Audit of the key ICT project federal GEVER programme Federal Chancellery
During the first stage, two new GEVER (electronic records and process management) products were procured in an open WTO tender within the framework of the two-product strategy (federal GEVER WTO ... procurement project). CHF 1.6 million was spent on these. The departments and Federal Chancellery (departments/FCh) had to choose one of the two products within three months of the contract being awarded. ... ... Advanced process management system's cost-effectiveness and deadlines at risk ... Ever since 1990, sequential controls and file management have been part of the Federal Administration's IT landscape (GEVER business administration). Significant obstacles have to be overcome ... in order to ensure the successful creation and introduction of GEVER. Previous efforts did not have any widespread success and led to a diverse GEVER landscape. The federal GEVER project has now laid ... the foundations for simplification and centralisation.
Full description
During the first stage, two new GEVER (electronic records and process management) products were procured in an open WTO tender within the framework of the two-product strategy (federal GEVER WTO ... procurement project). CHF 1.6 million was spent on these. The departments and Federal Chancellery (departments/FCh) had to choose one of the two products within three months of the contract being awarded. ... ... Advanced process management system's cost-effectiveness and deadlines at risk ... Ever since 1990, sequential controls and file management have been part of the Federal Administration's IT landscape (GEVER business administration). Significant obstacles have to be overcome ... in order to ensure the successful creation and introduction of GEVER. Previous efforts did not have any widespread success and led to a diverse GEVER landscape. The federal GEVER project has now laid ... the foundations for simplification and centralisation.
Full description
Swiss Federal Audit Office
, issued in 2015
Risk cases: 2
The Ministry of the Environment lacks a compact information system and still uses 125 separate information systems and databases
The objective of the audit was to scrutinise the management of funds earmarked for the purchase and administration of ICT within the MoE and selected organisations which come under the management ... of the MoE. The audit identified the following risks: (1) non-existence of the Integrated environmental information system (IEIS) as an independent information system; (2) purchase of ICT, within the budget ... chapter of the MoE, through a state co-funded organisation CENIA which comes under the management of the MoE; (3) utilisation of the information systems. The audited period was 2010 to 2013; where relevant ... ... Ministry of the Environment manages 125 information systems and databases ... The Ministry of the Environment (MoE) has for more than 20 years a legal obligation to administer and manage an Integrated Environmental Information System (IEIS). In spite of this fact, the existing ... systems (more than 125 information systems and databases) are designed, implemented and managed as individual information systems without a direct integration into a joint point of reference.
Full description
The objective of the audit was to scrutinise the management of funds earmarked for the purchase and administration of ICT within the MoE and selected organisations which come under the management ... of the MoE. The audit identified the following risks: (1) non-existence of the Integrated environmental information system (IEIS) as an independent information system; (2) purchase of ICT, within the budget ... chapter of the MoE, through a state co-funded organisation CENIA which comes under the management of the MoE; (3) utilisation of the information systems. The audited period was 2010 to 2013; where relevant ... ... Ministry of the Environment manages 125 information systems and databases ... The Ministry of the Environment (MoE) has for more than 20 years a legal obligation to administer and manage an Integrated Environmental Information System (IEIS). In spite of this fact, the existing ... systems (more than 125 information systems and databases) are designed, implemented and managed as individual information systems without a direct integration into a joint point of reference.
Full description
Supreme Audit Office of Czech Republic
, issued in 2015
Risk cases: 7
Audit on the operation of the “Ministry of Finance” Central Budget Chapter
and their development and the role of the Hungarian State Treasury within the IT framework of public finances. ... The audit was carried out on the "Ministry of Finance" central budget chapter and covered the period of 2003-2008. One of the audited activities of the Ministry were the IT systems ... ... Simple receipt: calculate costs, standardize data, divide duties... ... Hungarian Audit Office analyzed in detail fundamentals of proper IT investment taking into account problems of Budget Management System.
Full description
and their development and the role of the Hungarian State Treasury within the IT framework of public finances. ... The audit was carried out on the "Ministry of Finance" central budget chapter and covered the period of 2003-2008. One of the audited activities of the Ministry were the IT systems ... ... Simple receipt: calculate costs, standardize data, divide duties... ... Hungarian Audit Office analyzed in detail fundamentals of proper IT investment taking into account problems of Budget Management System.
Full description
State Audit Office of Hungary
, issued in 2008
Risk cases: 3
Is the project 'E-health in Latvia' a step towards the right direction?
