Lessons learned from government ICT-projects
to request this audit. The audit has been performed in only 5 months time and consisted of the re-use of earlier performed audits. We have 'recycled' earlier findings about ICT-projects. ... This audit has been performed on request of the Dutch parliament. Some newspapers mentioned government losses of four to five billion euro's on a yearly bases. These news items caused the parliament ... 'Expensive' does not always mean 'High Quality', so... do not feed the spiral ... Excellent analysis of systemic errors commited when designing Government IT projects. The report aims at the essence of problems which are encountered far from information technologies - in: politics ... , business, psychology... Do not be mislead by date of report, it is evergreen for all who really want to know why IT projects fail.
Full description
Netherlands Court of Audits , issued in 2007
Risk cases: 3
State aid for IT projects in social and health care
In 2000-2009 about 180 million euros in national and European Union funds went to finance information technology projects in social and health care, not including the costs of developing national ... information system services (KanTa project) or the National Project for Social Services IT (Tikesos project). Financing has been provided by the Ministry of Social Affairs and H ealth, the Finnish Funding ... and Health. All in all approximately 250 million euros was tied to development projects carried out as national measures in 2000-2010, not including the self-funded portion of aid or loans granted ... Difficult coordination of IT projects ... Finish Audit Office analyzed results of poor cooperation between authorities on national and local level in social and health care projects: difficult integration of information systems and poor ... coordination of the financing information technology projects, including double financing.
Full description
National Audit Office of Finland , issued in 2011
Risk cases: 3
Is the project 'E-health in Latvia' a step towards the right direction?
of funds invested in the project for achievement of set objectives and gaining the planned benefits. Audit covered such main questions: 1) Will the e-health policy be able to solve problems and achieve ... in the newly built e-health information system? 4) Has an efficient supervision and control of the project 'E-health in Latvia' been set up? ... Objective of the audit was to verify efficiency and productivity of the actions by the institutions in charge for implementation of the e-health, as well as to audit economy and productivity of use ... E-health is a step forward in right direction, but not all objectives will be reached! ... Project “E-health in Latvia” supports healthy lifestyle, it will provide valuable and accessible information and will promote more efficient provision of services to patients. It is undoubtedly ... a step towards the right direction then. However, as found the Latvian SAI, the e-health policy will not be implemented within the initially planned scope and deadline and within set data security levels ... , thus the objective of this policy – to promote more effective provision of healthcare services will be attained only partially.
Full description
State Audit Office of the Republic of Latvia , issued in 2015
Risk cases: 3
Use of European Union funds in promoting information society
business as well as citizens. The National Audit Office sees a situation as transparent if all applicants can obtain the reassurance that preferring certain projects to others was justified. The National ... Development Plan, and not paid enough attention on improving the competitiveness of companies and supporting the IT development projects that are aimed at the third sector. Also, the selection of IT projects ... has not been transparent and the state’s supervision of the implementation of the projects has been regarded as a formality. ... Riigikontroll auditeeris Euroopa Liidu struktuurifondidest ehk tõukefondidest eraldatud toetuste (edaspidi ELi toetusraha) kasutamist riigi infotehnoloogia (IT) valdkonnas. Uuriti, kas raha jagamine ... infoühiskonna arendamise eesmärgil on olnud tasakaalustatud ja läbipaistev ning kas toetuste jagamise üle tehakse piisavat järelevalvet. Riigikontrolli hinnangul on riik infoühiskonna arengukava rakendamiseks ... toetuste jagamisel keskendunud liiga riigile suunatud IT-arenduste rahastamisele ning jätnud tagaplaanile ettevõtete konkurentsivõime parandamisele ja kolmandale sektorile suunatud IT arendusprojektide ... Balance needed for success of Information Society Development Plan ... , true suppervision and measurement of progress are listed by the Estonian SAI as next key elements necessary to keep balanced development of strategy for Information Society. ... 50% of aid has been granted primarily for the development of information systems of state agencies, i.e. as much as the other two target groups - business and citizens - put together. Information
Full description
National Audit Office of Estonia , issued in 2012
Risk cases: 2
Effectiveness of the execution of the eHealth project
The Court of Audit of the Republic of Slovenia has audited how effectively the Ministry of Health had managed the project eHealth - the national plan for developing information system support ... to the national public health system in the period between 1st of January 2004 and 26th of September 2013. The audit has focused on the effectiveness of the Ministry in achieving the project’s goals, time ... management of the health and health related data. The Ministry had planned to finish the project by December 2015 with estimated implementation and operational costs of 133 million euro by December 2023 ... ... Clear concept, good planning and financial control are indispensable conditions for a successful IT project ... The Court of Audit of the Republic of Slovenia analysed a Government eHealth project. Its goal was to implement a modern information system, which would support the health services and health related ... data. The Court has pointed at a long list of project management fundamentals to be corrected.
