The effectiveness of Official Development Assistance expenditure
Need of more coordination and transparency The audit of the UK's Official Development Assistance revealed among others: fragmented responsibilities and difficulties in review and reporting. These led to difficulties in assessment of effectiveness of the assistance and of progress in implementing the UK Aid Strategy.
Full description
Need of more coordination and transparency The audit of the UK's Official Development Assistance revealed among others: fragmented responsibilities and difficulties in review and reporting. These led to difficulties in assessment of effectiveness of the assistance and of progress in implementing the UK Aid Strategy.
Full description
National Audit Office
, issued in 2019
Risk cases: 4
Evaluation of the effectiveness of implementation and compliance with regulatory enactments and the legal framework of the project “E-government Portfolio”
programme of the European Regional Development Fund (hereinafter: ERDF) of the European Union (hereinafter: EU), “Development and improvement of the infrastructural foundation for electronic governance”. ... The objective of the audit is to evaluate the effectiveness of implementation and compliance with regulatory enactments and the legal framework of the project “Egovernment Portfolio” of the national ... ... Funds to absorb but no efficient project methodology? Be prepared for troubles ... Wide list of problems that can be met when more care is received by 'absorb funds' objective than by clear vision what and how can be improved. SAI Latvia's analysis shows how dangerous it can ... be for both effectiveness and financial management.
Full description
programme of the European Regional Development Fund (hereinafter: ERDF) of the European Union (hereinafter: EU), “Development and improvement of the infrastructural foundation for electronic governance”. ... The objective of the audit is to evaluate the effectiveness of implementation and compliance with regulatory enactments and the legal framework of the project “Egovernment Portfolio” of the national ... ... Funds to absorb but no efficient project methodology? Be prepared for troubles ... Wide list of problems that can be met when more care is received by 'absorb funds' objective than by clear vision what and how can be improved. SAI Latvia's analysis shows how dangerous it can ... be for both effectiveness and financial management.
Full description
State Audit Office of Latvia
, issued in 2010
Risk cases: 3
Effectiveness of development of broadband network or high-speed internet
The National Audit Office audited whether the state has made every effort to ensure that everyone can have unlimited access to fast internet connection by 2020. The National Audit Office also ... analysed whether the network of fibre-optical cables or the basic broadband network, which is built with European Union support and should guarantee high-speed internet connection, has helped to achieve ... this goal. ... ... ... Slower broadband paid by customers ... The Estonian Information Society Development Plan foresees that high-speed internet of 30 Mbit/s should be accessible to all people in Estonia by 2020 and that 60% of the population will be using ... superfast internet of over 100 Mbit/s. To achieve these goals, the state, with the help of European Union support, decided to establish a broadband network which is not further than 1.5 km from 98% of homes ... and institutions. Private companies have not entirely met the Government's expectations. The Estonian SAI has looked for an answer: Why?
Full description
The National Audit Office audited whether the state has made every effort to ensure that everyone can have unlimited access to fast internet connection by 2020. The National Audit Office also ... analysed whether the network of fibre-optical cables or the basic broadband network, which is built with European Union support and should guarantee high-speed internet connection, has helped to achieve ... this goal. ... ... ... Slower broadband paid by customers ... The Estonian Information Society Development Plan foresees that high-speed internet of 30 Mbit/s should be accessible to all people in Estonia by 2020 and that 60% of the population will be using ... superfast internet of over 100 Mbit/s. To achieve these goals, the state, with the help of European Union support, decided to establish a broadband network which is not further than 1.5 km from 98% of homes ... and institutions. Private companies have not entirely met the Government's expectations. The Estonian SAI has looked for an answer: Why?