Objective of the audit was to verify efficiency and productivity of the actions by the institutions in charge for implementation of the e-health, as well as to audit economy and productivity of use ... of funds invested in the project for achievement of set objectives and gaining the planned benefits. Audit covered such main questions: 1) Will the e-health policy be able to solve problems and achieve ... the objective? 2) Are the actual activities performed by the National Health Service justified for achievement of the set objectives? 3) Will necessary information security and personal data protection be ensured ... E-health is a step forward in right direction, but not all objectives will be reached! ... a step towards the right direction then. However, as found the Latvian SAI, the e-health policy will not be implemented within the initially planned scope and deadline and within set data security levels ... Project “E-health in Latvia” supports healthy lifestyle, it will provide valuable and accessible information and will promote more efficient provision of services to patients. It is undoubtedly ... , thus the objective of this policy – to promote more effective provision of healthcare services will be attained only partially.
Full description
Objective of the audit was to verify efficiency and productivity of the actions by the institutions in charge for implementation of the e-health, as well as to audit economy and productivity of use ... of funds invested in the project for achievement of set objectives and gaining the planned benefits. Audit covered such main questions: 1) Will the e-health policy be able to solve problems and achieve ... the objective? 2) Are the actual activities performed by the National Health Service justified for achievement of the set objectives? 3) Will necessary information security and personal data protection be ensured ... E-health is a step forward in right direction, but not all objectives will be reached! ... a step towards the right direction then. However, as found the Latvian SAI, the e-health policy will not be implemented within the initially planned scope and deadline and within set data security levels ... Project “E-health in Latvia” supports healthy lifestyle, it will provide valuable and accessible information and will promote more efficient provision of services to patients. It is undoubtedly ... , thus the objective of this policy – to promote more effective provision of healthcare services will be attained only partially.
Full description
State Audit Office of the Republic of Latvia
, issued in 2015
Risk cases: 3
IT security in the Federal Administration
The SFAO has audited the Admin PKI – the basic infrastructure and offering for the issuing of digital certificates – within the Federal Office of Information Technology, Systems and Telecommunication ... (FOITT). The examination concentrated on assessing the development and current operation as well as future prospects. Admin PKI refers to all processes and the hardware and software needed for issuing ... certificates of different grades. ... Technical and organizational deficiencies work together against data security ... Only minor deficiencies were revealed in the Windows environment but only in case of Microsoft products.Providers' lack of both assertiveness and synergy adds to 'the great unknown' of authonomous ... entities' networks.
Full description
The SFAO has audited the Admin PKI – the basic infrastructure and offering for the issuing of digital certificates – within the Federal Office of Information Technology, Systems and Telecommunication ... (FOITT). The examination concentrated on assessing the development and current operation as well as future prospects. Admin PKI refers to all processes and the hardware and software needed for issuing ... certificates of different grades. ... Technical and organizational deficiencies work together against data security ... Only minor deficiencies were revealed in the Windows environment but only in case of Microsoft products.Providers' lack of both assertiveness and synergy adds to 'the great unknown' of authonomous ... entities' networks.
Full description
Swiss Federal Audit Office
, issued in 2011
Risk cases: 4
Informatisation of hospitals
to the construction of the health information system within the framework of the "Healthcare Informatisation Program" ... The goals of the audit were: 1. Assesment to what degree service providers are prepared to implement the electronic health information system. 2. Assessment of government activities related ... ... Sometimes it is really not about the money.. ... Informatisation of healthcare is one of the most money-consuming IT activities of the State. Polish NIK shows how a poor concept can delay modernization of hospitals. The new IT system was expected ... to take some burden off doctors, streamline medical care, prevent fraud and improve efficiency. But will it be created at all?
Full description
to the construction of the health information system within the framework of the "Healthcare Informatisation Program" ... The goals of the audit were: 1. Assesment to what degree service providers are prepared to implement the electronic health information system. 2. Assessment of government activities related ... ... Sometimes it is really not about the money.. ... Informatisation of healthcare is one of the most money-consuming IT activities of the State. Polish NIK shows how a poor concept can delay modernization of hospitals. The new IT system was expected ... to take some burden off doctors, streamline medical care, prevent fraud and improve efficiency. But will it be created at all?
