Results of the development of the state’s information systems
The National Audit Office has repeatedly audited the management and development of the state’s information technology (IT) area in the last ten years. The last audit was performed in 2005. After that ... , several measures have been implemented in the state to organise the development better and to guarantee that the systems are compatible. This audit gives an opinion of the results of development project ... management and the state’s coordination mechanism in this process. ... ... Success and failure depend on preparation ... Conclusions of performance IT audit based on a sample of government projects: business portal, land register, e-police, fire safety monitoring system, childcare information system and the document ... management system of the Defence Forces. Key problems and discussion with auditees are presented.
Full description
National Audit Office of Estonia , issued in 2010
Risk cases: 3
Audit of the key ICT project federal GEVER programme Federal Chancellery
During the first stage, two new GEVER (electronic records and process management) products were procured in an open WTO tender within the framework of the two-product strategy (federal GEVER WTO ... procurement project). CHF 1.6 million was spent on these. The departments and Federal Chancellery (departments/FCh) had to choose one of the two products within three months of the contract being awarded. ... ... Advanced process management system's cost-effectiveness and deadlines at risk ... in order to ensure the successful creation and introduction of GEVER. Previous efforts did not have any widespread success and led to a diverse GEVER landscape. The federal GEVER project has now laid ... Ever since 1990, sequential controls and file management have been part of the Federal Administration's IT landscape (GEVER business administration). Significant obstacles have to be overcome ... the foundations for simplification and centralisation.
Full description
Swiss Federal Audit Office , issued in 2015
Risk cases: 2
Effectiveness of the execution of the eHealth project
The Court of Audit of the Republic of Slovenia has audited how effectively the Ministry of Health had managed the project eHealth - the national plan for developing information system support ... to the national public health system in the period between 1st of January 2004 and 26th of September 2013. The audit has focused on the effectiveness of the Ministry in achieving the project’s goals, time ... management, management of the human resources and financial oversight. The goal of the Ministry was to implement a modern information system, which would support secure eHealth operations and effective ... ... Clear concept, good planning and financial control are indispensable conditions for a successful IT project ... The Court of Audit of the Republic of Slovenia analysed a Government eHealth project. Its goal was to implement a modern information system, which would support the health services and health related ... data. The Court has pointed at a long list of project management fundamentals to be corrected.
Full description
Court of Audit of the Republic of Slovenia , issued in 2013
Risk cases: 5
The National Government Service Centre – Has administration become more effective?
. These viewpoints have been analysed with a special focus on the conditions that applied to the Service Centre when it was formed and the measures taken by the Government and the Service Centre in the first years. ... The purpose of this audit has been to investigate whether the Service Centre has made administrative operational support functions taken over from client agencies more effective, and to find ... explanations for the results so far achieved by the Service Centre. The audit has also aspired to illustrate how agencies that do not subscribe to the services regard their potential for doing so ... ... Has Swedish public administration become more effective? ... The Service Centre – payroll and financial administration IT system for Swedish public agencies under the government – has achieved the target of a subscription rate of 25 per cent of the total ... number of state employees. However, subscription to the Service Centre was initially slower than the Government had predicted and meant lower revenues than expected in autumn 2013. The Service Centre ... then introduced a rigorous review of its expenditure, for example for some planned development initiatives for internal procedures and support systems.<br/>The Swedish NAO noted that the Government’s steering
Full description
Swedish National Audit Office , issued in 2016
Risk cases: 2
Effectiveness of development of broadband network or high-speed internet
The National Audit Office audited whether the state has made every effort to ensure that everyone can have unlimited access to fast internet connection by 2020. The National Audit Office also ... analysed whether the network of fibre-optical cables or the basic broadband network, which is built with European Union support and should guarantee high-speed internet connection, has helped to achieve ... this goal. ... ... ... Slower broadband paid by customers ... The Estonian Information Society Development Plan foresees that high-speed internet of 30 Mbit/s should be accessible to all people in Estonia by 2020 and that 60% of the population will be using ... superfast internet of over 100 Mbit/s. To achieve these goals, the state, with the help of European Union support, decided to establish a broadband network which is not further than 1.5 km from 98% of homes ... and institutions. Private companies have not entirely met the Government's expectations. The Estonian SAI has looked for an answer: Why?