Full description
National Audit Office of Estonia
, issued in 2015
Risk cases: 3
Use of European Union funds in promoting information society
Audit Office checked whether the distribution of funds for the development of the information society has been balanced and transparent, and whether the distribution of aid is adequately supervised ... . Balanced distribution of aid means that development of the information society entails paying attention (and ideally providing proportional funding) to information systems aimed at the public sector, private ... Audit Office is of the opinion that the state is too focussed on financing the IT developments aimed at the state when distributing aid for the implementation of the National Information Society ... Riigikontroll auditeeris Euroopa Liidu struktuurifondidest ehk tõukefondidest eraldatud toetuste (edaspidi ELi toetusraha) kasutamist riigi infotehnoloogia (IT) valdkonnas. Uuriti, kas raha jagamine ... infoühiskonna arendamise eesmärgil on olnud tasakaalustatud ja läbipaistev ning kas toetuste jagamise üle tehakse piisavat järelevalvet. Riigikontrolli hinnangul on riik infoühiskonna arengukava rakendamiseks ... toetuste jagamisel keskendunud liiga riigile suunatud IT-arenduste rahastamisele ning jätnud tagaplaanile ettevõtete konkurentsivõime parandamisele ja kolmandale sektorile suunatud IT arendusprojektide ... Balance needed for success of Information Society Development Plan ... 50% of aid has been granted primarily for the development of information systems of state agencies, i.e. as much as the other two target groups - business and citizens - put together. Information ... , true suppervision and measurement of progress are listed by the Estonian SAI as next key elements necessary to keep balanced development of strategy for Information Society.
Full description
Audit Office checked whether the distribution of funds for the development of the information society has been balanced and transparent, and whether the distribution of aid is adequately supervised ... . Balanced distribution of aid means that development of the information society entails paying attention (and ideally providing proportional funding) to information systems aimed at the public sector, private ... Audit Office is of the opinion that the state is too focussed on financing the IT developments aimed at the state when distributing aid for the implementation of the National Information Society ... Riigikontroll auditeeris Euroopa Liidu struktuurifondidest ehk tõukefondidest eraldatud toetuste (edaspidi ELi toetusraha) kasutamist riigi infotehnoloogia (IT) valdkonnas. Uuriti, kas raha jagamine ... infoühiskonna arendamise eesmärgil on olnud tasakaalustatud ja läbipaistev ning kas toetuste jagamise üle tehakse piisavat järelevalvet. Riigikontrolli hinnangul on riik infoühiskonna arengukava rakendamiseks ... toetuste jagamisel keskendunud liiga riigile suunatud IT-arenduste rahastamisele ning jätnud tagaplaanile ettevõtete konkurentsivõime parandamisele ja kolmandale sektorile suunatud IT arendusprojektide ... Balance needed for success of Information Society Development Plan ... 50% of aid has been granted primarily for the development of information systems of state agencies, i.e. as much as the other two target groups - business and citizens - put together. Information ... , true suppervision and measurement of progress are listed by the Estonian SAI as next key elements necessary to keep balanced development of strategy for Information Society.
Full description
National Audit Office of Estonia
, issued in 2012
Risk cases: 2
Identifying and meeting central government's skills requirements
Start with well managed responsibilities UK Departments have invested heavily in skills development. Government estimates that expenditure on formal training, including salary costs of departmental learning and development staff, was £275 million in 2009-10. NAO identified weaknesses of the system which start with devolved responsibilities, lead to: weak data, mis-profiled trainings, doubtful personal decisions, lack of well-targeted evaluation - and finish at more expensive buying-in and retaining key skills...
Full description
Start with well managed responsibilities UK Departments have invested heavily in skills development. Government estimates that expenditure on formal training, including salary costs of departmental learning and development staff, was £275 million in 2009-10. NAO identified weaknesses of the system which start with devolved responsibilities, lead to: weak data, mis-profiled trainings, doubtful personal decisions, lack of well-targeted evaluation - and finish at more expensive buying-in and retaining key skills...
Full description
National Audit Office
, issued in 2011
Risk cases: 6
Audit of the asset preservation and management activities of state-owned (partly state-owned) economic organisations – HungaroControl Hungarian Air Navigation Services Pte.Ltd.Co.
Compliance review of an air traffic services provider Lack of formal approval of the 2014 annual report was an issue found by Hungarian auditors in HungaroControl, a state-owned company, which provides training for air traffic personnel and carries out air navigation research and development.
