Electronic Health Records - VA Needs to Identify and Report Existing System Costs
Difficulties after 30 years of decentralized development The US Department of Veterans Affairs provides health care services to approximately 9 million veterans and their families. However, the IT system they use is more than 30 years old, is costly to maintain, and does not fully support exchanging health data. The US GAO, analyzed the system's modenization plans and found serious problems with definition and cost estimation.
Full description
Difficulties after 30 years of decentralized development The US Department of Veterans Affairs provides health care services to approximately 9 million veterans and their families. However, the IT system they use is more than 30 years old, is costly to maintain, and does not fully support exchanging health data. The US GAO, analyzed the system's modenization plans and found serious problems with definition and cost estimation.
Full description
US Government Accountability Office
, issued in 2019
Risk cases: 3
Prevention Activities Against Traffic Accidents
traffic accidents, which are dramatically leading to loss of life and property. Examination and evaluation of the Traffic Information Systems (TIS) under the traffic control headline. TIS' main purpose ... Performance Audit Studies covering certain IT Issues related to Prevention Activities Against Traffic Accidents. It aims to contribute to the continuous improvement of prevention activities against ... is to conduct the traffic control activities efficiently with the help of systematic data. Objective of this audit was to contribute to the continuous improvement of prevention activities against traffic ... ... ... You need a way more than IT, to make an IT system successful ... SAI of Turkey examined the Traffic Information Systems and found out that not only IT infrastructure determined the audited IT project's outcomes. There were also non-IT issues that decided: low ... quality of driving education, poor technical infrastruture, as well as lack of monitoring and coordination at prioritization stage.
Full description
traffic accidents, which are dramatically leading to loss of life and property. Examination and evaluation of the Traffic Information Systems (TIS) under the traffic control headline. TIS' main purpose ... Performance Audit Studies covering certain IT Issues related to Prevention Activities Against Traffic Accidents. It aims to contribute to the continuous improvement of prevention activities against ... is to conduct the traffic control activities efficiently with the help of systematic data. Objective of this audit was to contribute to the continuous improvement of prevention activities against traffic ... ... ... You need a way more than IT, to make an IT system successful ... SAI of Turkey examined the Traffic Information Systems and found out that not only IT infrastructure determined the audited IT project's outcomes. There were also non-IT issues that decided: low ... quality of driving education, poor technical infrastruture, as well as lack of monitoring and coordination at prioritization stage.
Full description
Turkish Court of Accounts
, issued in 2008
Risk cases: 4
Coordination of Infrastructure Works by Metropolitan Municipalities
Rapid population growth at metropoles as well as dense and planless structuring, especially in İstanbul and Ankara, have lead to an increase in demand for utilities services and consequently ... , in the resources used for the construction and maintenance of utilities. Moreover, in cities with dense population, damages to roads and sidewalks during the construction and maintenance of utilities cause problems ... in daily life, create financial burden and necessitate effective solutions. The purpose of this audit is to ensure that metropolitan municipalities eradicate defects in implementation, and Ministry ... ... ... Start geographic information system with cooperation rules and digital maps ... Organization of geographic and infrastructure information systems is an especially difficult task when bacause vast and intense coordination is necessary. The Turkisch Court of Accounts lists ... problems that reduce use and rise costs of this fundamental task.
Full description
Rapid population growth at metropoles as well as dense and planless structuring, especially in İstanbul and Ankara, have lead to an increase in demand for utilities services and consequently ... , in the resources used for the construction and maintenance of utilities. Moreover, in cities with dense population, damages to roads and sidewalks during the construction and maintenance of utilities cause problems ... in daily life, create financial burden and necessitate effective solutions. The purpose of this audit is to ensure that metropolitan municipalities eradicate defects in implementation, and Ministry ... ... ... Start geographic information system with cooperation rules and digital maps ... Organization of geographic and infrastructure information systems is an especially difficult task when bacause vast and intense coordination is necessary. The Turkisch Court of Accounts lists ... problems that reduce use and rise costs of this fundamental task.