Full description
Sumpreme Audit Office
, issued in 2013
Risk cases: 3
Report on the problems connected with the development and implementation of the digitally based Shared Medication Record
a sufficient framework for carrying through the SMR programme? 2) Has the Ministry of Health and the NHA directed the SMR programme towards delivering within the agreed costs, time and quality parameters ... The purpose of the examination was to assess whether the department of the Danish Ministry of Health, the Danish National eHealth Authority (NHA) and the five regions that are responsible ... for the hospitals have made an adequate effort to develop and implement the Shared Medication Record (SMR). With the SMR, data on the citizens’ medication can be shared across hospitals, general practitioners, etc ... ... Involvement of key participants necessary from the very beginning ... Digitally based Shared Medication Record is basis of the complex healthcare system. Rigsrevisionen analysed unsolved issues related to unclear business case, insufficient analysis of work flows ... and processes leading to implementation problems, governance not involving key players, and IT security organisation.
Full description
a sufficient framework for carrying through the SMR programme? 2) Has the Ministry of Health and the NHA directed the SMR programme towards delivering within the agreed costs, time and quality parameters ... The purpose of the examination was to assess whether the department of the Danish Ministry of Health, the Danish National eHealth Authority (NHA) and the five regions that are responsible ... for the hospitals have made an adequate effort to develop and implement the Shared Medication Record (SMR). With the SMR, data on the citizens’ medication can be shared across hospitals, general practitioners, etc ... ... Involvement of key participants necessary from the very beginning ... Digitally based Shared Medication Record is basis of the complex healthcare system. Rigsrevisionen analysed unsolved issues related to unclear business case, insufficient analysis of work flows ... and processes leading to implementation problems, governance not involving key players, and IT security organisation.
Full description
National Audit Office of Denmark
, issued in 2014
Risk cases: 2
Australian Taxation Office: Administration of Australian Business Number Registrations
More elligibility and data integrity needed The Australian Business Number (ABN) and Australian Business Register initiatives were implemented as part of theGovernment's comprehensive reform of the taxation system in 2000. Their introduction involved challenging issues of technology and governance , including the imperative to process and register significant numbers of applications in a short time. Overall, the Australian SAI concluded that the ABN registration process is operating effectively. However, matters relating to the eligibility of some ABN applicants need to be reviewed. Further, some data integrity issues remain outstanding.
Full description
More elligibility and data integrity needed The Australian Business Number (ABN) and Australian Business Register initiatives were implemented as part of theGovernment's comprehensive reform of the taxation system in 2000. Their introduction involved challenging issues of technology and governance , including the imperative to process and register significant numbers of applications in a short time. Overall, the Australian SAI concluded that the ABN registration process is operating effectively. However, matters relating to the eligibility of some ABN applicants need to be reviewed. Further, some data integrity issues remain outstanding.
Full description
The Australian National Audit Office
, issued in 2003
Risk cases: 3
Conflicts of interest
First, recognise the conflicts of interest are a real risk the British NAO gathered a significant amount of intelligence on conflicts, particularly in the health and education sectors. These are areas of government where services are increasingly commissioned and delivered by parties at arm’s-length to departments. Conflicts of interest can occur naturally as a product of the way a system is designed and most often arise from operational situations.
Full description
First, recognise the conflicts of interest are a real risk the British NAO gathered a significant amount of intelligence on conflicts, particularly in the health and education sectors. These are areas of government where services are increasingly commissioned and delivered by parties at arm’s-length to departments. Conflicts of interest can occur naturally as a product of the way a system is designed and most often arise from operational situations.
Full description
National Audit Office
, issued in 2015
Risk cases: 8
Housing in England: overview
Efforts to support housing Even if housebuilding in England has not kept pace with need and there has been a reduction in social rented homes, significant advantages can be enjoyed: an increase in home ownership and in the number of private rented homes. The quality of housing improved in recent years too. The National Audit Office has reviewed critical elements of the housing being one of the government's key priorities. Looking for risks, they found that a potential conflict of objectives can lead to tensions in delivery.
Full description
Efforts to support housing Even if housebuilding in England has not kept pace with need and there has been a reduction in social rented homes, significant advantages can be enjoyed: an increase in home ownership and in the number of private rented homes. The quality of housing improved in recent years too. The National Audit Office has reviewed critical elements of the housing being one of the government's key priorities. Looking for risks, they found that a potential conflict of objectives can lead to tensions in delivery.
Full description
National Audit Office
, issued in 2017
Risk cases: 2