6
results found in
5 ms
Page 1
of 1
The National Offender Management Information System (NOMIS)
for project’s cost reduction, the aims of the revised National Offender Management Service (NOMS) and the progress made, the impact of the delays and rescoping on the costs and benefits achieved, and NOMS ... This report examines the reasons for the delays and cost increases to the original integrated information system and, since the moratorium imposed by the Minister of State in order to seek options ... ’ fitness to deliver. The aim of one integrated information system (C-NOMIS i.e. National Offender Management Information System) was to improve information sharing about offenders; address the lack ... Rescoping necessary, but not fully successful ... by poor management leading to a three-year delay, a doubling in project costs and reductions in scope and benefits. ... An initiative to build a single offender management IT system for the prison and probation services has not delivered value for money. The NAO investigation found the project had been hampered
Full description
for project’s cost reduction, the aims of the revised National Offender Management Service (NOMS) and the progress made, the impact of the delays and rescoping on the costs and benefits achieved, and NOMS ... This report examines the reasons for the delays and cost increases to the original integrated information system and, since the moratorium imposed by the Minister of State in order to seek options ... ’ fitness to deliver. The aim of one integrated information system (C-NOMIS i.e. National Offender Management Information System) was to improve information sharing about offenders; address the lack ... Rescoping necessary, but not fully successful ... by poor management leading to a three-year delay, a doubling in project costs and reductions in scope and benefits. ... An initiative to build a single offender management IT system for the prison and probation services has not delivered value for money. The NAO investigation found the project had been hampered
Full description
National Audit Office
, issued in 2009
Risk cases: 4
Audit of the key ICT project federal GEVER programme Federal Chancellery
During the first stage, two new GEVER (electronic records and process management) products were procured in an open WTO tender within the framework of the two-product strategy (federal GEVER WTO ... procurement project). CHF 1.6 million was spent on these. The departments and Federal Chancellery (departments/FCh) had to choose one of the two products within three months of the contract being awarded. ... ... Advanced process management system's cost-effectiveness and deadlines at risk ... Ever since 1990, sequential controls and file management have been part of the Federal Administration's IT landscape (GEVER business administration). Significant obstacles have to be overcome ... in order to ensure the successful creation and introduction of GEVER. Previous efforts did not have any widespread success and led to a diverse GEVER landscape. The federal GEVER project has now laid ... the foundations for simplification and centralisation.
Full description
During the first stage, two new GEVER (electronic records and process management) products were procured in an open WTO tender within the framework of the two-product strategy (federal GEVER WTO ... procurement project). CHF 1.6 million was spent on these. The departments and Federal Chancellery (departments/FCh) had to choose one of the two products within three months of the contract being awarded. ... ... Advanced process management system's cost-effectiveness and deadlines at risk ... Ever since 1990, sequential controls and file management have been part of the Federal Administration's IT landscape (GEVER business administration). Significant obstacles have to be overcome ... in order to ensure the successful creation and introduction of GEVER. Previous efforts did not have any widespread success and led to a diverse GEVER landscape. The federal GEVER project has now laid ... the foundations for simplification and centralisation.
Full description
Swiss Federal Audit Office
, issued in 2015
Risk cases: 2
Managing the risk of legacy ICT to public service delivery
The cross-government report describes the case studies from four public services (state pension, Value Added Tax collection, prescription payment and consumer credit licensing services) selected ... to illustrate the range of approaches that small and large government bodies are taking to address the issues arising from legacy ICT (defined as "systems and applications that have been operationally embedded ... within a business function but superseded by newer and more effective technologies or changed business needs"). ... Possible approaches to the problem of 'legacy ICT' ... UK’s government experience in managing the risks connected to legacy ICT provides valuable insight for others facing the same problem and are considering transforming their services.
Full description
The cross-government report describes the case studies from four public services (state pension, Value Added Tax collection, prescription payment and consumer credit licensing services) selected ... to illustrate the range of approaches that small and large government bodies are taking to address the issues arising from legacy ICT (defined as "systems and applications that have been operationally embedded ... within a business function but superseded by newer and more effective technologies or changed business needs"). ... Possible approaches to the problem of 'legacy ICT' ... UK’s government experience in managing the risks connected to legacy ICT provides valuable insight for others facing the same problem and are considering transforming their services.
