Audit of the Government, Government-guaranteed and Municipal Debt Management Information Systems in the Ministry of Finance of the Republic of Bulgaria
The main audit question studied during the audit was: Are the government, government-guaranteed (SDMS) and municipal debt management information systems (CMDR) at the Ministry of Finance effective ... ? The audit covered the period from 01.01.2013 to 31.12.2013 and investigated four major areas: IT system strategy and general management; IT security and controls against disasters; Operational controls ... and Documentation; Application Controls. ... ... Even effective and modern IT systems require improvements and updates to ensure their security and accountability ... For the management of the government, government-guaranteed and municipal debt the Ministry of Finance has established an advanced integrated information infrastructure. According to Bulgarian SAI ... the established system is effective and provides updated, complete and correct information. Nevertheless the audit report points out areas of security, application controls as well as documentation as the subjects ... that need further improvement and optimization.
Full description
Bulgarian National Audit Office , issued in 2014
Risk cases: 3
IT Support in the Judicial Chain
The Swedish National Audit Office has examined how well agencies in the judicial chain have handled known flaws in their IT support and whether the Government’s control mechanisms have provided ... the agencies with sufficient prerequisites to expand and improve IT support. ... ... Needed: good conditions by government, better steering and control by authorities ... Despite many years’ of work to modernize the IT support within the judiciary, there are still many deficiencies. The Government has not given the authorities good conditions enough to lead the work ... . The authorities, in their turn, need to improve their steering and control, as well as interact to a much higher degree.
Full description
Swedish National Audit Office , issued in 2011
Risk cases: 3
Operation of the Record Systems Applied in the Eligibility Scheme of Benefits and Services Provided from the Social Security Funds
Hungarian SAI evaluated the set-up and operation of the basic registries of managing bodies (National Health Insurance Fund, Central Administration of National Pension Insurance, National Tax ... and Customs Administration), as well as the dataflow amongst them. In addition, the control system of fulfilling the data provision obligation was evaluated, as well as the IT support activities and whether ... the records had proven reliable in supporting services in compliance with eligibilities and in filtering unjustified services. The audited period covered the years 2007-2010. ... ... Well considered regulations are essential for good quality data ... State Audit Office of Hungary.has proved that date safety may depend on quality of regulations. The report on record systems of social security services casted light on risk connected with huge data ... bases managed by different entities, in a changing legal environment.
Full description
State Audit Office of Hungary , issued in 2012
Risk cases: 2
Audit on the broadband internet infrastructure access
Poland has been granted over PLN 4 billion from the European Regional Development Fund to build the broadband internet access infrastructure. As part of three operational programmes 90 percent ... of assumed financing was contracted, namely PLN 3.9 billion. By the end of 2015, Poland should complete the investment and account for the expenses. According to NIK there is a risk that the infrastructure ... construction will not be completed by the deadline and the EU funds may not be used to the full. ... ... Simpler regulations and better supervision needed ... Polish SAI audited a project, which aim had been to develop broadband internet network across the country. They revealed that legal obstacles, idleness and lack of supervision were the main causes ... of delays. Some of the projects are in danger of not being completed on time and some of the EU funds may not be fully used.
Full description
Supreme Audit Office of Poland , issued in 2015
Risk cases: 2
THE CYBER SECURITY ENVIRONMENT IN LITHUANIA
The purpose of the audit was to assess whether cyber security is being ensured in Lithuania. In view of this goal, we assessed whether: (1) an effective cyber security system has been set up; (2 ... ) cyber security is ensured in public establishments. During the audit, the SAI Lithuania analysed current regulation, strategic planning and management practices in the field of cyber security ... and electronic information security as well as the funds allocated and used in this area. The SAI evaluated whether the cyber security and electronic information security objectives detailed in planning documents ... ... Cyber-security is much more than preventing incidents ... SAI Lithuania determined that the issue of ensuring and increasing cyber security and resilience has not been effectively addressed at the national level. The focus has primarily been on reacting ... to and preventing incidents in cyber space, which means that traditional issues related to electronic information security (confidentiality, integrity, accessibility) have been neglected, and from 2015, not enough ... attention has been paid to development, legislation, improvement of organisational structure, etc. in this field.
Full description
National Audit Office of the Republic of Lithuania , issued in 2015
Risk cases: 6