Management and protection of assets in the field of the information-communication technologies at the ME SR
and lawbreaking, violation of the conditions determined in the particular contracts, documents and agreements (if they were ever found or valid), obsolete conception of the ISPA development, not established ... internal and security directives, unidentified critical and strategic Information Systems (IS), absolutely unsatisfying principles, procedures, conditions and policy relating to the data backuping (and ... The Supreme Audit office of the Slovak Republic (SAO SR) has conducted the audit at the Ministry of Environment of the Slovak Republic (ME SR) for the audit period 2011 and 2012 to examine ... ... Started from contracting, ended in security ... The perceptive and filled with findings audit - conducted by the Slovak SAI - discovered the list of issues which started in careless contracting procedures, failure to update the development concept ... and ended in exposing the organization to high security risks.
Full description
Supreme Audit Office of the Slovak Republic , issued in 2012
Risk cases: 4
IT Police Systems
and effectiveness of their work. Audit explained the reason of failure in the case of E-police station project and success in the case of CSS. Although some irregularities occurred in both cases, careful planning ... Implementation by the Polish Police of two IT projects (E-police station and Command Support System - CSS) was audited. Both systems were to relieve the Police officers and increase the quality ... and organization of the project turned out to make the difference. Accordance with the public procurement law was not part of the audit as a separate investigation in that matter was carried by respective Polish ... ... A textbook example of how not to implement the IT projects ... Polish NIK compared the implementation of two flagship IT projects of the Police HQ: successful 'Command Support System' and problematic 'E-police station'. List of interesting problems appeared...
Full description
Supreme Audit Office of Poland , issued in 2013
Risk cases: 5
Management of Police Information Resources
Police tasks of the necessary data are processed departmental registers, information systems, automated data processing systems and networks where information is stored, processed and transferred ... to the classified information. The police department has all of these information resources, so the audit focused on the activities and actions of the Department to ensure planning and organizing of the recourses ... , monitoring, evaluation and coordination and other aspects of registers and IS strategic management. The audited period was 2012-2014. For the analysis, there were used previous data and data of 2015 ... ... Fundamentals of IT organisation ... and well understood architecture of information. Well functioning IT management structures, which on the other hand may sound trivial, were proved here as the key to success. ... Review by SAI Lithuania makes readers aware that nowadays it is difficult to develop a larger IT system without whole conceptual infrastracture: planning composed into strategy of the organisation
Full description
National Audit Office of the Republic of Lithuania , issued in 2015
Risk cases: 4
The Ministry of the Environment lacks a compact information system and still uses 125 separate information systems and databases
The objective of the audit was to scrutinise the management of funds earmarked for the purchase and administration of ICT within the MoE and selected organisations which come under the management ... of the MoE. The audit identified the following risks: (1) non-existence of the Integrated environmental information system (IEIS) as an independent information system; (2) purchase of ICT, within the budget ... chapter of the MoE, through a state co-funded organisation CENIA which comes under the management of the MoE; (3) utilisation of the information systems. The audited period was 2010 to 2013; where relevant ... ... Ministry of the Environment manages 125 information systems and databases ... The Ministry of the Environment (MoE) has for more than 20 years a legal obligation to administer and manage an Integrated Environmental Information System (IEIS). In spite of this fact, the existing ... systems (more than 125 information systems and databases) are designed, implemented and managed as individual information systems without a direct integration into a joint point of reference.
Full description
Supreme Audit Office of Czech Republic , issued in 2015
Risk cases: 7
Audit of the Government, Government-guaranteed and Municipal Debt Management Information Systems in the Ministry of Finance of the Republic of Bulgaria
The main audit question studied during the audit was: Are the government, government-guaranteed (SDMS) and municipal debt management information systems (CMDR) at the Ministry of Finance effective ... ? The audit covered the period from 01.01.2013 to 31.12.2013 and investigated four major areas: IT system strategy and general management; IT security and controls against disasters; Operational controls ... and Documentation; Application Controls. ... ... Even effective and modern IT systems require improvements and updates to ensure their security and accountability ... For the management of the government, government-guaranteed and municipal debt the Ministry of Finance has established an advanced integrated information infrastructure. According to Bulgarian SAI ... the established system is effective and provides updated, complete and correct information. Nevertheless the audit report points out areas of security, application controls as well as documentation as the subjects ... that need further improvement and optimization.
Full description
Bulgarian National Audit Office , issued in 2014
Risk cases: 3