Reports Search Reports Spatial Search Risk-cases Search Risk-cases Graph Traversal
45 results found in 13 ms Page 1 of 5
Audit of the key ICT project federal GEVER programme Federal Chancellery
During the first stage, two new GEVER (electronic records and process management) products were procured in an open WTO tender within the framework of the two-product strategy (federal GEVER WTO ... procurement project). CHF 1.6 million was spent on these. The departments and Federal Chancellery (departments/FCh) had to choose one of the two products within three months of the contract being awarded. ... ... Advanced process management system's cost-effectiveness and deadlines at risk ... Ever since 1990, sequential controls and file management have been part of the Federal Administration's IT landscape (GEVER business administration). Significant obstacles have to be overcome ... in order to ensure the successful creation and introduction of GEVER. Previous efforts did not have any widespread success and led to a diverse GEVER landscape. The federal GEVER project has now laid ... the foundations for simplification and centralisation.
Full description
Swiss Federal Audit Office , issued in 2015
Risk cases: 2
OMB and Agencies Need to Focus Continued Attention on Implementing Reform Law
How to invest efficiently in IT IT investments are large and growing position in annual budgets. Historically, they have frequently failed, incurred cost overruns and schedule slippages, or contributed little to mission-related outcomes. GAO recommendations focus on the oversight and execution of the data center consolidation initiative, the accuracy and reliability of the IT Dashboard, and incremental development policies.
Full description
General Accountability Office , issued in 2016
Risk cases: 3
Australian Taxation Office: Administration of Australian Business Number Registrations
More elligibility and data integrity needed The Australian Business Number (ABN) and Australian Business Register initiatives were implemented as part of theGovernment's comprehensive reform of the taxation system in 2000. Their introduction involved challenging issues of technology and governance , including the imperative to process and register significant numbers of applications in a short time. Overall, the Australian SAI concluded that the ABN registration process is operating effectively. However, matters relating to the eligibility of some ABN applicants need to be reviewed. Further, some data integrity issues remain outstanding.
Full description
The Australian National Audit Office , issued in 2003
Risk cases: 3
Identifying and meeting central government's skills requirements
Start with well managed responsibilities UK Departments have invested heavily in skills development. Government estimates that expenditure on formal training, including salary costs of departmental learning and development staff, was £275 million in 2009-10. NAO identified weaknesses of the system which start with devolved responsibilities, lead to: weak data, mis-profiled trainings, doubtful personal decisions, lack of well-targeted evaluation - and finish at more expensive buying-in and retaining key skills...
Full description
National Audit Office , issued in 2011
Risk cases: 6
Housing in England: overview
Efforts to support housing Even if housebuilding in England has not kept pace with need and there has been a reduction in social rented homes, significant advantages can be enjoyed: an increase in home ownership and in the number of private rented homes. The quality of housing improved in recent years too. The National Audit Office has reviewed critical elements of the housing being one of the government's key priorities. Looking for risks, they found that a potential conflict of objectives can lead to tensions in delivery.
Full description
National Audit Office , issued in 2017
Risk cases: 2
FEMA Needs to Address Management Weaknesses to Improve Its Systems
Controls in emergency management GAO audited the agency of the Department of Homeland Security, responsible for federal efforts to mitigate, respond to, and recover from disasters. American auditors recommend that the agency fully define its investment board’s roles and responsibilities and procedures for selecting and overseeing investments, update its strategic plan and complete plans for IT modernization, and establish time frames for completing workforce planning efforts. The agency should also establish policies and guidance for implementing key IT management controls.
Full description
General Accountability Office , issued in 2016
Risk cases: 4
General and Creation Control of the Information Systems of the Ministry of Foreign Affairs
achieved considerable progress in the management of the information systems. The auditors reviewed and assessed all key elements of the process. ... The objective of the audit was to assess general and creation control of the information systems of the Ministry of Foreign Affairs. Since the beginning of 2009, the Ministry of Foreign Affairs has ... Overview of problems - area by area ... SAI Lithuania looked into all critical elements of a Ministry's information system, starting from IT architecture, through information security to automation of data processing.
Full description
National Audit Office of the Republic of Lithuania , issued in 2013
Risk cases: 4
Report on the problems connected with the development and implementation of the digitally based Shared Medication Record
The purpose of the examination was to assess whether the department of the Danish Ministry of Health, the Danish National eHealth Authority (NHA) and the five regions that are responsible ... for the hospitals have made an adequate effort to develop and implement the Shared Medication Record (SMR). With the SMR, data on the citizens’ medication can be shared across hospitals, general practitioners, etc ... . and relevant health staff and the patients have direct digital access to updated medical data round the clock. The report answers the following questions: 1) Has the Ministry of Health and the NHA provided ... ... Involvement of key participants necessary from the very beginning ... and processes leading to implementation problems, governance not involving key players, and IT security organisation. ... Digitally based Shared Medication Record is basis of the complex healthcare system. Rigsrevisionen analysed unsolved issues related to unclear business case, insufficient analysis of work flows
Full description
National Audit Office of Denmark , issued in 2014
Risk cases: 2
Results of the development of the state’s information systems
The National Audit Office has repeatedly audited the management and development of the state’s information technology (IT) area in the last ten years. The last audit was performed in 2005. After that ... , several measures have been implemented in the state to organise the development better and to guarantee that the systems are compatible. This audit gives an opinion of the results of development project ... management and the state’s coordination mechanism in this process. ... ... Success and failure depend on preparation ... management system of the Defence Forces. Key problems and discussion with auditees are presented. ... Conclusions of performance IT audit based on a sample of government projects: business portal, land register, e-police, fire safety monitoring system, childcare information system and the document
Full description
National Audit Office of Estonia , issued in 2010
Risk cases: 3
Homeland Security. Oversight of Neglected Human Resources Information Technology Investment Is Needed
Human resources IT investments get stuck in management's lack of interest Although the Human Resources Information Technology (HRIT) investment was initiated about 12 years ago with the intent to consolidate, integrate, and modernize the department's human resources IT infrastructure, the Department of Homeland Security (DHS) has made very limited progress in achieving these goals. HRIT's minimally involved executive steering committee during a time when significant problems were occurring was a key factor in the lack of progress. This is particularly problematic given that the department's ability to efficiently and effectively carry out its mission is significantly hampered by its fragmented human resources. DHS's ineffective management of HRIT, such as the lack of an updated schedule and a life-cycle cost estimate, also contributed to the neglect this investment has experienced. DHS will be limited in efficiently tracking and reporting accurate, comprehensive performance and learning management data across the organization, and could risk further implementation delays.
Full description
US Government Accountability Office , issued in 2016
Risk cases: 1
45 results found. Page 1 of 5 next