Full description
Turkish Court of Accounts
, issued in 2008
Risk cases: 2
Products sold on the European market: unravelling the system of CE marking
Problems with general picture The Netherlands National Court of Audit was interested in finding out whether anyone keeps track of all the actors involved in the process of system of European Union product markings. The interest was aroused by an observation that the vast majority of the questions raised about the system were prompted by incidents and that the questioners did not generally appear to be interested in the operation of the system as a whole...
Full description
Problems with general picture The Netherlands National Court of Audit was interested in finding out whether anyone keeps track of all the actors involved in the process of system of European Union product markings. The interest was aroused by an observation that the vast majority of the questions raised about the system were prompted by incidents and that the questioners did not generally appear to be interested in the operation of the system as a whole...
Full description
The Netherlands Court of Audit
, issued in 2017
Risk cases: 5
Opportunities Exist for SEC to Improve Its Controls over Financial Systems and Data
. In carrying out its mission, the SEC relies on computerized information systems to collect, process, and store sensitive information, including financial data. Having effective information security controls ... in place is essential to protecting these systems and the information they contain. <br/> This report details weaknesses GAO identified in the information security program at SEC during its audit ... of SEC’s key financial systems and information. To do this, GAO examined information security policies, plans, and procedures; tested controls over key financial applications; interviewed agency officials ... IT security basics under scrutiny ... Financial audit by US GAO was accompanied by an IT examination focused on information security measures in the Securities and Exchange Commission (SEC). GAO found that SEC’s systems could ... be compromised, because of risks jeopardizing the confidentiality, integrity, and availability of sensitive financial information.
Full description
. In carrying out its mission, the SEC relies on computerized information systems to collect, process, and store sensitive information, including financial data. Having effective information security controls ... in place is essential to protecting these systems and the information they contain. <br/> This report details weaknesses GAO identified in the information security program at SEC during its audit ... of SEC’s key financial systems and information. To do this, GAO examined information security policies, plans, and procedures; tested controls over key financial applications; interviewed agency officials ... IT security basics under scrutiny ... Financial audit by US GAO was accompanied by an IT examination focused on information security measures in the Securities and Exchange Commission (SEC). GAO found that SEC’s systems could ... be compromised, because of risks jeopardizing the confidentiality, integrity, and availability of sensitive financial information.
Full description
General Accountability Office
, issued in 2016
Risk cases: 5
Building and Implementing the Phoenix Pay System
Expensive IT project became a failure Phoenix project (development of states pay system) was an incomprehensible failure of project management and oversight. Phoenix executives prioritized certain aspects, such as schedule and budget, over other critical ones, such as functionality and security. Phoenix executives did not understand the importance of warnings that the Miramichi Pay Centre, departments and agencies, and the new system were not ready. They did not provide complete and accurate information to deputy ministers and associate deputy ministers of departments and agencies, including the Deputy Minister of Public Services and Procurement, when briefing them on Phoenix readiness for implementation.
Full description
Expensive IT project became a failure Phoenix project (development of states pay system) was an incomprehensible failure of project management and oversight. Phoenix executives prioritized certain aspects, such as schedule and budget, over other critical ones, such as functionality and security. Phoenix executives did not understand the importance of warnings that the Miramichi Pay Centre, departments and agencies, and the new system were not ready. They did not provide complete and accurate information to deputy ministers and associate deputy ministers of departments and agencies, including the Deputy Minister of Public Services and Procurement, when briefing them on Phoenix readiness for implementation.
Full description
Office of theAuditor Generalof Canada
, issued in 2018
Risk cases: 3
Federal Agencies Need to Address Aging Legacy Systems
Be aware of legacy IT risks The US government spends about 75 percent of the total amount budgeted for information technology on operations and maintenance. GAO reviewed Office of Management and Budget and 26 agencies, covering years 2010 through 2017 and recommends to develop a goal for spending measure and finalize guidance to identify and prioritize legacy IT needing to be modernized or replaced.
Full description
Be aware of legacy IT risks The US government spends about 75 percent of the total amount budgeted for information technology on operations and maintenance. GAO reviewed Office of Management and Budget and 26 agencies, covering years 2010 through 2017 and recommends to develop a goal for spending measure and finalize guidance to identify and prioritize legacy IT needing to be modernized or replaced.
