The aim of the audit was to scrutinise the management of funds spent on building and operating the national data centre (hereinafter “STC1 data centre”), including the expenditure of selected ... organisational units of the state on buying hosting, server-housing and other related services. The audited period was between 2010 and 2014; where relevant, the preceding period was also scrutinised. Audited ... entities: Ministry of the Interior (“MoI”); Ministry of Finance (“MoF”); STÁTNÍ TISKÁRNA CENIN, state firm (state banknote printing firm, hereinafter “STC” or “the state firm”). The audit was conducted ... ... Risks steming from uncoordinated strategy ... SAI of Czech Republic analysed consequences of failures in strategic IT management at the state level. Lack of coordination and implementation rules reduced practical role of the ministry whose task ... was to guard high quality standards for all crucial IT systems in the state administration. Next consecquences were (among others) risk of uneconomical results of large IT investment and risk of inefficient ... supply of services, as well as opposite results of workforce reduction.
Full description
The aim of the audit was to scrutinise the management of funds spent on building and operating the national data centre (hereinafter “STC1 data centre”), including the expenditure of selected ... organisational units of the state on buying hosting, server-housing and other related services. The audited period was between 2010 and 2014; where relevant, the preceding period was also scrutinised. Audited ... entities: Ministry of the Interior (“MoI”); Ministry of Finance (“MoF”); STÁTNÍ TISKÁRNA CENIN, state firm (state banknote printing firm, hereinafter “STC” or “the state firm”). The audit was conducted ... ... Risks steming from uncoordinated strategy ... SAI of Czech Republic analysed consequences of failures in strategic IT management at the state level. Lack of coordination and implementation rules reduced practical role of the ministry whose task ... was to guard high quality standards for all crucial IT systems in the state administration. Next consecquences were (among others) risk of uneconomical results of large IT investment and risk of inefficient ... supply of services, as well as opposite results of workforce reduction.
Full description
Supreme Audit Office of Czech Republic
, issued in 2015
Risk cases: 7
Maintenance efficiency in the rail network
the Ministry of Transport and Communications, and its responsibilities include operation, maintenance and development of the State's railway infrastructure. The maintenance activities must safeguard safety ... The primary objective of railway politics is to contribute to ensure that users of the transport service have good railway options. The Norwegian National Rail Administration is organised under ... , fixed assets and operational stability of the railway system. The most important objective for the maintenance is to reduce the scope of operational interruptions, and to facilitate better punctuality ... ... Rail network maintenance - negative balance of costs and results ... SAI Norway evaluated efficiency of the railway maintenance and found that its costs increased nearly 110 per cent in years 2006–2014. Negative development in uptime and regularity dominated the first ... part of the examined period, from 2006 to 2011. It turned positive from 2011, but in 2014 results were still worse than in 2006. The results have lagged behind the Ministry's target figures for most ... of the period.
Full description
the Ministry of Transport and Communications, and its responsibilities include operation, maintenance and development of the State's railway infrastructure. The maintenance activities must safeguard safety ... The primary objective of railway politics is to contribute to ensure that users of the transport service have good railway options. The Norwegian National Rail Administration is organised under ... , fixed assets and operational stability of the railway system. The most important objective for the maintenance is to reduce the scope of operational interruptions, and to facilitate better punctuality ... ... Rail network maintenance - negative balance of costs and results ... SAI Norway evaluated efficiency of the railway maintenance and found that its costs increased nearly 110 per cent in years 2006–2014. Negative development in uptime and regularity dominated the first ... part of the examined period, from 2006 to 2011. It turned positive from 2011, but in 2014 results were still worse than in 2006. The results have lagged behind the Ministry's target figures for most ... of the period.
Full description
Office of the Auditor General of Norway
, issued in 2016
Risk cases: 2
Management and protection of assets in the field of the information-communication technologies at the ME SR
internal and security directives, unidentified critical and strategic Information Systems (IS), absolutely unsatisfying principles, procedures, conditions and policy relating to the data backuping (and ... and lawbreaking, violation of the conditions determined in the particular contracts, documents and agreements (if they were ever found or valid), obsolete conception of the ISPA development, not established ... The Supreme Audit office of the Slovak Republic (SAO SR) has conducted the audit at the Ministry of Environment of the Slovak Republic (ME SR) for the audit period 2011 and 2012 to examine ... ... Started from contracting, ended in security ... The perceptive and filled with findings audit - conducted by the Slovak SAI - discovered the list of issues which started in careless contracting procedures, failure to update the development concept ... and ended in exposing the organization to high security risks.
