Audit of the key ICT project federal GEVER programme Federal Chancellery
During the first stage, two new GEVER (electronic records and process management) products were procured in an open WTO tender within the framework of the two-product strategy (federal GEVER WTO ... procurement project). CHF 1.6 million was spent on these. The departments and Federal Chancellery (departments/FCh) had to choose one of the two products within three months of the contract being awarded. ... ... Advanced process management system's cost-effectiveness and deadlines at risk ... Ever since 1990, sequential controls and file management have been part of the Federal Administration's IT landscape (GEVER business administration). Significant obstacles have to be overcome ... in order to ensure the successful creation and introduction of GEVER. Previous efforts did not have any widespread success and led to a diverse GEVER landscape. The federal GEVER project has now laid ... the foundations for simplification and centralisation.
Full description
During the first stage, two new GEVER (electronic records and process management) products were procured in an open WTO tender within the framework of the two-product strategy (federal GEVER WTO ... procurement project). CHF 1.6 million was spent on these. The departments and Federal Chancellery (departments/FCh) had to choose one of the two products within three months of the contract being awarded. ... ... Advanced process management system's cost-effectiveness and deadlines at risk ... Ever since 1990, sequential controls and file management have been part of the Federal Administration's IT landscape (GEVER business administration). Significant obstacles have to be overcome ... in order to ensure the successful creation and introduction of GEVER. Previous efforts did not have any widespread success and led to a diverse GEVER landscape. The federal GEVER project has now laid ... the foundations for simplification and centralisation.
Full description
Swiss Federal Audit Office
, issued in 2015
Risk cases: 2
Parallel Audit on Biometric Passports - Overall Results (anonymised)
A biometric passport (or ePassport) contains biometric information which serves to authenticate the identity of travellers. Biometric passport management is the process of establishing ... and implementing the regulation on standards for security features and biometrics in passports and travel documents issued by the member states. The aim is to develop and maintain efficient and secure biometric ... passport production procedures (see page 5). ... EUROSAI ITWG: Parallel Audit on Biometric Passports ... deficiencies and weaknesses related to the IS/IT system and the IT management. Medium risks have been identified in the area of laws and regulations, cost-benefit realisation and transparency, as well ... Swiss SAI summed up results of audits concluded in seven countries (Belgium, Latvia, Lithuania, Norway, Portugal, Switzerland). The evaluation of the reported results showed that the overall passport ... process is generally under control while a couple of high-risk findings were identified in the non-process-specific assessments. In the non-process-specific assessments, most of the countries found
Full description
A biometric passport (or ePassport) contains biometric information which serves to authenticate the identity of travellers. Biometric passport management is the process of establishing ... and implementing the regulation on standards for security features and biometrics in passports and travel documents issued by the member states. The aim is to develop and maintain efficient and secure biometric ... passport production procedures (see page 5). ... EUROSAI ITWG: Parallel Audit on Biometric Passports ... deficiencies and weaknesses related to the IS/IT system and the IT management. Medium risks have been identified in the area of laws and regulations, cost-benefit realisation and transparency, as well ... Swiss SAI summed up results of audits concluded in seven countries (Belgium, Latvia, Lithuania, Norway, Portugal, Switzerland). The evaluation of the reported results showed that the overall passport ... process is generally under control while a couple of high-risk findings were identified in the non-process-specific assessments. In the non-process-specific assessments, most of the countries found
Full description
Swiss Federal Audit Office
, issued in 2015
Risk cases: 4
ACQUISITION REFORM: DOD Should Streamline Its Decision-Making Process for Weapon Systems to Reduce Inefficiencies
Refinement of decision-making processes The US Department of Defense (DOD) has long sought to improve the efficiency of its weapon system acquisition process, including the time and effort needed to complete the milestone decision process. Good practices of some DOD programs and five commercial firms were used by GAO to look for new momentum in refining the process.
Full description
Refinement of decision-making processes The US Department of Defense (DOD) has long sought to improve the efficiency of its weapon system acquisition process, including the time and effort needed to complete the milestone decision process. Good practices of some DOD programs and five commercial firms were used by GAO to look for new momentum in refining the process.
