11
results found in
10 ms
Page 1
of 2
Coordination of Infrastructure Works by Metropolitan Municipalities
Rapid population growth at metropoles as well as dense and planless structuring, especially in İstanbul and Ankara, have lead to an increase in demand for utilities services and consequently ... , in the resources used for the construction and maintenance of utilities. Moreover, in cities with dense population, damages to roads and sidewalks during the construction and maintenance of utilities cause problems ... in daily life, create financial burden and necessitate effective solutions. The purpose of this audit is to ensure that metropolitan municipalities eradicate defects in implementation, and Ministry ... ... ... Start geographic information system with cooperation rules and digital maps ... problems that reduce use and rise costs of this fundamental task. ... Organization of geographic and infrastructure information systems is an especially difficult task when bacause vast and intense coordination is necessary. The Turkisch Court of Accounts lists
Full description
Rapid population growth at metropoles as well as dense and planless structuring, especially in İstanbul and Ankara, have lead to an increase in demand for utilities services and consequently ... , in the resources used for the construction and maintenance of utilities. Moreover, in cities with dense population, damages to roads and sidewalks during the construction and maintenance of utilities cause problems ... in daily life, create financial burden and necessitate effective solutions. The purpose of this audit is to ensure that metropolitan municipalities eradicate defects in implementation, and Ministry ... ... ... Start geographic information system with cooperation rules and digital maps ... problems that reduce use and rise costs of this fundamental task. ... Organization of geographic and infrastructure information systems is an especially difficult task when bacause vast and intense coordination is necessary. The Turkisch Court of Accounts lists
Full description
Turkish Court of Accounts
, issued in 2008
Risk cases: 2
Prevention Activities Against Traffic Accidents
Performance Audit Studies covering certain IT Issues related to Prevention Activities Against Traffic Accidents. It aims to contribute to the continuous improvement of prevention activities against ... traffic accidents, which are dramatically leading to loss of life and property. Examination and evaluation of the Traffic Information Systems (TIS) under the traffic control headline. TIS' main purpose ... is to conduct the traffic control activities efficiently with the help of systematic data. Objective of this audit was to contribute to the continuous improvement of prevention activities against traffic ... ... ... You need a way more than IT, to make an IT system successful ... SAI of Turkey examined the Traffic Information Systems and found out that not only IT infrastructure determined the audited IT project's outcomes. There were also non-IT issues that decided: low ... quality of driving education, poor technical infrastruture, as well as lack of monitoring and coordination at prioritization stage.
Full description
Performance Audit Studies covering certain IT Issues related to Prevention Activities Against Traffic Accidents. It aims to contribute to the continuous improvement of prevention activities against ... traffic accidents, which are dramatically leading to loss of life and property. Examination and evaluation of the Traffic Information Systems (TIS) under the traffic control headline. TIS' main purpose ... is to conduct the traffic control activities efficiently with the help of systematic data. Objective of this audit was to contribute to the continuous improvement of prevention activities against traffic ... ... ... You need a way more than IT, to make an IT system successful ... SAI of Turkey examined the Traffic Information Systems and found out that not only IT infrastructure determined the audited IT project's outcomes. There were also non-IT issues that decided: low ... quality of driving education, poor technical infrastruture, as well as lack of monitoring and coordination at prioritization stage.
Full description
Turkish Court of Accounts
, issued in 2008
Risk cases: 4
Maintenance efficiency in the rail network
, fixed assets and operational stability of the railway system. The most important objective for the maintenance is to reduce the scope of operational interruptions, and to facilitate better punctuality ... to evaluate whether the maintenance tasks that fall under the Norwegian National Rail Administration are carried out efficiently, and in such a way that safeguards practical and accessible transportation ... The primary objective of railway politics is to contribute to ensure that users of the transport service have good railway options. The Norwegian National Rail Administration is organised under ... ... Rail network maintenance - negative balance of costs and results ... SAI Norway evaluated efficiency of the railway maintenance and found that its costs increased nearly 110 per cent in years 2006–2014. Negative development in uptime and regularity dominated the first ... part of the examined period, from 2006 to 2011. It turned positive from 2011, but in 2014 results were still worse than in 2006. The results have lagged behind the Ministry's target figures for most ... of the period.
