Management of Information Resources of the Ministry of Agriculture
The Ministry of Agriculture of the Republic of Lithuania has managed 32 information systems and registers. Of these, 24 ones are managed, developed and upgraded by a state enterprise subordinate ... to the Ministry of Agriculture, the Agricultural Information and Rural Business Centre. The annual amount allocated by the Ministry for the maintenance of the Centre totals LTL 17.5 million on average ... . The objective of the audit was to assess the general and development controls of the information resources of the Ministry of Agriculture. The audit was conducted at the Ministry of Agriculture and the state ... ... Without appropiate IT management  it is hard to achieve reliable, consistent and secure systems for agriculture ... Since 1996 the Ministry has been using information systems of varying complexity for collecting and processing data, including personal data. The Ministry of Agriculture of the Republic of Lithuania ... has managed 32 information systems and registers. SAI of Lithuania revealed that systems were not well mantained what affected use of funds devoted to the systemsand also their legality and security.
Full description
National Audit Office of the Republic of Lithuania , issued in 2013
Risk cases: 2
Lessons learned from government ICT-projects
This audit has been performed on request of the Dutch parliament. Some newspapers mentioned government losses of four to five billion euro's on a yearly bases. These news items caused the parliament ... to request this audit. The audit has been performed in only 5 months time and consisted of the re-use of earlier performed audits. We have 'recycled' earlier findings about ICT-projects. ... 'Expensive' does not always mean 'High Quality', so... do not feed the spiral ... Excellent analysis of systemic errors commited when designing Government IT projects. The report aims at the essence of problems which are encountered far from information technologies - in: politics ... , business, psychology... Do not be mislead by date of report, it is evergreen for all who really want to know why IT projects fail.
Full description
Netherlands Court of Audits , issued in 2007
Risk cases: 3
Managing the risk of legacy ICT to public service delivery
The cross-government report describes the case studies from four public services (state pension, Value Added Tax collection, prescription payment and consumer credit licensing services) selected ... to illustrate the range of approaches that small and large government bodies are taking to address the issues arising from legacy ICT (defined as "systems and applications that have been operationally embedded ... within a business function but superseded by newer and more effective technologies or changed business needs"). ... Possible approaches to the problem of 'legacy ICT' ... UK’s government experience in managing the risks connected to legacy ICT provides valuable insight for others facing the same problem and are considering transforming their services.
Full description
National Audit Office , issued in 2013
Risk cases: 3
The National Offender Management Information System (NOMIS)
This report examines the reasons for the delays and cost increases to the original integrated information system and, since the moratorium imposed by the Minister of State in order to seek options ... for project’s cost reduction, the aims of the revised National Offender Management Service (NOMS) and the progress made, the impact of the delays and rescoping on the costs and benefits achieved, and NOMS ... ’ fitness to deliver. The aim of one integrated information system (C-NOMIS i.e. National Offender Management Information System) was to improve information sharing about offenders; address the lack ... Rescoping necessary, but not fully successful ... An initiative to build a single offender management IT system for the prison and probation services has not delivered value for money. The NAO investigation found the project had been hampered ... by poor management leading to a three-year delay, a doubling in project costs and reductions in scope and benefits.
Full description
National Audit Office , issued in 2009
Risk cases: 4
General and Creation Control of the Information Systems of the Ministry of Foreign Affairs
The objective of the audit was to assess general and creation control of the information systems of the Ministry of Foreign Affairs. Since the beginning of 2009, the Ministry of Foreign Affairs has ... achieved considerable progress in the management of the information systems. The auditors reviewed and assessed all key elements of the process. ... Overview of problems - area by area ... SAI Lithuania looked into all critical elements of a Ministry's information system, starting from IT architecture, through information security to automation of data processing.
Full description
National Audit Office of the Republic of Lithuania , issued in 2013
Risk cases: 4