratorium imposed by the Minister of State in order to seek options ... for project’s cost reduction, the aims of the revised National Offender Management Service (NOMS) and the progress made, the impact of the delays and rescoping on the costs and benefits achieved, and NOMS ... ’ fitness to deliver. The aim of one integrated information system (C-NOMIS i.e. National Offender Management Information System) was to improve information sharing about offenders; address the lack ... Rescoping necessary, but not fully successful ... An initiative to build a single offender management IT system for the prison and probation services has not delivered value for money. The NAO investigation found the project had been hampered ... by poor management leading to a three-year delay, a doubling in project costs and reductions in scope and benefits.
Full description
National Audit Office
, issued in 2009
Risk cases: 4
Australian Taxation Office: Administration of Australian Business Number Registrations
More elligibility and data integrity needed The Australian Business Number (ABN) and Australian Business Register initiatives were implemented as part of theGovernment's comprehensive reform of the taxation system in 2000. Their introduction involved challenging issues of technology and governance , including the imperative to process and register significant numbers of applications in a short time. Overall, the Australian SAI concluded that the ABN registration process is operating effectively. However, matters relating to the eligibility of some ABN applicants need to be reviewed. Further, some data integrity issues remain outstanding.
Full description
More elligibility and data integrity needed The Australian Business Number (ABN) and Australian Business Register initiatives were implemented as part of theGovernment's comprehensive reform of the taxation system in 2000. Their introduction involved challenging issues of technology and governance , including the imperative to process and register significant numbers of applications in a short time. Overall, the Australian SAI concluded that the ABN registration process is operating effectively. However, matters relating to the eligibility of some ABN applicants need to be reviewed. Further, some data integrity issues remain outstanding.
Full description
The Australian National Audit Office
, issued in 2003
Risk cases: 3