Reports Search Reports Spatial Search Risk-cases Search Risk-cases Graph Traversal
3 results found in 3 ms Page 1 of 1
Effectiveness of the execution of the eHealth project
The Court of Audit of the Republic of Slovenia has audited how effectively the Ministry of Health had managed the project eHealth - the national plan for developing information system support ... to the national public health system in the period between 1st of January 2004 and 26th of September 2013. The audit has focused on the effectiveness of the Ministry in achieving the project’s goals, time ... management, management of the human resources and financial oversight. The goal of the Ministry was to implement a modern information system, which would support secure eHealth operations and effective ... ... Clear concept, good planning and financial control are indispensable conditions for a successful IT project ... The Court of Audit of the Republic of Slovenia analysed a Government eHealth project. Its goal was to implement a modern information system, which would support the health services and health related ... data. The Court has pointed at a long list of project management fundamentals to be corrected.
Full description
Court of Audit of the Republic of Slovenia , issued in 2013
Risk cases: 5
State funds spent on development, operation and using of data centres services
The aim of the audit was to scrutinise the management of funds spent on building and operating the national data centre (hereinafter “STC1 data centre”), including the expenditure of selected ... organisational units of the state on buying hosting, server-housing and other related services. The audited period was between 2010 and 2014; where relevant, the preceding period was also scrutinised. Audited ... entities: Ministry of the Interior (“MoI”); Ministry of Finance (“MoF”); STÁTNÍ TISKÁRNA CENIN, state firm (state banknote printing firm, hereinafter “STC” or “the state firm”). The audit was conducted ... ... Risks steming from uncoordinated strategy ... SAI of Czech Republic analysed consequences of failures in strategic IT management at the state level. Lack of coordination and implementation rules reduced practical role of the ministry whose task ... was to guard high quality standards for all crucial IT systems in the state administration. Next consecquences were (among others) risk of uneconomical results of large IT investment and risk of inefficient ... supply of services, as well as opposite results of workforce reduction.
Full description
Supreme Audit Office of Czech Republic , issued in 2015
Risk cases: 7
Audit on the broadband internet infrastructure access
Poland has been granted over PLN 4 billion from the European Regional Development Fund to build the broadband internet access infrastructure. As part of three operational programmes 90 percent ... of assumed financing was contracted, namely PLN 3.9 billion. By the end of 2015, Poland should complete the investment and account for the expenses. According to NIK there is a risk that the infrastructure ... construction will not be completed by the deadline and the EU funds may not be used to the full. ... ... Simpler regulations and better supervision needed ... Polish SAI audited a project, which aim had been to develop broadband internet network across the country. They revealed that legal obstacles, idleness and lack of supervision were the main causes ... of delays. Some of the projects are in danger of not being completed on time and some of the EU funds may not be fully used.
Full description
Supreme Audit Office of Poland , issued in 2015
Risk cases: 2
3 results found. Page 1 of 1