Effectiveness of the execution of the eHealth project
The Court of Audit of the Republic of Slovenia has audited how effectively the Ministry of Health had managed the project eHealth - the national plan for developing information system support ... to the national public health system in the period between 1st of January 2004 and 26th of September 2013. The audit has focused on the effectiveness of the Ministry in achieving the project’s goals, time ... management, management of the human resources and financial oversight. The goal of the Ministry was to implement a modern information system, which would support secure eHealth operations and effective ... ... Clear concept, good planning and financial control are indispensable conditions for a successful IT project ... data. The Court has pointed at a long list of project management fundamentals to be corrected. ... The Court of Audit of the Republic of Slovenia analysed a Government eHealth project. Its goal was to implement a modern information system, which would support the health services and health related
Full description
Court of Audit of the Republic of Slovenia , issued in 2013
Risk cases: 5
Prevention Activities Against Traffic Accidents
Performance Audit Studies covering certain IT Issues related to Prevention Activities Against Traffic Accidents. It aims to contribute to the continuous improvement of prevention activities against ... traffic accidents, which are dramatically leading to loss of life and property. Examination and evaluation of the Traffic Information Systems (TIS) under the traffic control headline. TIS' main purpose ... is to conduct the traffic control activities efficiently with the help of systematic data. Objective of this audit was to contribute to the continuous improvement of prevention activities against traffic ... ... ... You need a way more than IT, to make an IT system successful ... SAI of Turkey examined the Traffic Information Systems and found out that not only IT infrastructure determined the audited IT project's outcomes. There were also non-IT issues that decided: low ... quality of driving education, poor technical infrastruture, as well as lack of monitoring and coordination at prioritization stage.
Full description
Turkish Court of Accounts , issued in 2008
Risk cases: 4
State funds spent on development, operation and using of data centres services
The aim of the audit was to scrutinise the management of funds spent on building and operating the national data centre (hereinafter “STC1 data centre”), including the expenditure of selected ... organisational units of the state on buying hosting, server-housing and other related services. The audited period was between 2010 and 2014; where relevant, the preceding period was also scrutinised. Audited ... entities: Ministry of the Interior (“MoI”); Ministry of Finance (“MoF”); STÁTNÍ TISKÁRNA CENIN, state firm (state banknote printing firm, hereinafter “STC” or “the state firm”). The audit was conducted ... ... Risks steming from uncoordinated strategy ... SAI of Czech Republic analysed consequences of failures in strategic IT management at the state level. Lack of coordination and implementation rules reduced practical role of the ministry whose task ... was to guard high quality standards for all crucial IT systems in the state administration. Next consecquences were (among others) risk of uneconomical results of large IT investment and risk of inefficient ... supply of services, as well as opposite results of workforce reduction.
Full description
Supreme Audit Office of Czech Republic , issued in 2015
Risk cases: 7