Full description
National Audit Office of Estonia , issued in 2015
Risk cases: 3
The development and use of identification services in public administration
The audit examined the implementation and coordination of projects aimed at developing identification services in public administration, cooperation among authorities in this area and compliance ... with legislation in procuring services. The audit also examined development, control and monitoring structures regarding identification services. The audit focused on electronic identification services that are used ... in public administration's electronic transactions. ... ... Unhealthy competition linked with lack of coordinatnion and with procurement irregularities ... See what may go wrong with the IT public procurement. Check out what is the basis to avoid irregularities or omissions in complying with public procurement legislation. National Audit Office ... of Finland identified also risks resulting from lack of horizontal coordination.
Full description
National Audit Office of Finland , issued in 2008
Risk cases: 3
The implementation of national IT projects in social and health care
IT management expenditure in public administration totalled about 2.1 billion euros in 2009. IT management expenditure by local authorities and federations of municipalities in the field of health ... care totalled about 270 million euros ino 2009. Health care's share of IT management expenditure in public administration thus amounted to about 13 per cent in 2009. ... ... IT-centred manner of project implementation can harm IT investments' results ... SAI Finland perfomed a vast review of IT projects in health and social protection. Many interesting findings cover structural problems, as 'Many separate systems with no future' and characteristics ... of poor governance, as 'No cost monitoring - unclear objectives - arguable usefulness'.
Full description
National Audit Office of Finland , issued in 2011
Risk cases: 3
State funds spent on development, operation and using of data centres services
The aim of the audit was to scrutinise the management of funds spent on building and operating the national data centre (hereinafter “STC1 data centre”), including the expenditure of selected ... organisational units of the state on buying hosting, server-housing and other related services. The audited period was between 2010 and 2014; where relevant, the preceding period was also scrutinised. Audited ... entities: Ministry of the Interior (“MoI”); Ministry of Finance (“MoF”); STÁTNÍ TISKÁRNA CENIN, state firm (state banknote printing firm, hereinafter “STC” or “the state firm”). The audit was conducted ... ... Risks steming from uncoordinated strategy ... SAI of Czech Republic analysed consequences of failures in strategic IT management at the state level. Lack of coordination and implementation rules reduced practical role of the ministry whose task ... was to guard high quality standards for all crucial IT systems in the state administration. Next consecquences were (among others) risk of uneconomical results of large IT investment and risk of inefficient ... supply of services, as well as opposite results of workforce reduction.
Full description
Supreme Audit Office of Czech Republic , issued in 2015
Risk cases: 7
Preparations and realization of the State A-levels
The aim of the audit was to scrutinise the utilisation of the state budget and EU budget funds that had been spent on preparing and implementing the State A-levels examinations. The auditing ... operation was performed from May to November 2011. The audited period extended from January 1, 2005, to June 30, 2011; where relevant, the data from the previous period and the period until the end ... of the auditing operation were also scrutinized. Among the audited bodies were the Ministry of Education, the Education Result Survey Centre, and the National Institute for Further Education. The auditing operation ... ... Begin with good strategy ... Analyzing problems of state examinations system, Czech Republic SAI found that commonplace strategy effected in shortsighted planning, poor procurement and disadvantageous contracting.
Full description
Supreme Audit Office of Czech Republic , issued in 2011
Risk cases: 4
Evaluation of the effectiveness of implementation and compliance with regulatory enactments and the legal framework of the project “E-government Portfolio”
The objective of the audit is to evaluate the effectiveness of implementation and compliance with regulatory enactments and the legal framework of the project “Egovernment Portfolio” of the national ... programme of the European Regional Development Fund (hereinafter: ERDF) of the European Union (hereinafter: EU), “Development and improvement of the infrastructural foundation for electronic governance”. ... ... Funds to absorb but no efficient project methodology? Be prepared for troubles ... Wide list of problems that can be met when more care is received by 'absorb funds' objective than by clear vision what and how can be improved. SAI Latvia's analysis shows how dangerous it can ... be for both effectiveness and financial management.
Full description
State Audit Office of Latvia , issued in 2010
Risk cases: 3