Full description
internal and security directives, unidentified critical and strategic Information Systems (IS), absolutely unsatisfying principles, procedures, conditions and policy relating to the data backuping (and ... and lawbreaking, violation of the conditions determined in the particular contracts, documents and agreements (if they were ever found or valid), obsolete conception of the ISPA development, not established ... The Supreme Audit office of the Slovak Republic (SAO SR) has conducted the audit at the Ministry of Environment of the Slovak Republic (ME SR) for the audit period 2011 and 2012 to examine ... ... Started from contracting, ended in security ... The perceptive and filled with findings audit - conducted by the Slovak SAI - discovered the list of issues which started in careless contracting procedures, failure to update the development concept ... and ended in exposing the organization to high security risks.
Full description
Supreme Audit Office of the Slovak Republic
, issued in 2012
Risk cases: 4
Performance Audit of Public Debt Management Information Systems
The usage and development of the information technologies in public financial management is an important priority of the country at the phase of intensive implementation of electronic governance ... (E-Governance). The fact that information systems play crucial role in the business processes of the Ministry of Finance affects the state and the public in general. <br/> Bearing in mind the role and importance ... of information systems in the public debt management process and having considered legal requirements to information security, State Audit Office of Georgia conducted Performance Audit of Public Debt Management ... ... More effective IT governance needed ... Importance of effective performance of public debt management e-systems may be explained by the world’s increased dependence on such systems. In parallel with the performance audit of debt management ... information systems of the Ministry Of Finance of Georgia, Supreme Audit Institutions of 11 countries also studied this topic, both in terms of systems’ performance and their practical application by local ... financial institutions. Audit conducted by the State Audit Office of Georgia has revealed security and governance shortcomings related to management and usage of these systems.
Full description
The usage and development of the information technologies in public financial management is an important priority of the country at the phase of intensive implementation of electronic governance ... (E-Governance). The fact that information systems play crucial role in the business processes of the Ministry of Finance affects the state and the public in general. <br/> Bearing in mind the role and importance ... of information systems in the public debt management process and having considered legal requirements to information security, State Audit Office of Georgia conducted Performance Audit of Public Debt Management ... ... More effective IT governance needed ... Importance of effective performance of public debt management e-systems may be explained by the world’s increased dependence on such systems. In parallel with the performance audit of debt management ... information systems of the Ministry Of Finance of Georgia, Supreme Audit Institutions of 11 countries also studied this topic, both in terms of systems’ performance and their practical application by local ... financial institutions. Audit conducted by the State Audit Office of Georgia has revealed security and governance shortcomings related to management and usage of these systems.
Full description
State Audit Office Of Georgia
, issued in 2014
Risk cases: 5
Effectiveness of the Tax Administration of the Republic of Slovenia in the execution of modernisation projects of the Slovenian duty information system and decreasing the number of duty sub-accounts
The Tax Administration of the Republic of Slovenia (hereinafter: the Tax Administration) is responsible for collecting taxes, fees and other compulsory levies (hereinafter: duties ... ). These are the revenue of the state budget, municipal budgets, the Health Insurance Institute of Slovenia, the Institute for Pension and Disability Insurance of Slovenia (hereinafter: duties recipients) and indirectly ... of the European Union budget. In order to improve its operations, the Tax Authority decided to modernise the Slovenian duties’ collection information system. It used this opportunity to implement also a second ... ... Shaky coordination of investments in important systems ... Slovenian SAI traced a series of problems in management of crucial IT investments in tax administration. Apart from promising goals, unclear business case gave a start to many problems at next stages ... of the project, involving additional spendings, delays and errors in data processing.
Full description
The Tax Administration of the Republic of Slovenia (hereinafter: the Tax Administration) is responsible for collecting taxes, fees and other compulsory levies (hereinafter: duties ... ). These are the revenue of the state budget, municipal budgets, the Health Insurance Institute of Slovenia, the Institute for Pension and Disability Insurance of Slovenia (hereinafter: duties recipients) and indirectly ... of the European Union budget. In order to improve its operations, the Tax Authority decided to modernise the Slovenian duties’ collection information system. It used this opportunity to implement also a second ... ... Shaky coordination of investments in important systems ... Slovenian SAI traced a series of problems in management of crucial IT investments in tax administration. Apart from promising goals, unclear business case gave a start to many problems at next stages ... of the project, involving additional spendings, delays and errors in data processing.
Full description
Court of Audit of the Republic of Slovenia
, issued in 2014
Risk cases: 7
Risks of e-Governance Strategy Dominated by Outsourcing
Audit of IT service in Ministry of Public Assets gave an opportunity to analize risks related to outsourcing dominated e-Governance strategy. Important findings were identified in preparation ... and testing stages, stemming from poor Business Case. ... ... IT outsourcing risks ... Presentation based on audit of IT services in Polish Ministry of Public Assets. Outsourcing risks were classified and next identified at Business Case, preparation and teststing stages.
Full description
Audit of IT service in Ministry of Public Assets gave an opportunity to analize risks related to outsourcing dominated e-Governance strategy. Important findings were identified in preparation ... and testing stages, stemming from poor Business Case. ... ... IT outsourcing risks ... Presentation based on audit of IT services in Polish Ministry of Public Assets. Outsourcing risks were classified and next identified at Business Case, preparation and teststing stages.