Full description
, fixed assets and operational stability of the railway system. The most important objective for the maintenance is to reduce the scope of operational interruptions, and to facilitate better punctuality ... to evaluate whether the maintenance tasks that fall under the Norwegian National Rail Administration are carried out efficiently, and in such a way that safeguards practical and accessible transportation ... The primary objective of railway politics is to contribute to ensure that users of the transport service have good railway options. The Norwegian National Rail Administration is organised under ... ... Rail network maintenance - negative balance of costs and results ... SAI Norway evaluated efficiency of the railway maintenance and found that its costs increased nearly 110 per cent in years 2006–2014. Negative development in uptime and regularity dominated the first ... part of the examined period, from 2006 to 2011. It turned positive from 2011, but in 2014 results were still worse than in 2006. The results have lagged behind the Ministry's target figures for most ... of the period.
Full description
Office of the Auditor General of Norway
, issued in 2016
Risk cases: 2
Management and implementation of 1BestariNet
Solution. 1BestariNet serves as a major catalyst for internet penetration in Malaysia as well as the projected increase in national income. AUDIT OBJECTIVE: The audit was carried out to evaluate whether ... the management and implementation of 1BestariNet was carried out economically, efficiency and effectively to achieve the inttended objectives. AUDIT SCOPE: The audit scope includes planning, implementation ... and monitoring of 1BestariNet Project. The audit was carried out at 1BestariNet’s Project Management Office, Ministry of Education Malaysia (Education Technology Division, Procurement and Asset Management Division ... ... To answer big risks in IT systems development you need all levels of organisation ... Audit of 1BestariNet is presented by the Malaysian National Audit Department together with other IT projects reviewed. A result is this concise and instructive list of lessons learnt and failures ... to be avoided. To maximize performance and minimize vendor lock-in you need a lot of concerted effort by top and line management, as well as users ready to work with new tools.
Full description
Solution. 1BestariNet serves as a major catalyst for internet penetration in Malaysia as well as the projected increase in national income. AUDIT OBJECTIVE: The audit was carried out to evaluate whether ... the management and implementation of 1BestariNet was carried out economically, efficiency and effectively to achieve the inttended objectives. AUDIT SCOPE: The audit scope includes planning, implementation ... and monitoring of 1BestariNet Project. The audit was carried out at 1BestariNet’s Project Management Office, Ministry of Education Malaysia (Education Technology Division, Procurement and Asset Management Division ... ... To answer big risks in IT systems development you need all levels of organisation ... Audit of 1BestariNet is presented by the Malaysian National Audit Department together with other IT projects reviewed. A result is this concise and instructive list of lessons learnt and failures ... to be avoided. To maximize performance and minimize vendor lock-in you need a lot of concerted effort by top and line management, as well as users ready to work with new tools.
Full description
National Audit Department of Malaysia
, issued in 2013
Risk cases: 4
Peering Point Betriebs GmbH
In 2004 the Peering Point Betriebs GmbH was established to provide an effective and secure IT network for the operation of the e-card (a smart card which replaced health insurance vouchers ... in the course of the introduction of the electronic administration system) and other services in health care. Since its foundation the company has suffered losses. Net losses were covered by the two owners ... – the Main Association of Austrian Social Insurance Institutions and the Austrian Medical Chamber – to 50 % each, and since 2011 in a proportion of 60 to 40. The Main Association failed to give an objective ... ... Safe but expensive ... Network safety of a healthcare e-card system has been provided at a high cost. As the Austrian Court of Audit discovered - there was no concept to reduce the expenditure.
Full description
In 2004 the Peering Point Betriebs GmbH was established to provide an effective and secure IT network for the operation of the e-card (a smart card which replaced health insurance vouchers ... in the course of the introduction of the electronic administration system) and other services in health care. Since its foundation the company has suffered losses. Net losses were covered by the two owners ... – the Main Association of Austrian Social Insurance Institutions and the Austrian Medical Chamber – to 50 % each, and since 2011 in a proportion of 60 to 40. The Main Association failed to give an objective ... ... Safe but expensive ... Network safety of a healthcare e-card system has been provided at a high cost. As the Austrian Court of Audit discovered - there was no concept to reduce the expenditure.
