Lack of information about heavy-duty transports on federal long-distance roads - number of closed bridges increases
Information on heavy-duty Transports The Bundesrechnungshof of Germany revealed that the Federal Ministry of Transport and Digital Infrastructure does not know which routes are particularly affected by heavy-duty transports, since it has not obtained comprehensive information from the state authorities about the heavy-duty transports.
Full description
Information on heavy-duty Transports The Bundesrechnungshof of Germany revealed that the Federal Ministry of Transport and Digital Infrastructure does not know which routes are particularly affected by heavy-duty transports, since it has not obtained comprehensive information from the state authorities about the heavy-duty transports.
Full description
Bundesrechnungshof
, issued in 2016
Risk cases: 1
Use of consultants and temporary staff
New skills needed in a longer term UK NAO: Used well, consultants and temporary staff can be an important source of specialist skills and capabilities that are uneconomic for departments to maintain in their permanent staff. Since 2009-10, the government has used spending controls to reduce its use of consultants and temporary staff, and by 2014-15 spending had fallen by £1.5 billion. However, spending has increased by between £400 million and £600 million since 2011-12, suggesting that this was more of a short-term reduction than a sustainable strategy. In the longer term, departments will need to develop workforce, skills and capacity plans to reduce their dependence on external skills. They will need to improve their strategic workforce planning to determine where they can deploy existing staff, where they need to recruit, and where they need to engage temporary resources. Without this, departments cannot demonstrate that they are achieving value for money from the use of consultants and temporary staff.
Full description
New skills needed in a longer term UK NAO: Used well, consultants and temporary staff can be an important source of specialist skills and capabilities that are uneconomic for departments to maintain in their permanent staff. Since 2009-10, the government has used spending controls to reduce its use of consultants and temporary staff, and by 2014-15 spending had fallen by £1.5 billion. However, spending has increased by between £400 million and £600 million since 2011-12, suggesting that this was more of a short-term reduction than a sustainable strategy. In the longer term, departments will need to develop workforce, skills and capacity plans to reduce their dependence on external skills. They will need to improve their strategic workforce planning to determine where they can deploy existing staff, where they need to recruit, and where they need to engage temporary resources. Without this, departments cannot demonstrate that they are achieving value for money from the use of consultants and temporary staff.
Full description
National Audit Office
, issued in 2016
Risk cases: 7
Central government staff costs
Results of staff reductions The British NAO found that departments had significantly reduced numbers of their civil servants and of course salary costs at the same time. But they reduced staff numbers mainly by minimising recruitment, and the age profile of the civil service has changed. NAO pays a lot attention to what effect this has had on the future pipeline of talent and skills. It reminds also that the departments need long-term operating models to work efficiently with the staff reduced.
Full description
Results of staff reductions The British NAO found that departments had significantly reduced numbers of their civil servants and of course salary costs at the same time. But they reduced staff numbers mainly by minimising recruitment, and the age profile of the civil service has changed. NAO pays a lot attention to what effect this has had on the future pipeline of talent and skills. It reminds also that the departments need long-term operating models to work efficiently with the staff reduced.
Full description
National Audit Office
, issued in 2015
Risk cases: 5
Correlations between the operational risks of companies in the majority ownership of local governments and the financial situation of the local governments
Risks related to local governments-owned companies The Hungarian SAI analysed four risk areas, taking 19 aspects and the specificities of Hungary’s settlement patterns into consideration. The four areas defined were the following: performance of public tasks, exercise of proprietary rights, financial stability of local governments, and short and medium-term stability of the financial management of companies.
Full description
Risks related to local governments-owned companies The Hungarian SAI analysed four risk areas, taking 19 aspects and the specificities of Hungary’s settlement patterns into consideration. The four areas defined were the following: performance of public tasks, exercise of proprietary rights, financial stability of local governments, and short and medium-term stability of the financial management of companies.
Full description
State Audit Office of Hungary
, issued in 2017
Risk cases: 1
Incorrect payments in social insurance - Control activities of the Swedish Social Insurance Agency
In 2014 the social insurance system accounted for six per cent of GDP. The long-term sustainability of a system of that magnitude requires that the public perceives its purpose to be important ... , that it is well administered and that it is as free of abuse as possible. It must also be financially stable over time, since major fluctuations impact other areas of the central government budget. When ... these things function as they should, the system is perceived to be legitimate and enjoys public confidence.<br/> According to available estimations, almost SEK 20 billion had been paid out incorrectly from ... Balance of priorities needed to reduce incorrect payments ... Role of social insurance in public finance is so substantial that reduction of incorrect payments' volume is matter of huge savings. The Swedish NAO noted positive initiatives by the Social Insurance ... Agency in this regard. However they found also, that serious problems can stem from giving higher priority to the speed of payment and customers satisfaction. They both are undoubtedly important features ... of each system, still, the prevention of incorrect payments needs strategic support to be really effective.
