Audit of the key ICT project federal GEVER programme Federal Chancellery
During the first stage, two new GEVER (electronic records and process management) products were procured in an open WTO tender within the framework of the two-product strategy (federal GEVER WTO ... procurement project). CHF 1.6 million was spent on these. The departments and Federal Chancellery (departments/FCh) had to choose one of the two products within three months of the contract being awarded. ... ... Advanced process management system's cost-effectiveness and deadlines at risk ... Ever since 1990, sequential controls and file management have been part of the Federal Administration's IT landscape (GEVER business administration). Significant obstacles have to be overcome ... in order to ensure the successful creation and introduction of GEVER. Previous efforts did not have any widespread success and led to a diverse GEVER landscape. The federal GEVER project has now laid ... the foundations for simplification and centralisation.
Full description
During the first stage, two new GEVER (electronic records and process management) products were procured in an open WTO tender within the framework of the two-product strategy (federal GEVER WTO ... procurement project). CHF 1.6 million was spent on these. The departments and Federal Chancellery (departments/FCh) had to choose one of the two products within three months of the contract being awarded. ... ... Advanced process management system's cost-effectiveness and deadlines at risk ... Ever since 1990, sequential controls and file management have been part of the Federal Administration's IT landscape (GEVER business administration). Significant obstacles have to be overcome ... in order to ensure the successful creation and introduction of GEVER. Previous efforts did not have any widespread success and led to a diverse GEVER landscape. The federal GEVER project has now laid ... the foundations for simplification and centralisation.
Full description
Swiss Federal Audit Office
, issued in 2015
Risk cases: 2
Managing the risk of legacy ICT to public service delivery
The cross-government report describes the case studies from four public services (state pension, Value Added Tax collection, prescription payment and consumer credit licensing services) selected ... to illustrate the range of approaches that small and large government bodies are taking to address the issues arising from legacy ICT (defined as "systems and applications that have been operationally embedded ... within a business function but superseded by newer and more effective technologies or changed business needs"). ... Possible approaches to the problem of 'legacy ICT' ... UK’s government experience in managing the risks connected to legacy ICT provides valuable insight for others facing the same problem and are considering transforming their services.
Full description
The cross-government report describes the case studies from four public services (state pension, Value Added Tax collection, prescription payment and consumer credit licensing services) selected ... to illustrate the range of approaches that small and large government bodies are taking to address the issues arising from legacy ICT (defined as "systems and applications that have been operationally embedded ... within a business function but superseded by newer and more effective technologies or changed business needs"). ... Possible approaches to the problem of 'legacy ICT' ... UK’s government experience in managing the risks connected to legacy ICT provides valuable insight for others facing the same problem and are considering transforming their services.
Full description
National Audit Office
, issued in 2013
Risk cases: 3
Audit of the key ICT project regarding a consumption tax platform Federal Customs Administration (FCA)
The Swiss Federal Audit Office (SFAO) audited the key ICT project concerning a consumption tax platform from May to June 2015. The programme was launched in January 2014 with a budget of CHF 13.5 ... million. The instructing parties were the management of the Federal Customs Administration (FCA), the Swiss Alcohol Board (SAB) and the Federal Office of Information Technology, Systems ... and Telecommunication (FOITT). ... ... First attempt to ITC consumption tax project ... SAI Switzerland analised problems steming from insufficient specification of a complex ICT system project concerning a consumption tax platform. The project's budget turned out to cover only 70 ... % of the expected functions. Suspension of the project and restarting preparations stage followed.
Full description
The Swiss Federal Audit Office (SFAO) audited the key ICT project concerning a consumption tax platform from May to June 2015. The programme was launched in January 2014 with a budget of CHF 13.5 ... million. The instructing parties were the management of the Federal Customs Administration (FCA), the Swiss Alcohol Board (SAB) and the Federal Office of Information Technology, Systems ... and Telecommunication (FOITT). ... ... First attempt to ITC consumption tax project ... SAI Switzerland analised problems steming from insufficient specification of a complex ICT system project concerning a consumption tax platform. The project's budget turned out to cover only 70 ... % of the expected functions. Suspension of the project and restarting preparations stage followed.
Full description
Swiss Federal Audit Office
, issued in 2015
Risk cases: 1
Risks of e-Governance Strategy Dominated by Outsourcing
Audit of IT service in Ministry of Public Assets gave an opportunity to analize risks related to outsourcing dominated e-Governance strategy. Important findings were identified in preparation ... and testing stages, stemming from poor Business Case. ... ... IT outsourcing risks ... Presentation based on audit of IT services in Polish Ministry of Public Assets. Outsourcing risks were classified and next identified at Business Case, preparation and teststing stages.
