Information Technology Cost Estimation Agencies Need to Address Significant Weakness in Policies and Practices
and agencies have appropriately implement costestimating policies an procedures(four caracteristics of a reliable cost estimation: comprehensive, well-documented, accurate, credible). ... To estimate reliable cost for the sucess of an IT program by providing the basis for the informed decision making and realistic budget information. To assess the extent to which selected departments ... IT cost estimation ... Check out what may go wrong with the information technology cost estimation. Results of the US GAO audit can help to identify high risk areas: comprehensiveness of estimations, their documentation ... , lack of adequacy and inadequate implementation.
Full description
General Accountability Office , issued in 2012
Risk cases: 4
Cost-intensive data centres stood idle for years
Idle data centres As found by the German SAI, some of costly Federal data centres stood largely idle. The Ministry failed to adequately assess the project risks. The Ministry needs to avoid similar shortcomings in the proposed federal IT consolidation project.
Full description
Bundesrechnungshof , issued in 2016
Risk cases: 1
Electronic Health Records - VA Needs to Identify and Report Existing System Costs
Difficulties after 30 years of decentralized development The US Department of Veterans Affairs provides health care services to approximately 9 million veterans and their families. However, the IT system they use is more than 30 years old, is costly to maintain, and does not fully support exchanging health data. The US GAO, analyzed the system's modenization plans and found serious problems with definition and cost estimation.
Full description
US Government Accountability Office , issued in 2019
Risk cases: 3
The Annual Municipal Accounts as a basis for comparing municipalities - are the cost indicator reliable?
Municipal accounting: more standardized or more controlled Municipalities report among others, their costs, which cannot be directly attributed to any specific activity, product, or service. Standardized taxonomies exist, but they are not applied uniformly. Swedish NAO traces ramifications: lower ability to compare municipalities' data and need of more central level control.
Full description
Swedish National Audit Office , issued in 2018
Risk cases: 3
The protection of valuable forest
Protection of valuable forest Protection of valuable forest land is an important mean of achieving the environmental quality objectives. Governments can establish formal protection of forests through the formation of national parks, biotope conservation areas, nature reserves or by signing nature conservation agreements. Beyond the state's formal protection of forests, the forest owners themselves are also expected to contribute through voluntary set-asides of forest. From a state perspective, it is important to investigate whether or not the resources for formal protection are being used cost-effectively. However, in order to achieve cost-effective formal protection work, the state also needs to address forest owners' voluntary set asides.
Full description
Swedish National Audit Office , issued in 2018
Risk cases: 4
OMB and Agencies Need to Focus Continued Attention on Implementing Reform Law
How to invest efficiently in IT IT investments are large and growing position in annual budgets. Historically, they have frequently failed, incurred cost overruns and schedule slippages, or contributed little to mission-related outcomes. GAO recommendations focus on the oversight and execution of the data center consolidation initiative, the accuracy and reliability of the IT Dashboard, and incremental development policies.
Full description
General Accountability Office , issued in 2016
Risk cases: 3
Audit of the key ICT project federal GEVER programme Federal Chancellery
During the first stage, two new GEVER (electronic records and process management) products were procured in an open WTO tender within the framework of the two-product strategy (federal GEVER WTO ... procurement project). CHF 1.6 million was spent on these. The departments and Federal Chancellery (departments/FCh) had to choose one of the two products within three months of the contract being awarded. ... ... Advanced process management system's cost-effectiveness and deadlines at risk ... Ever since 1990, sequential controls and file management have been part of the Federal Administration's IT landscape (GEVER business administration). Significant obstacles have to be overcome ... in order to ensure the successful creation and introduction of GEVER. Previous efforts did not have any widespread success and led to a diverse GEVER landscape. The federal GEVER project has now laid ... the foundations for simplification and centralisation.
Full description
Swiss Federal Audit Office , issued in 2015
Risk cases: 2
Homeland Security. Oversight of Neglected Human Resources Information Technology Investment Is Needed
Human resources IT investments get stuck in management's lack of interest Although the Human Resources Information Technology (HRIT) investment was initiated about 12 years ago with the intent to consolidate, integrate, and modernize the department's human resources IT infrastructure, the Department of Homeland Security (DHS) has made very limited progress in achieving these goals. HRIT's minimally involved executive steering committee during a time when significant problems were occurring was a key factor in the lack of progress. This is particularly problematic given that the department's ability to efficiently and effectively carry out its mission is significantly hampered by its fragmented human resources. DHS's ineffective management of HRIT, such as the lack of an updated schedule and a life-cycle cost estimate, also contributed to the neglect this investment has experienced. DHS will be limited in efficiently tracking and reporting accurate, comprehensive performance and learning management data across the organization, and could risk further implementation delays.
Full description
US Government Accountability Office , issued in 2016
Risk cases: 1
Results of the development of the state’s information systems
The National Audit Office has repeatedly audited the management and development of the state’s information technology (IT) area in the last ten years. The last audit was performed in 2005. After that ... , several measures have been implemented in the state to organise the development better and to guarantee that the systems are compatible. This audit gives an opinion of the results of development project ... management and the state’s coordination mechanism in this process. ... ... Success and failure depend on preparation ... Conclusions of performance IT audit based on a sample of government projects: business portal, land register, e-police, fire safety monitoring system, childcare information system and the document ... management system of the Defence Forces. Key problems and discussion with auditees are presented.
Full description
National Audit Office of Estonia , issued in 2010
Risk cases: 3
The National Government Service Centre – Has administration become more effective?
The purpose of this audit has been to investigate whether the Service Centre has made administrative operational support functions taken over from client agencies more effective, and to find ... explanations for the results so far achieved by the Service Centre. The audit has also aspired to illustrate how agencies that do not subscribe to the services regard their potential for doing so ... . These viewpoints have been analysed with a special focus on the conditions that applied to the Service Centre when it was formed and the measures taken by the Government and the Service Centre in the first years. ... ... Has Swedish public administration become more effective? ... The Service Centre – payroll and financial administration IT system for Swedish public agencies under the government – has achieved the target of a subscription rate of 25 per cent of the total ... number of state employees. However, subscription to the Service Centre was initially slower than the Government had predicted and meant lower revenues than expected in autumn 2013. The Service Centre ... then introduced a rigorous review of its expenditure, for example for some planned development initiatives for internal procedures and support systems.<br/>The Swedish NAO noted that the Government’s steering
Full description
Swedish National Audit Office , issued in 2016
Risk cases: 2