Full description
Supreme Audit Office of Poland
, issued in 2010
Risk cases: 4
Public access point to the Polish e-Administration
Coordinated audit series (46 auditees) focused on a web solution applied to give an easy access to Government e-services (the project planned to be completed in 2013) The audit was performed in 2008 ... and public report issued in March 2009. Primary goal of th presentation was intended to illustrate the use of 'e-Government Algorithm' elaborated by EUROSAI IT Working Group in 2005. One of issues mede better ... known by the audit was 'Project Frameworks vs Public Procurement'. ... ... Buyer, provider and methodologies need a balance ... Presentation based on a vast audit by Polish SAI which subject was of big network project aiming to provide one access point to Government and Selfgovernments services. The presentation illustrates ... old EUROSAI IT Wg 'Algorithm approach' and focuses on procurement systemic problems.
Full description
Coordinated audit series (46 auditees) focused on a web solution applied to give an easy access to Government e-services (the project planned to be completed in 2013) The audit was performed in 2008 ... and public report issued in March 2009. Primary goal of th presentation was intended to illustrate the use of 'e-Government Algorithm' elaborated by EUROSAI IT Working Group in 2005. One of issues mede better ... known by the audit was 'Project Frameworks vs Public Procurement'. ... ... Buyer, provider and methodologies need a balance ... Presentation based on a vast audit by Polish SAI which subject was of big network project aiming to provide one access point to Government and Selfgovernments services. The presentation illustrates ... old EUROSAI IT Wg 'Algorithm approach' and focuses on procurement systemic problems.
Full description
Supreme Audit Office of Poland
, issued in 2008
Risk cases: 3
Audit of the key ICT project federal GEVER programme Federal Chancellery
During the first stage, two new GEVER (electronic records and process management) products were procured in an open WTO tender within the framework of the two-product strategy (federal GEVER WTO ... procurement project). CHF 1.6 million was spent on these. The departments and Federal Chancellery (departments/FCh) had to choose one of the two products within three months of the contract being awarded. ... ... Advanced process management system's cost-effectiveness and deadlines at risk ... Ever since 1990, sequential controls and file management have been part of the Federal Administration's IT landscape (GEVER business administration). Significant obstacles have to be overcome ... in order to ensure the successful creation and introduction of GEVER. Previous efforts did not have any widespread success and led to a diverse GEVER landscape. The federal GEVER project has now laid ... the foundations for simplification and centralisation.
Full description
During the first stage, two new GEVER (electronic records and process management) products were procured in an open WTO tender within the framework of the two-product strategy (federal GEVER WTO ... procurement project). CHF 1.6 million was spent on these. The departments and Federal Chancellery (departments/FCh) had to choose one of the two products within three months of the contract being awarded. ... ... Advanced process management system's cost-effectiveness and deadlines at risk ... Ever since 1990, sequential controls and file management have been part of the Federal Administration's IT landscape (GEVER business administration). Significant obstacles have to be overcome ... in order to ensure the successful creation and introduction of GEVER. Previous efforts did not have any widespread success and led to a diverse GEVER landscape. The federal GEVER project has now laid ... the foundations for simplification and centralisation.
Full description
Swiss Federal Audit Office
, issued in 2015
Risk cases: 2
The National Offender Management Information System (NOMIS)
This report examines the reasons for the delays and cost increases to the original integrated information system and, since the moratorium imposed by the Minister of State in order to seek options ... for project’s cost reduction, the aims of the revised National Offender Management Service (NOMS) and the progress made, the impact of the delays and rescoping on the costs and benefits achieved, and NOMS ... ’ fitness to deliver. The aim of one integrated information system (C-NOMIS i.e. National Offender Management Information System) was to improve information sharing about offenders; address the lack ... Rescoping necessary, but not fully successful ... An initiative to build a single offender management IT system for the prison and probation services has not delivered value for money. The NAO investigation found the project had been hampered ... by poor management leading to a three-year delay, a doubling in project costs and reductions in scope and benefits.
Full description
This report examines the reasons for the delays and cost increases to the original integrated information system and, since the moratorium imposed by the Minister of State in order to seek options ... for project’s cost reduction, the aims of the revised National Offender Management Service (NOMS) and the progress made, the impact of the delays and rescoping on the costs and benefits achieved, and NOMS ... ’ fitness to deliver. The aim of one integrated information system (C-NOMIS i.e. National Offender Management Information System) was to improve information sharing about offenders; address the lack ... Rescoping necessary, but not fully successful ... An initiative to build a single offender management IT system for the prison and probation services has not delivered value for money. The NAO investigation found the project had been hampered ... by poor management leading to a three-year delay, a doubling in project costs and reductions in scope and benefits.
Full description
National Audit Office
, issued in 2009
Risk cases: 4