Full description
Audit of IT service in Ministry of Public Assets gave an opportunity to analize risks related to outsourcing dominated e-Governance strategy. Important findings were identified in preparation ... and testing stages, stemming from poor Business Case. ... ... IT outsourcing risks ... Presentation based on audit of IT services in Polish Ministry of Public Assets. Outsourcing risks were classified and next identified at Business Case, preparation and teststing stages.
Full description
Supreme Audit Office of Poland
, issued in 2010
Risk cases: 4
Performance Audit of the Georgian Government electronic Procurement system
State procurement is one of the key components of public financial management. Its share in state budget is approximately 25 percent. Effective management of state procurements is an important sphere ... of a high-quality service has a particular importance. <br /> It is noteworthy that establishment of open, transparent and competitive environment for the procurement parties mitigates the risks of corruption ... of interest for the State Audit Office. Considering the fact that since 2010 major part of public procurements is being conducted electronically and there is no alternative tool, uninterrupted provision ... ... Electronic procurement system - how effective are management and control mechanisms? ... SAI Georgia analyzed the electronic Government Procurement system. In their report they focus on compliance and security problems, which may harm the business goals and overall mission of the system.
Full description
State procurement is one of the key components of public financial management. Its share in state budget is approximately 25 percent. Effective management of state procurements is an important sphere ... of a high-quality service has a particular importance. <br /> It is noteworthy that establishment of open, transparent and competitive environment for the procurement parties mitigates the risks of corruption ... of interest for the State Audit Office. Considering the fact that since 2010 major part of public procurements is being conducted electronically and there is no alternative tool, uninterrupted provision ... ... Electronic procurement system - how effective are management and control mechanisms? ... SAI Georgia analyzed the electronic Government Procurement system. In their report they focus on compliance and security problems, which may harm the business goals and overall mission of the system.
Full description
State Audit Office Of Georgia
, issued in 2016
Risk cases: 5
Management and protection of assets in the field of the information-communication technologies at the ME SR
control of backup's functionality), restoring and security, possibility of unauthorised persons to access the IS and data, which increases the risk of information leakage and security risk, and inadequate ... The Supreme Audit office of the Slovak Republic (SAO SR) has conducted the audit at the Ministry of Environment of the Slovak Republic (ME SR) for the audit period 2011 and 2012 to examine ... the compliance with the generally binding legal regulations and the general statues in the field of the information-communication technologies (ICT) and the information systems of the public administration (ISPA ... ... Started from contracting, ended in security ... and ended in exposing the organization to high security risks. ... The perceptive and filled with findings audit - conducted by the Slovak SAI - discovered the list of issues which started in careless contracting procedures, failure to update the development concept
Full description
control of backup's functionality), restoring and security, possibility of unauthorised persons to access the IS and data, which increases the risk of information leakage and security risk, and inadequate ... The Supreme Audit office of the Slovak Republic (SAO SR) has conducted the audit at the Ministry of Environment of the Slovak Republic (ME SR) for the audit period 2011 and 2012 to examine ... the compliance with the generally binding legal regulations and the general statues in the field of the information-communication technologies (ICT) and the information systems of the public administration (ISPA ... ... Started from contracting, ended in security ... and ended in exposing the organization to high security risks. ... The perceptive and filled with findings audit - conducted by the Slovak SAI - discovered the list of issues which started in careless contracting procedures, failure to update the development concept
Full description
Supreme Audit Office of the Slovak Republic
, issued in 2012
Risk cases: 4
State funds spent on development, operation and using of data centres services
The aim of the audit was to scrutinise the management of funds spent on building and operating the national data centre (hereinafter “STC1 data centre”), including the expenditure of selected ... organisational units of the state on buying hosting, server-housing and other related services. The audited period was between 2010 and 2014; where relevant, the preceding period was also scrutinised. Audited ... entities: Ministry of the Interior (“MoI”); Ministry of Finance (“MoF”); STÁTNÍ TISKÁRNA CENIN, state firm (state banknote printing firm, hereinafter “STC” or “the state firm”). The audit was conducted ... ... Risks steming from uncoordinated strategy ... was to guard high quality standards for all crucial IT systems in the state administration. Next consecquences were (among others) risk of uneconomical results of large IT investment and risk of inefficient ... SAI of Czech Republic analysed consequences of failures in strategic IT management at the state level. Lack of coordination and implementation rules reduced practical role of the ministry whose task ... supply of services, as well as opposite results of workforce reduction.