Full description
Austrian Court of Audit
, issued in 2012
Risk cases: 1
State aid for IT projects in social and health care
and Health. All in all approximately 250 million euros was tied to development projects carried out as national measures in 2000-2010, not including the self-funded portion of aid or loans granted ... In 2000-2009 about 180 million euros in national and European Union funds went to finance information technology projects in social and health care, not including the costs of developing national ... information system services (KanTa project) or the National Project for Social Services IT (Tikesos project). Financing has been provided by the Ministry of Social Affairs and H ealth, the Finnish Funding ... Difficult coordination of IT projects ... Finish Audit Office analyzed results of poor cooperation between authorities on national and local level in social and health care projects: difficult integration of information systems and poor ... coordination of the financing information technology projects, including double financing.
Full description
and Health. All in all approximately 250 million euros was tied to development projects carried out as national measures in 2000-2010, not including the self-funded portion of aid or loans granted ... In 2000-2009 about 180 million euros in national and European Union funds went to finance information technology projects in social and health care, not including the costs of developing national ... information system services (KanTa project) or the National Project for Social Services IT (Tikesos project). Financing has been provided by the Ministry of Social Affairs and H ealth, the Finnish Funding ... Difficult coordination of IT projects ... Finish Audit Office analyzed results of poor cooperation between authorities on national and local level in social and health care projects: difficult integration of information systems and poor ... coordination of the financing information technology projects, including double financing.
Full description
National Audit Office of Finland
, issued in 2011
Risk cases: 3
State funds spent on development, operation and using of data centres services
The aim of the audit was to scrutinise the management of funds spent on building and operating the national data centre (hereinafter “STC1 data centre”), including the expenditure of selected ... organisational units of the state on buying hosting, server-housing and other related services. The audited period was between 2010 and 2014; where relevant, the preceding period was also scrutinised. Audited ... entities: Ministry of the Interior (“MoI”); Ministry of Finance (“MoF”); STÁTNÍ TISKÁRNA CENIN, state firm (state banknote printing firm, hereinafter “STC” or “the state firm”). The audit was conducted ... ... Risks steming from uncoordinated strategy ... SAI of Czech Republic analysed consequences of failures in strategic IT management at the state level. Lack of coordination and implementation rules reduced practical role of the ministry whose task ... was to guard high quality standards for all crucial IT systems in the state administration. Next consecquences were (among others) risk of uneconomical results of large IT investment and risk of inefficient ... supply of services, as well as opposite results of workforce reduction.
Full description
The aim of the audit was to scrutinise the management of funds spent on building and operating the national data centre (hereinafter “STC1 data centre”), including the expenditure of selected ... organisational units of the state on buying hosting, server-housing and other related services. The audited period was between 2010 and 2014; where relevant, the preceding period was also scrutinised. Audited ... entities: Ministry of the Interior (“MoI”); Ministry of Finance (“MoF”); STÁTNÍ TISKÁRNA CENIN, state firm (state banknote printing firm, hereinafter “STC” or “the state firm”). The audit was conducted ... ... Risks steming from uncoordinated strategy ... SAI of Czech Republic analysed consequences of failures in strategic IT management at the state level. Lack of coordination and implementation rules reduced practical role of the ministry whose task ... was to guard high quality standards for all crucial IT systems in the state administration. Next consecquences were (among others) risk of uneconomical results of large IT investment and risk of inefficient ... supply of services, as well as opposite results of workforce reduction.
Full description
Supreme Audit Office of Czech Republic
, issued in 2015
Risk cases: 7
Report on the problems connected with the development and implementation of the digitally based Shared Medication Record
a sufficient framework for carrying through the SMR programme? 2) Has the Ministry of Health and the NHA directed the SMR programme towards delivering within the agreed costs, time and quality parameters ... The purpose of the examination was to assess whether the department of the Danish Ministry of Health, the Danish National eHealth Authority (NHA) and the five regions that are responsible ... for the hospitals have made an adequate effort to develop and implement the Shared Medication Record (SMR). With the SMR, data on the citizens’ medication can be shared across hospitals, general practitioners, etc ... ... Involvement of key participants necessary from the very beginning ... Digitally based Shared Medication Record is basis of the complex healthcare system. Rigsrevisionen analysed unsolved issues related to unclear business case, insufficient analysis of work flows ... and processes leading to implementation problems, governance not involving key players, and IT security organisation.