Full description
In 2014 the social insurance system accounted for six per cent of GDP. The long-term sustainability of a system of that magnitude requires that the public perceives its purpose to be important ... , that it is well administered and that it is as free of abuse as possible. It must also be financially stable over time, since major fluctuations impact other areas of the central government budget. When ... these things function as they should, the system is perceived to be legitimate and enjoys public confidence.<br/> According to available estimations, almost SEK 20 billion had been paid out incorrectly from ... Balance of priorities needed to reduce incorrect payments ... Role of social insurance in public finance is so substantial that reduction of incorrect payments' volume is matter of huge savings. The Swedish NAO noted positive initiatives by the Social Insurance ... Agency in this regard. However they found also, that serious problems can stem from giving higher priority to the speed of payment and customers satisfaction. They both are undoubtedly important features ... of each system, still, the prevention of incorrect payments needs strategic support to be really effective.
Full description
Swedish National Audit Office
, issued in 2016
Risk cases: 3
Electronic Records. Management and Preservation Pose Challenges
Basics of electronic records management This audit of GAO, reported in 2003, can be helpful in looking for basic problems in electronic records management. These problems are compounded as computer hardware, application software, and even storage media become obsolete, as they may leave behind electronic records that can no longer be read.
Full description
Basics of electronic records management This audit of GAO, reported in 2003, can be helpful in looking for basic problems in electronic records management. These problems are compounded as computer hardware, application software, and even storage media become obsolete, as they may leave behind electronic records that can no longer be read.
Full description
General Accountability Office
, issued in 2003
Risk cases: 7
Federal Institute for Risk Assessment purchased unnecessary software
Risk of poor requirements management The Germamn SAI audited the Federal Institute for Risk Assessment that introduce a new software. Time of implementation was nearly three times as long as originally scheduled. The costs also nearly trebled. Moreover, the Institute purchased unnecessary licences for expanding the software
Full description
Risk of poor requirements management The Germamn SAI audited the Federal Institute for Risk Assessment that introduce a new software. Time of implementation was nearly three times as long as originally scheduled. The costs also nearly trebled. Moreover, the Institute purchased unnecessary licences for expanding the software
Full description
Bundesrechnungshof
, issued in 2017
Risk cases: 2
Has Public Administration Used All Opportunities for Efficient Management of ICT Infrastructure?
Efficient Management of ICT Infrastructure Centralised management of ICT services and infrastructure would allow the institutions to optimise in long run their resources – financial, human, material and technical. However, we observed during the audit that the move towards ICT centralisation and single data centres has ceased. The different ministries and even the institutions subordinated to the same ministry do not cooperate sufficiently with each other regarding the ICT management, maintenance, and infrastructure placement. They rather choose to maintain their own, sometimes even several, data centres.
Full description
Efficient Management of ICT Infrastructure Centralised management of ICT services and infrastructure would allow the institutions to optimise in long run their resources – financial, human, material and technical. However, we observed during the audit that the move towards ICT centralisation and single data centres has ceased. The different ministries and even the institutions subordinated to the same ministry do not cooperate sufficiently with each other regarding the ICT management, maintenance, and infrastructure placement. They rather choose to maintain their own, sometimes even several, data centres.
Full description
State Audit Office of the Republic of Latvia
, issued in 2019
Risk cases: 3
Online fraud
Uneven response to online fraud This type of fraud can affect everyone, but yet it is not a strategic priority for local police forces and the response from industry is uneven. UK NAO underlines: For too long, as a low-value but high-volume crime, online fraud has been overlooked by government, law enforcement and industry. It is a crime that can affect everyone. Fraud is now the most commonly experienced crime in England and Wales, is growing rapidly and demands an urgent response. Yet fraud is not a strategic priority for local police forces, and the response from industry is uneven.
Full description
Uneven response to online fraud This type of fraud can affect everyone, but yet it is not a strategic priority for local police forces and the response from industry is uneven. UK NAO underlines: For too long, as a low-value but high-volume crime, online fraud has been overlooked by government, law enforcement and industry. It is a crime that can affect everyone. Fraud is now the most commonly experienced crime in England and Wales, is growing rapidly and demands an urgent response. Yet fraud is not a strategic priority for local police forces, and the response from industry is uneven.
Full description
National Audit Office
, issued in 2017
Risk cases: 6
Management of IT security in systems outsourced to external suppliers
Security to be improved in IT processes outsourced to external suppliers When IT processes are outsourced to external suppliers, the authorities no longer have direct control of the IT security, but remain responsible for managing the security of the IT. Authorities that fail to manage IT security actively based on risk assessments, and omit to monitor the implementation of these requirements, will not be able to determine if the level of IT security in the outsourced systems safeguards their systems and data. This is how the conclusion of the Rigsrevisionen starts. The Danish auditors noticed improvement in the audited entities, but they add that tha majority of the auditees: can refine their requirements for and follow-up on access control and logging practices
Full description
Security to be improved in IT processes outsourced to external suppliers When IT processes are outsourced to external suppliers, the authorities no longer have direct control of the IT security, but remain responsible for managing the security of the IT. Authorities that fail to manage IT security actively based on risk assessments, and omit to monitor the implementation of these requirements, will not be able to determine if the level of IT security in the outsourced systems safeguards their systems and data. This is how the conclusion of the Rigsrevisionen starts. The Danish auditors noticed improvement in the audited entities, but they add that tha majority of the auditees: can refine their requirements for and follow-up on access control and logging practices
Full description
National Audit Office of Denmark
, issued in 2016
Risk cases: 3