Full description
The aim of the audit was to scrutinise the management of funds spent on building and operating the national data centre (hereinafter “STC1 data centre”), including the expenditure of selected ... organisational units of the state on buying hosting, server-housing and other related services. The audited period was between 2010 and 2014; where relevant, the preceding period was also scrutinised. Audited ... entities: Ministry of the Interior (“MoI”); Ministry of Finance (“MoF”); STÁTNÍ TISKÁRNA CENIN, state firm (state banknote printing firm, hereinafter “STC” or “the state firm”). The audit was conducted ... ... Risks steming from uncoordinated strategy ... was to guard high quality standards for all crucial IT systems in the state administration. Next consecquences were (among others) risk of uneconomical results of large IT investment and risk of inefficient ... SAI of Czech Republic analysed consequences of failures in strategic IT management at the state level. Lack of coordination and implementation rules reduced practical role of the ministry whose task ... supply of services, as well as opposite results of workforce reduction.
Full description
Supreme Audit Office of Czech Republic
, issued in 2015
Risk cases: 7
Lessons learned from government ICT-projects
This audit has been performed on request of the Dutch parliament. Some newspapers mentioned government losses of four to five billion euro's on a yearly bases. These news items caused the parliament ... to request this audit. The audit has been performed in only 5 months time and consisted of the re-use of earlier performed audits. We have 'recycled' earlier findings about ICT-projects. ... 'Expensive' does not always mean 'High Quality', so... do not feed the spiral ... Excellent analysis of systemic errors commited when designing Government IT projects. The report aims at the essence of problems which are encountered far from information technologies - in: politics ... , business, psychology... Do not be mislead by date of report, it is evergreen for all who really want to know why IT projects fail.
Full description
This audit has been performed on request of the Dutch parliament. Some newspapers mentioned government losses of four to five billion euro's on a yearly bases. These news items caused the parliament ... to request this audit. The audit has been performed in only 5 months time and consisted of the re-use of earlier performed audits. We have 'recycled' earlier findings about ICT-projects. ... 'Expensive' does not always mean 'High Quality', so... do not feed the spiral ... Excellent analysis of systemic errors commited when designing Government IT projects. The report aims at the essence of problems which are encountered far from information technologies - in: politics ... , business, psychology... Do not be mislead by date of report, it is evergreen for all who really want to know why IT projects fail.
Full description
Netherlands Court of Audits
, issued in 2007
Risk cases: 3
The National Offender Management Information System (NOMIS)
This report examines the reasons for the delays and cost increases to the original integrated information system and, since the moratorium imposed by the Minister of State in order to seek options ... for project’s cost reduction, the aims of the revised National Offender Management Service (NOMS) and the progress made, the impact of the delays and rescoping on the costs and benefits achieved, and NOMS ... ’ fitness to deliver. The aim of one integrated information system (C-NOMIS i.e. National Offender Management Information System) was to improve information sharing about offenders; address the lack ... Rescoping necessary, but not fully successful ... An initiative to build a single offender management IT system for the prison and probation services has not delivered value for money. The NAO investigation found the project had been hampered ... by poor management leading to a three-year delay, a doubling in project costs and reductions in scope and benefits.
Full description
This report examines the reasons for the delays and cost increases to the original integrated information system and, since the moratorium imposed by the Minister of State in order to seek options ... for project’s cost reduction, the aims of the revised National Offender Management Service (NOMS) and the progress made, the impact of the delays and rescoping on the costs and benefits achieved, and NOMS ... ’ fitness to deliver. The aim of one integrated information system (C-NOMIS i.e. National Offender Management Information System) was to improve information sharing about offenders; address the lack ... Rescoping necessary, but not fully successful ... An initiative to build a single offender management IT system for the prison and probation services has not delivered value for money. The NAO investigation found the project had been hampered ... by poor management leading to a three-year delay, a doubling in project costs and reductions in scope and benefits.
Full description
National Audit Office
, issued in 2009
Risk cases: 4
Software management assessment in local governments and local government educational institutions
Objective of the audit was to verify compliance of software recording and management with regulatory enactments, as well as to assess the effectiveness of software management in local governments ... and local government educational institutions. ... ... Software management assessment in local governments and local government educational institutions ... Manage your software! Local governments and local government education institution neglect basic safety procedures, use outdated or illegal kinds of software, use two and more different software ... for the same function.
Full description
Objective of the audit was to verify compliance of software recording and management with regulatory enactments, as well as to assess the effectiveness of software management in local governments ... and local government educational institutions. ... ... Software management assessment in local governments and local government educational institutions ... Manage your software! Local governments and local government education institution neglect basic safety procedures, use outdated or illegal kinds of software, use two and more different software ... for the same function.
Full description
State Audit Office of the Republic of Latvia
, issued in 2013
Risk cases: 4