Full description
Court of Audit of the Republic of Slovenia , issued in 2013
Risk cases: 5
The implementation of national IT projects in social and health care
IT management expenditure in public administration totalled about 2.1 billion euros in 2009. IT management expenditure by local authorities and federations of municipalities in the field of health ... care totalled about 270 million euros ino 2009. Health care's share of IT management expenditure in public administration thus amounted to about 13 per cent in 2009. ... ... IT-centred manner of project implementation can harm IT investments' results ... SAI Finland perfomed a vast review of IT projects in health and social protection. Many interesting findings cover structural problems, as 'Many separate systems with no future' and characteristics ... of poor governance, as 'No cost monitoring - unclear objectives - arguable usefulness'.
Full description
National Audit Office of Finland , issued in 2011
Risk cases: 3
Effectiveness of the Tax Administration of the Republic of Slovenia in the execution of modernisation projects of the Slovenian duty information system and decreasing the number of duty sub-accounts
some improvements and had also enabled implementation of the second project - decreasing the number of government duty sub-accounts. Despite these successes, the combined projects of modernisation ... project aiming at lessening taxpayers’ administrative burdens by decreasing the number of duty sub-accounts. The modernisation of the Tax Authority’s duties’ collection information system had brought about ... The Tax Administration of the Republic of Slovenia (hereinafter: the Tax Administration) is responsible for collecting taxes, fees and other compulsory levies (hereinafter: duties ... ... Shaky coordination of investments in important systems ... of the project, involving additional spendings, delays and errors in data processing. ... Slovenian SAI traced a series of problems in management of crucial IT investments in tax administration. Apart from promising goals, unclear business case gave a start to many problems at next stages
Full description
Court of Audit of the Republic of Slovenia , issued in 2014
Risk cases: 7
Evaluation of the effectiveness of implementation and compliance with regulatory enactments and the legal framework of the project “E-government Portfolio”
The objective of the audit is to evaluate the effectiveness of implementation and compliance with regulatory enactments and the legal framework of the project “Egovernment Portfolio” of the national ... programme of the European Regional Development Fund (hereinafter: ERDF) of the European Union (hereinafter: EU), “Development and improvement of the infrastructural foundation for electronic governance”. ... ... Funds to absorb but no efficient project methodology? Be prepared for troubles ... Wide list of problems that can be met when more care is received by 'absorb funds' objective than by clear vision what and how can be improved. SAI Latvia's analysis shows how dangerous it can ... be for both effectiveness and financial management.
Full description
State Audit Office of Latvia , issued in 2010
Risk cases: 3
Software Developement Effective Practices and Federal Chalenges in Applying Agile Methods
To identify effective practices in applying Agile for software developement solutions and federal challenges in implementing Agile techniques. ... Agile project approach in government practice ... Useful products delivered in a short time are basis for often applauded features of agile project approach. Applied by many private companies, it tends as well to be more and more popular among state ... administrations. American GAO reviewed set of agile projects and revealed - apart from advantages - a set of commonly occurring problems: poor team work, lack of time and deficit of customers’ trust.
Full description
General Accountability Office , issued in 2012
Risk cases: 4
Public access point to the Polish e-Administration
Coordinated audit series (46 auditees) focused on a web solution applied to give an easy access to Government e-services (the project planned to be completed in 2013) The audit was performed in 2008 ... known by the audit was 'Project Frameworks vs Public Procurement'. ... and public report issued in March 2009. Primary goal of th presentation was intended to illustrate the use of 'e-Government Algorithm' elaborated by EUROSAI IT Working Group in 2005. One of issues mede better ... ... Buyer, provider and methodologies need a balance ... Presentation based on a vast audit by Polish SAI which subject was of big network project aiming to provide one access point to Government and Selfgovernments services. The presentation illustrates ... old EUROSAI IT Wg 'Algorithm approach' and focuses on procurement systemic problems.
Full description
Supreme Audit Office of Poland , issued in 2008
Risk cases: 3