Full description
Compliance review of an air traffic services provider Lack of formal approval of the 2014 annual report was an issue found by Hungarian auditors in HungaroControl, a state-owned company, which provides training for air traffic personnel and carries out air navigation research and development.
Full description
State Audit Office of Hungary
, issued in 2017
Risk cases: 1
OMB and Agencies Need to Focus Continued Attention on Implementing Reform Law
How to invest efficiently in IT IT investments are large and growing position in annual budgets. Historically, they have frequently failed, incurred cost overruns and schedule slippages, or contributed little to mission-related outcomes. GAO recommendations focus on the oversight and execution of the data center consolidation initiative, the accuracy and reliability of the IT Dashboard, and incremental development policies.
Full description
How to invest efficiently in IT IT investments are large and growing position in annual budgets. Historically, they have frequently failed, incurred cost overruns and schedule slippages, or contributed little to mission-related outcomes. GAO recommendations focus on the oversight and execution of the data center consolidation initiative, the accuracy and reliability of the IT Dashboard, and incremental development policies.
Full description
General Accountability Office
, issued in 2016
Risk cases: 3
Electronic Health Records - VA Needs to Identify and Report Existing System Costs
Difficulties after 30 years of decentralized development The US Department of Veterans Affairs provides health care services to approximately 9 million veterans and their families. However, the IT system they use is more than 30 years old, is costly to maintain, and does not fully support exchanging health data. The US GAO, analyzed the system's modenization plans and found serious problems with definition and cost estimation.
Full description
Difficulties after 30 years of decentralized development The US Department of Veterans Affairs provides health care services to approximately 9 million veterans and their families. However, the IT system they use is more than 30 years old, is costly to maintain, and does not fully support exchanging health data. The US GAO, analyzed the system's modenization plans and found serious problems with definition and cost estimation.
Full description
US Government Accountability Office
, issued in 2019
Risk cases: 3
Relocation of government jobs
Difficult experience of relocation of jobs The Danish government decided to move almost 4 thousand government jobs away from the metropolitan area. The purpose of the relocation was to attain a better balance and development across Denmark and ensure that government institutions were located close to the citizens and businesses. Study of the SAI Denmark shows that overall, the departments have implemented the whole operation in an appropriate manner. At the same time, however, the relocation had negative consequences for the institutions’ production which has also affected citizens and businesses.
Full description
Difficult experience of relocation of jobs The Danish government decided to move almost 4 thousand government jobs away from the metropolitan area. The purpose of the relocation was to attain a better balance and development across Denmark and ensure that government institutions were located close to the citizens and businesses. Study of the SAI Denmark shows that overall, the departments have implemented the whole operation in an appropriate manner. At the same time, however, the relocation had negative consequences for the institutions’ production which has also affected citizens and businesses.
Full description
National Audit Office of Denmark
, issued in 2017
Risk cases: 4
Building and Implementing the Phoenix Pay System
Expensive IT project became a failure Phoenix project (development of states pay system) was an incomprehensible failure of project management and oversight. Phoenix executives prioritized certain aspects, such as schedule and budget, over other critical ones, such as functionality and security. Phoenix executives did not understand the importance of warnings that the Miramichi Pay Centre, departments and agencies, and the new system were not ready. They did not provide complete and accurate information to deputy ministers and associate deputy ministers of departments and agencies, including the Deputy Minister of Public Services and Procurement, when briefing them on Phoenix readiness for implementation.
Full description
Expensive IT project became a failure Phoenix project (development of states pay system) was an incomprehensible failure of project management and oversight. Phoenix executives prioritized certain aspects, such as schedule and budget, over other critical ones, such as functionality and security. Phoenix executives did not understand the importance of warnings that the Miramichi Pay Centre, departments and agencies, and the new system were not ready. They did not provide complete and accurate information to deputy ministers and associate deputy ministers of departments and agencies, including the Deputy Minister of Public Services and Procurement, when briefing them on Phoenix readiness for implementation.
Full description
Office of theAuditor Generalof Canada
, issued in 2018
Risk cases: 3