Building and Implementing the Phoenix Pay System
Expensive IT project became a failure Phoenix project (development of states pay system) was an incomprehensible failure of project management and oversight. Phoenix executives prioritized certain aspects, such as schedule and budget, over other critical ones, such as functionality and security. Phoenix executives did not understand the importance of warnings that the Miramichi Pay Centre, departments and agencies, and the new system were not ready. They did not provide complete and accurate information to deputy ministers and associate deputy ministers of departments and agencies, including the Deputy Minister of Public Services and Procurement, when briefing them on Phoenix readiness for implementation.
Full description
Office of theAuditor Generalof Canada , issued in 2018
Risk cases: 3
Housing in England: overview
Efforts to support housing Even if housebuilding in England has not kept pace with need and there has been a reduction in social rented homes, significant advantages can be enjoyed: an increase in home ownership and in the number of private rented homes. The quality of housing improved in recent years too. The National Audit Office has reviewed critical elements of the housing being one of the government's key priorities. Looking for risks, they found that a potential conflict of objectives can lead to tensions in delivery.
Full description
National Audit Office , issued in 2017
Risk cases: 2
Centralisation of support services of state authorities
Most goals of centralisation of support services were achived Centralisation of support services of state authorities has generally been successful, the quality of accounting has improved, and accounting has become more effective. The objective of saving on costs was not achieved. It would be beneficial to analyse the implementation of a similar model in local governments, i.e. concentrating the accounting services to central units in order to improve the quality of accounting and make work more effective. It would allow saving working time on doing routine accounting procedures and use this time more for financial management, which helps to use public funds better and more expediently.
Full description
National Audit Office of Estonia , issued in 2018
Risk cases: 2
The protection of valuable forest
Protection of valuable forest Protection of valuable forest land is an important mean of achieving the environmental quality objectives. Governments can establish formal protection of forests through the formation of national parks, biotope conservation areas, nature reserves or by signing nature conservation agreements. Beyond the state's formal protection of forests, the forest owners themselves are also expected to contribute through voluntary set-asides of forest. From a state perspective, it is important to investigate whether or not the resources for formal protection are being used cost-effectively. However, in order to achieve cost-effective formal protection work, the state also needs to address forest owners' voluntary set asides.
Full description
Swedish National Audit Office , issued in 2018
Risk cases: 4
Federal Human Resources Data
Internal control weaknesses may put mission at risk GAO audited the Enterprise Human Resources Integration payroll data warehose. The American auditors pointed at problems that may impede 'leverage of these data to meet its mission and allow others to make full use' of them. The critical internal contols areas to be improved in this cas are: completeness, accuracy, and validity of information, authorization, documentation, monitoring, results' evaluation.
Full description
General Accountability Office , issued in 2016
Risk cases: 2
Has Public Administration Used All Opportunities for Efficient Management of ICT Infrastructure?
Efficient Management of ICT Infrastructure Centralised management of ICT services and infrastructure would allow the institutions to optimise in long run their resources – financial, human, material and technical. However, we observed during the audit that the move towards ICT centralisation and single data centres has ceased. The different ministries and even the institutions subordinated to the same ministry do not cooperate sufficiently with each other regarding the ICT management, maintenance, and infrastructure placement. They rather choose to maintain their own, sometimes even several, data centres.
Full description
State Audit Office of the Republic of Latvia , issued in 2019
Risk cases: 3
Coordinated Audit on Information Technology Governance
IT governance needs awareness and SAIs' support The OLACEFS auditors found that the greatest challenge for the SAIs is to raise the awareness of the audit institutions about the importance of IT governance and the benefits that could be obtained by improving its degree of maturity. The audit was conducted by 11 SAIs and coordinated by TCU of Brasil. They concluded: 'It is important, even urgent, to invest resources to implement or enhance: the IT committees; the IT planning process; strategic IT planning; monitoring the IT contracting process; the business continuity plan; the designation of a responsible person or unit to manage security information; a risk management process; an asset inventory process; an information security committee; and a policy for access control.'
Full description
Latin American andCaribbean Organization of Supreme Audit Institutions , issued in 2015
Risk cases: 5
Usability of public digital services directed at businesses
G2B - in search of user friendliness Danish Rigsrevisionen finds that the digital services directed at businesses, examined during this audit, are not sufficiently user-friendly from start to finish, and the authorities need to focus more on ensuring that relevant solutions are interlinked in a userfriendly manner.
Full description
National Audit Office of Denmark , issued in 2015
Risk cases: 3
Recovery of housing allowance - easy to make mistakes
Avoid mistakes in housing allowance recovery Housing allowance recovery rules are complex and outdated. What more, ad hoc changes can result in unpredicted deficiencies. The Swedish NAO found that monitoring and evaluation based analysis is of critical importance to avoid problems on the administration side - and what much more important: on the side of financialy vulnerable households.
Full description
Swedish National Audit Office , issued in 2018
Risk cases: 4
Homeland Security. Oversight of Neglected Human Resources Information Technology Investment Is Needed
Human resources IT investments get stuck in management's lack of interest Although the Human Resources Information Technology (HRIT) investment was initiated about 12 years ago with the intent to consolidate, integrate, and modernize the department's human resources IT infrastructure, the Department of Homeland Security (DHS) has made very limited progress in achieving these goals. HRIT's minimally involved executive steering committee during a time when significant problems were occurring was a key factor in the lack of progress. This is particularly problematic given that the department's ability to efficiently and effectively carry out its mission is significantly hampered by its fragmented human resources. DHS's ineffective management of HRIT, such as the lack of an updated schedule and a life-cycle cost estimate, also contributed to the neglect this investment has experienced. DHS will be limited in efficiently tracking and reporting accurate, comprehensive performance and learning management data across the organization, and could risk further implementation delays.
Full description
US Government Accountability Office , issued in 2016
Risk cases: 1