Full description
General Accountability Office
, issued in 2016
Risk cases: 3
FEMA Needs to Address Management Weaknesses to Improve Its Systems
Controls in emergency management GAO audited the agency of the Department of Homeland Security, responsible for federal efforts to mitigate, respond to, and recover from disasters. American auditors recommend that the agency fully define its investment board’s roles and responsibilities and procedures for selecting and overseeing investments, update its strategic plan and complete plans for IT modernization, and establish time frames for completing workforce planning efforts. The agency should also establish policies and guidance for implementing key IT management controls.
Full description
Controls in emergency management GAO audited the agency of the Department of Homeland Security, responsible for federal efforts to mitigate, respond to, and recover from disasters. American auditors recommend that the agency fully define its investment board’s roles and responsibilities and procedures for selecting and overseeing investments, update its strategic plan and complete plans for IT modernization, and establish time frames for completing workforce planning efforts. The agency should also establish policies and guidance for implementing key IT management controls.
Full description
General Accountability Office
, issued in 2016
Risk cases: 4
Management of IT security in systems outsourced to external suppliers
Security to be improved in IT processes outsourced to external suppliers When IT processes are outsourced to external suppliers, the authorities no longer have direct control of the IT security, but remain responsible for managing the security of the IT. Authorities that fail to manage IT security actively based on risk assessments, and omit to monitor the implementation of these requirements, will not be able to determine if the level of IT security in the outsourced systems safeguards their systems and data. This is how the conclusion of the Rigsrevisionen starts. The Danish auditors noticed improvement in the audited entities, but they add that tha majority of the auditees: can refine their requirements for and follow-up on access control and logging practices
Full description
Security to be improved in IT processes outsourced to external suppliers When IT processes are outsourced to external suppliers, the authorities no longer have direct control of the IT security, but remain responsible for managing the security of the IT. Authorities that fail to manage IT security actively based on risk assessments, and omit to monitor the implementation of these requirements, will not be able to determine if the level of IT security in the outsourced systems safeguards their systems and data. This is how the conclusion of the Rigsrevisionen starts. The Danish auditors noticed improvement in the audited entities, but they add that tha majority of the auditees: can refine their requirements for and follow-up on access control and logging practices
Full description
National Audit Office of Denmark
, issued in 2016
Risk cases: 3
The Ministry of the Environment lacks a compact information system and still uses 125 separate information systems and databases
of the MoE. The audit identified the following risks: (1) non-existence of the Integrated environmental information system (IEIS) as an independent information system; (2) purchase of ICT, within the budget ... chapter of the MoE, through a state co-funded organisation CENIA which comes under the management of the MoE; (3) utilisation of the information systems. The audited period was 2010 to 2013; where relevant ... The objective of the audit was to scrutinise the management of funds earmarked for the purchase and administration of ICT within the MoE and selected organisations which come under the management ... ... Ministry of the Environment manages 125 information systems and databases ... The Ministry of the Environment (MoE) has for more than 20 years a legal obligation to administer and manage an Integrated Environmental Information System (IEIS). In spite of this fact, the existing ... systems (more than 125 information systems and databases) are designed, implemented and managed as individual information systems without a direct integration into a joint point of reference.
Full description
of the MoE. The audit identified the following risks: (1) non-existence of the Integrated environmental information system (IEIS) as an independent information system; (2) purchase of ICT, within the budget ... chapter of the MoE, through a state co-funded organisation CENIA which comes under the management of the MoE; (3) utilisation of the information systems. The audited period was 2010 to 2013; where relevant ... The objective of the audit was to scrutinise the management of funds earmarked for the purchase and administration of ICT within the MoE and selected organisations which come under the management ... ... Ministry of the Environment manages 125 information systems and databases ... The Ministry of the Environment (MoE) has for more than 20 years a legal obligation to administer and manage an Integrated Environmental Information System (IEIS). In spite of this fact, the existing ... systems (more than 125 information systems and databases) are designed, implemented and managed as individual information systems without a direct integration into a joint point of reference.
Full description
Supreme Audit Office of Czech Republic
, issued in 2015
Risk cases: 7