Full description
National Audit Office
, issued in 2013
Risk cases: 3
Software management assessment in local governments and local government educational institutions
Objective of the audit was to verify compliance of software recording and management with regulatory enactments, as well as to assess the effectiveness of software management in local governments ... and local government educational institutions. ... ... Software management assessment in local governments and local government educational institutions ... Manage your software! Local governments and local government education institution neglect basic safety procedures, use outdated or illegal kinds of software, use two and more different software ... for the same function.
Full description
Objective of the audit was to verify compliance of software recording and management with regulatory enactments, as well as to assess the effectiveness of software management in local governments ... and local government educational institutions. ... ... Software management assessment in local governments and local government educational institutions ... Manage your software! Local governments and local government education institution neglect basic safety procedures, use outdated or illegal kinds of software, use two and more different software ... for the same function.
Full description
State Audit Office of the Republic of Latvia
, issued in 2013
Risk cases: 4
State funds spent on development, operation and using of data centres services
The aim of the audit was to scrutinise the management of funds spent on building and operating the national data centre (hereinafter “STC1 data centre”), including the expenditure of selected ... organisational units of the state on buying hosting, server-housing and other related services. The audited period was between 2010 and 2014; where relevant, the preceding period was also scrutinised. Audited ... entities: Ministry of the Interior (“MoI”); Ministry of Finance (“MoF”); STÁTNÍ TISKÁRNA CENIN, state firm (state banknote printing firm, hereinafter “STC” or “the state firm”). The audit was conducted ... ... Risks steming from uncoordinated strategy ... SAI of Czech Republic analysed consequences of failures in strategic IT management at the state level. Lack of coordination and implementation rules reduced practical role of the ministry whose task ... was to guard high quality standards for all crucial IT systems in the state administration. Next consecquences were (among others) risk of uneconomical results of large IT investment and risk of inefficient ... supply of services, as well as opposite results of workforce reduction.
Full description
The aim of the audit was to scrutinise the management of funds spent on building and operating the national data centre (hereinafter “STC1 data centre”), including the expenditure of selected ... organisational units of the state on buying hosting, server-housing and other related services. The audited period was between 2010 and 2014; where relevant, the preceding period was also scrutinised. Audited ... entities: Ministry of the Interior (“MoI”); Ministry of Finance (“MoF”); STÁTNÍ TISKÁRNA CENIN, state firm (state banknote printing firm, hereinafter “STC” or “the state firm”). The audit was conducted ... ... Risks steming from uncoordinated strategy ... SAI of Czech Republic analysed consequences of failures in strategic IT management at the state level. Lack of coordination and implementation rules reduced practical role of the ministry whose task ... was to guard high quality standards for all crucial IT systems in the state administration. Next consecquences were (among others) risk of uneconomical results of large IT investment and risk of inefficient ... supply of services, as well as opposite results of workforce reduction.
Full description
Supreme Audit Office of Czech Republic
, issued in 2015
Risk cases: 7
Audit of the key ICT project regarding a consumption tax platform Federal Customs Administration (FCA)
The Swiss Federal Audit Office (SFAO) audited the key ICT project concerning a consumption tax platform from May to June 2015. The programme was launched in January 2014 with a budget of CHF 13.5 ... million. The instructing parties were the management of the Federal Customs Administration (FCA), the Swiss Alcohol Board (SAB) and the Federal Office of Information Technology, Systems ... and Telecommunication (FOITT). ... ... First attempt to ITC consumption tax project ... SAI Switzerland analised problems steming from insufficient specification of a complex ICT system project concerning a consumption tax platform. The project's budget turned out to cover only 70 ... % of the expected functions. Suspension of the project and restarting preparations stage followed.
Full description
The Swiss Federal Audit Office (SFAO) audited the key ICT project concerning a consumption tax platform from May to June 2015. The programme was launched in January 2014 with a budget of CHF 13.5 ... million. The instructing parties were the management of the Federal Customs Administration (FCA), the Swiss Alcohol Board (SAB) and the Federal Office of Information Technology, Systems ... and Telecommunication (FOITT). ... ... First attempt to ITC consumption tax project ... SAI Switzerland analised problems steming from insufficient specification of a complex ICT system project concerning a consumption tax platform. The project's budget turned out to cover only 70 ... % of the expected functions. Suspension of the project and restarting preparations stage followed.
Full description
Swiss Federal Audit Office
, issued in 2015
Risk cases: 1
6
results found.
Page 1
of 1