Building and Implementing the Phoenix Pay System
Expensive IT project became a failure Phoenix project (development of states pay system) was an incomprehensible failure of project management and oversight. Phoenix executives prioritized certain aspects, such as schedule and budget, over other critical ones, such as functionality and security. Phoenix executives did not understand the importance of warnings that the Miramichi Pay Centre, departments and agencies, and the new system were not ready. They did not provide complete and accurate information to deputy ministers and associate deputy ministers of departments and agencies, including the Deputy Minister of Public Services and Procurement, when briefing them on Phoenix readiness for implementation.
Full description
Office of theAuditor Generalof Canada , issued in 2018
Risk cases: 3
Audit of the key ICT project federal GEVER programme Federal Chancellery
During the first stage, two new GEVER (electronic records and process management) products were procured in an open WTO tender within the framework of the two-product strategy (federal GEVER WTO ... procurement project). CHF 1.6 million was spent on these. The departments and Federal Chancellery (departments/FCh) had to choose one of the two products within three months of the contract being awarded. ... ... Advanced process management system's cost-effectiveness and deadlines at risk ... in order to ensure the successful creation and introduction of GEVER. Previous efforts did not have any widespread success and led to a diverse GEVER landscape. The federal GEVER project has now laid ... Ever since 1990, sequential controls and file management have been part of the Federal Administration's IT landscape (GEVER business administration). Significant obstacles have to be overcome ... the foundations for simplification and centralisation.
Full description
Swiss Federal Audit Office , issued in 2015
Risk cases: 2
Management and protection of assets in the field of the information-communication technologies at the AO SR
The Supreme Audit office of the Slovak Republic (SAO SR) has executed the audit at the Antimonopoly Office of the Slovak Republic (AO SR) for the audit period 2010 and 2011 to verify the operation ... and security of the information-communication technologies (ICT) and the information systems of the public administration (ISPA) as well as the state assets administration, the economy and disposal ... with the state assets, the compliance with the generally binding legal regulations and the general statues in the field of the ISPA. There were 24 irregularities found, mainly in the field of the protection ... ... ... Failure to comply with the law leads to unnecessary jeopardizing of data security ... The audit in the field of the information systems of the public administration (ISPA) executed by the Supreme Audit Office of the Slovak Republic at the Antimonopoly Office of the Slovak Republic (AO ... SR) exposed several deficiencies related to the information systems and the data security as a consequence of a lawbreaking.
Full description
Supreme Audit Office of the Slovak Republic , issued in 2011
Risk cases: 4
Effectiveness of the Tax Administration of the Republic of Slovenia in the execution of modernisation projects of the Slovenian duty information system and decreasing the number of duty sub-accounts
some improvements and had also enabled implementation of the second project - decreasing the number of government duty sub-accounts. Despite these successes, the combined projects of modernisation ... The Tax Administration of the Republic of Slovenia (hereinafter: the Tax Administration) is responsible for collecting taxes, fees and other compulsory levies (hereinafter: duties ... ). These are the revenue of the state budget, municipal budgets, the Health Insurance Institute of Slovenia, the Institute for Pension and Disability Insurance of Slovenia (hereinafter: duties recipients) and indirectly ... ... Shaky coordination of investments in important systems ... Slovenian SAI traced a series of problems in management of crucial IT investments in tax administration. Apart from promising goals, unclear business case gave a start to many problems at next stages ... of the project, involving additional spendings, delays and errors in data processing.
Full description
Court of Audit of the Republic of Slovenia , issued in 2014
Risk cases: 7
Use of European Union funds in promoting information society
The National Audit Office audited the use of the aid allocated from the structural funds of the European Union (hereinafter EU aid) in the information technology (IT) area of the state. The National ... Audit Office checked whether the distribution of funds for the development of the information society has been balanced and transparent, and whether the distribution of aid is adequately supervised ... . Balanced distribution of aid means that development of the information society entails paying attention (and ideally providing proportional funding) to information systems aimed at the public sector, private ... Riigikontroll auditeeris Euroopa Liidu struktuurifondidest ehk tõukefondidest eraldatud toetuste (edaspidi ELi toetusraha) kasutamist riigi infotehnoloogia (IT) valdkonnas. Uuriti, kas raha jagamine ... infoühiskonna arendamise eesmärgil on olnud tasakaalustatud ja läbipaistev ning kas toetuste jagamise üle tehakse piisavat järelevalvet. Riigikontrolli hinnangul on riik infoühiskonna arengukava rakendamiseks ... toetuste jagamisel keskendunud liiga riigile suunatud IT-arenduste rahastamisele ning jätnud tagaplaanile ettevõtete konkurentsivõime parandamisele ja kolmandale sektorile suunatud IT arendusprojektide ... Balance needed for success of Information Society Development Plan ... 50% of aid has been granted primarily for the development of information systems of state agencies, i.e. as much as the other two target groups - business and citizens - put together. Information ... , true suppervision and measurement of progress are listed by the Estonian SAI as next key elements necessary to keep balanced development of strategy for Information Society.
Full description
National Audit Office of Estonia , issued in 2012
Risk cases: 2
Audit of the procurement of ICT products with the potential to be standard products
ICT procurement system reviewed SFAO points out what is critical in ICT procurement. Requirements management is extremely important, as well as procurement strategies for relevant product groups. Legal rules should protect investments and support competition, but they can still be insufficient without appropriate reporting - if you want your system to adapt to changes.
Full description
Swiss Federal Audit Office , issued in 2015
Risk cases: 4
Digital transformation in government
Support exemplars, provide consistent guidance... and do not lose focus As the NAO states: Government faces significant challenges in providing public services. While many government services are now available online, public administration is struggling to manage more complicated programmes and to improve the complex systems and processes that support public services.
Full description
National Audit Office , issued in 2017
Risk cases: 4
Performance measurement by regulators
Performance measurement for regulators Primary adressees of this good practice guide - by the British NAO - are regulators, the public institutions established for making sure that an industry or system works legally and fairly. But we are sure that many more can find this guidance useful - including auditors. NAO presents a comprehensible framework for performance measurement and hints how to focus on influence that regulators can use.
Full description
National Audit Office , issued in 2016
Risk cases: 2
FEMA Needs to Address Management Weaknesses to Improve Its Systems
Controls in emergency management GAO audited the agency of the Department of Homeland Security, responsible for federal efforts to mitigate, respond to, and recover from disasters. American auditors recommend that the agency fully define its investment board’s roles and responsibilities and procedures for selecting and overseeing investments, update its strategic plan and complete plans for IT modernization, and establish time frames for completing workforce planning efforts. The agency should also establish policies and guidance for implementing key IT management controls.
Full description
General Accountability Office , issued in 2016
Risk cases: 4
Working of Inland Container Depots and Container Freight Stations
NEW! Online report on audit of SAI India With this first digital audit report of the Comptroller and Auditor General of India, new chapter has been opened in our profession: the online form is primary versus printable pdf. Advantages: high level of readability, live responsive charts, easy browsing and search of what users find interesting. The reported performance audit concerned 'dry ports', or multimodal logistics centres, which play growing role in domestic and international trade. It shows how gaps in concept and lax attitude to internal control can result on capacities, speed of trade, and enviromental safety.
Full description
Comptroller and Auditor General of India , issued in 2017
Risk cases: 5