Central government staff costs
Results of staff reductions The British NAO found that departments had significantly reduced numbers of their civil servants and of course salary costs at the same time. But they reduced staff numbers mainly by minimising recruitment, and the age profile of the civil service has changed. NAO pays a lot attention to what effect this has had on the future pipeline of talent and skills. It reminds also that the departments need long-term operating models to work efficiently with the staff reduced.
Full description
National Audit Office , issued in 2015
Risk cases: 5
Electronic Health Records - VA Needs to Identify and Report Existing System Costs
Difficulties after 30 years of decentralized development The US Department of Veterans Affairs provides health care services to approximately 9 million veterans and their families. However, the IT system they use is more than 30 years old, is costly to maintain, and does not fully support exchanging health data. The US GAO, analyzed the system's modenization plans and found serious problems with definition and cost estimation.
Full description
US Government Accountability Office , issued in 2019
Risk cases: 3
Performance measurement by regulators
Performance measurement for regulators Primary adressees of this good practice guide - by the British NAO - are regulators, the public institutions established for making sure that an industry or system works legally and fairly. But we are sure that many more can find this guidance useful - including auditors. NAO presents a comprehensible framework for performance measurement and hints how to focus on influence that regulators can use.
Full description
National Audit Office , issued in 2016
Risk cases: 2
Improved Planning and Performance Measures Are Needed to Help Ensure Successful Technology Modernization
Massive modernization effort needs coordination Social security issues can touch lives of many. Information technology in this area are increasingly costly and difficult to maintain. GAO is recommending to develop comprehensive metrics to effectively gauge modernization progress; complete comprehensive strategic planning, including its enterprise architecture; and define the new roles and responsibilities to help ensure effective oversight.
Full description
General Accountability Office , issued in 2012
Risk cases: 3
Open Data Trend Report 2015
How to activate the open data policy The Dutch SAI looks for ways to improve open data practice in the Netherlands. They point at experience of two leading countries: UK and US, and advise to: prepare a concrete action plan, to increase number of mandatory published data, to develop government-wide data inventory and to put open data to work.
Full description
Netherlands Court of Audits , issued in 2015
Risk cases: 4
Federal Human Resources Data
Internal control weaknesses may put mission at risk GAO audited the Enterprise Human Resources Integration payroll data warehose. The American auditors pointed at problems that may impede 'leverage of these data to meet its mission and allow others to make full use' of them. The critical internal contols areas to be improved in this cas are: completeness, accuracy, and validity of information, authorization, documentation, monitoring, results' evaluation.
Full description
General Accountability Office , issued in 2016
Risk cases: 2
Performance Audit of the Management of ICT in the Criminal Justice Sector
The Norwegian OAG has assesed how the Ministry of Justice and Public Security has discharged its responsibility for effiecient case processing through developing and applying Information ... and Communications Technology (ICT) in the criminal justice sector ... ... Unclear signals from a Ministry weaken development of ICT in the justice chain ... Points by SAI Norway: development of an overall rolling action plan based on the current ICT (Information and Communication Technology) strategy for the justice sector, performance ... -oriented reporting from the subordinate agencies, ensuring that the new ICT Police System takes into account other sub-sectors need for electronic interaction.
Full description
Office of the Auditor General of Norway , issued in 2012
Risk cases: 2
Cost-intensive data centres stood idle for years
Idle data centres As found by the German SAI, some of costly Federal data centres stood largely idle. The Ministry failed to adequately assess the project risks. The Ministry needs to avoid similar shortcomings in the proposed federal IT consolidation project.
Full description
Bundesrechnungshof , issued in 2016
Risk cases: 1
The protection of research data at the Danish universities
The protection of research data at the Danish universities It is Rigsrevisionen’s assessment that the five largest universities are not adequately protecting their research data against unknown IT equipment. As a result, foreign actors may relatively easy gain unauthorized access to the universities’ research data.This is not considered satisfactory by Rigsrevisionen. The study shows that the five largest universities have defined guidelines for researchers’ use of software and hardware centrally, but that they have failed to centralise efforts to maintain a satisfactory level of security for research data. This is due mainly to the fact that, at some universities, researchers are allowed to bring their own devices,and at all the universities, researchers are allowed to have local administrator privileges, which gives them access to install software. Additionally, all five universities know of incidents where unknown hardware has been connected to their network.
Full description
National Audit Office of Denmark , issued in 2018
Risk cases: 3
Coordination of Infrastructure Works by Metropolitan Municipalities
Rapid population growth at metropoles as well as dense and planless structuring, especially in İstanbul and Ankara, have lead to an increase in demand for utilities services and consequently ... , in the resources used for the construction and maintenance of utilities. Moreover, in cities with dense population, damages to roads and sidewalks during the construction and maintenance of utilities cause problems ... in daily life, create financial burden and necessitate effective solutions. The purpose of this audit is to ensure that metropolitan municipalities eradicate defects in implementation, and Ministry ... ... ... Start geographic information system with cooperation rules and digital maps ... problems that reduce use and rise costs of this fundamental task. ... Organization of geographic and infrastructure information systems is an especially difficult task when bacause vast and intense coordination is necessary. The Turkisch Court of Accounts lists
Full description
Turkish Court of Accounts , issued in 2008
Risk cases: 2
70 results found. Page 1 of 7 next