Full description
a sufficient framework for carrying through the SMR programme? 2) Has the Ministry of Health and the NHA directed the SMR programme towards delivering within the agreed costs, time and quality parameters ... The purpose of the examination was to assess whether the department of the Danish Ministry of Health, the Danish National eHealth Authority (NHA) and the five regions that are responsible ... for the hospitals have made an adequate effort to develop and implement the Shared Medication Record (SMR). With the SMR, data on the citizens’ medication can be shared across hospitals, general practitioners, etc ... ... Involvement of key participants necessary from the very beginning ... Digitally based Shared Medication Record is basis of the complex healthcare system. Rigsrevisionen analysed unsolved issues related to unclear business case, insufficient analysis of work flows ... and processes leading to implementation problems, governance not involving key players, and IT security organisation.
Full description
National Audit Office of Denmark
, issued in 2014
Risk cases: 2
Open Government Data - Are all exceptions to the principle of cost-free access and reuse legitimate?
comparisons carried out extremely competently in record time by France's economic units in 36 countries;<br/> - hearings of evidence from competent official authorities, comprising official bodies in France ... The United Kingdom, a country seen, like the United States, as a pioneer in open public data, has estimated at £6.8bn (€7,9bn) the revenue in 2010 and 2011 generated for British society by open ... public data, of which £5bn (€5.8bn) is profit. As an example, a start-up has highlighted the existence of areas in which massive savings can be made by analysing prescriptions of patented drugs ... ... Open data strategy should decide the costs problem ... French Cour des comptes presents analysis on implementation of the open data practice across the administration. Massive savings are expected, when public access to large amounts of highquality data ... is made easy. France is among the pioneers and countries making the most rapid progress in this domain. Charges for the reuse of the public information has been identified as the main problem.
Full description
comparisons carried out extremely competently in record time by France's economic units in 36 countries;<br/> - hearings of evidence from competent official authorities, comprising official bodies in France ... The United Kingdom, a country seen, like the United States, as a pioneer in open public data, has estimated at £6.8bn (€7,9bn) the revenue in 2010 and 2011 generated for British society by open ... public data, of which £5bn (€5.8bn) is profit. As an example, a start-up has highlighted the existence of areas in which massive savings can be made by analysing prescriptions of patented drugs ... ... Open data strategy should decide the costs problem ... French Cour des comptes presents analysis on implementation of the open data practice across the administration. Massive savings are expected, when public access to large amounts of highquality data ... is made easy. France is among the pioneers and countries making the most rapid progress in this domain. Charges for the reuse of the public information has been identified as the main problem.
Full description
Cour des comptes
, issued in 2013
Risk cases: 1
Managing the risk of legacy ICT to public service delivery
The cross-government report describes the case studies from four public services (state pension, Value Added Tax collection, prescription payment and consumer credit licensing services) selected ... to illustrate the range of approaches that small and large government bodies are taking to address the issues arising from legacy ICT (defined as "systems and applications that have been operationally embedded ... within a business function but superseded by newer and more effective technologies or changed business needs"). ... Possible approaches to the problem of 'legacy ICT' ... UK’s government experience in managing the risks connected to legacy ICT provides valuable insight for others facing the same problem and are considering transforming their services.
Full description
The cross-government report describes the case studies from four public services (state pension, Value Added Tax collection, prescription payment and consumer credit licensing services) selected ... to illustrate the range of approaches that small and large government bodies are taking to address the issues arising from legacy ICT (defined as "systems and applications that have been operationally embedded ... within a business function but superseded by newer and more effective technologies or changed business needs"). ... Possible approaches to the problem of 'legacy ICT' ... UK’s government experience in managing the risks connected to legacy ICT provides valuable insight for others facing the same problem and are considering transforming their services.
Full description
National Audit Office
, issued in 2013
Risk cases: 3