Full description
US Government Accountability Office
, issued in 2015
Risk cases: $risks.size()
ACQUISITION REFORM: DOD Should Streamline Its Decision-Making Process for Weapon Systems to Reduce Inefficiencies
Refinement of decision-making processes The US Department of Defense (DOD) has long sought to improve the efficiency of its weapon system acquisition process, including the time and effort needed to complete the milestone decision process. Good practices of some DOD programs and five commercial firms were used by GAO to look for new momentum in refining the process.
Full description
Refinement of decision-making processes The US Department of Defense (DOD) has long sought to improve the efficiency of its weapon system acquisition process, including the time and effort needed to complete the milestone decision process. Good practices of some DOD programs and five commercial firms were used by GAO to look for new momentum in refining the process.
Full description
US Government Accountability Office
, issued in 2015
Risk cases: $risks.size()
ACQUISITION REFORM: DOD Should Streamline Its Decision-Making Process for Weapon Systems to Reduce Inefficiencies
Refinement of decision-making processes The US Department of Defense (DOD) has long sought to improve the efficiency of its weapon system acquisition process, including the time and effort needed to complete the milestone decision process. Good practices of some DOD programs and five commercial firms were used by GAO to look for new momentum in refining the process.
Full description
Refinement of decision-making processes The US Department of Defense (DOD) has long sought to improve the efficiency of its weapon system acquisition process, including the time and effort needed to complete the milestone decision process. Good practices of some DOD programs and five commercial firms were used by GAO to look for new momentum in refining the process.
Full description
US Government Accountability Office
, issued in 2015
Risk cases: $risks.size()
ACQUISITION REFORM: DOD Should Streamline Its Decision-Making Process for Weapon Systems to Reduce Inefficiencies
Refinement of decision-making processes The US Department of Defense (DOD) has long sought to improve the efficiency of its weapon system acquisition process, including the time and effort needed to complete the milestone decision process. Good practices of some DOD programs and five commercial firms were used by GAO to look for new momentum in refining the process.
Full description
Refinement of decision-making processes The US Department of Defense (DOD) has long sought to improve the efficiency of its weapon system acquisition process, including the time and effort needed to complete the milestone decision process. Good practices of some DOD programs and five commercial firms were used by GAO to look for new momentum in refining the process.
Full description
US Government Accountability Office
, issued in 2015
Risk cases: $risks.size()
ACQUISITION REFORM: DOD Should Streamline Its Decision-Making Process for Weapon Systems to Reduce Inefficiencies
Refinement of decision-making processes The US Department of Defense (DOD) has long sought to improve the efficiency of its weapon system acquisition process, including the time and effort needed to complete the milestone decision process. Good practices of some DOD programs and five commercial firms were used by GAO to look for new momentum in refining the process.
Full description
Refinement of decision-making processes The US Department of Defense (DOD) has long sought to improve the efficiency of its weapon system acquisition process, including the time and effort needed to complete the milestone decision process. Good practices of some DOD programs and five commercial firms were used by GAO to look for new momentum in refining the process.
Full description
US Government Accountability Office
, issued in 2015
Risk cases: $risks.size()
ACQUISITION REFORM: DOD Should Streamline Its Decision-Making Process for Weapon Systems to Reduce Inefficiencies
Refinement of decision-making processes The US Department of Defense (DOD) has long sought to improve the efficiency of its weapon system acquisition process, including the time and effort needed to complete the milestone decision process. Good practices of some DOD programs and five commercial firms were used by GAO to look for new momentum in refining the process.
Full description
Refinement of decision-making processes The US Department of Defense (DOD) has long sought to improve the efficiency of its weapon system acquisition process, including the time and effort needed to complete the milestone decision process. Good practices of some DOD programs and five commercial firms were used by GAO to look for new momentum in refining the process.
Full description
US Government Accountability Office
, issued in 2015
Risk cases: $risks.size()
ACQUISITION REFORM: DOD Should Streamline Its Decision-Making Process for Weapon Systems to Reduce Inefficiencies
Refinement of decision-making processes The US Department of Defense (DOD) has long sought to improve the efficiency of its weapon system acquisition process, including the time and effort needed to complete the milestone decision process. Good practices of some DOD programs and five commercial firms were used by GAO to look for new momentum in refining the process.
Full description
Refinement of decision-making processes The US Department of Defense (DOD) has long sought to improve the efficiency of its weapon system acquisition process, including the time and effort needed to complete the milestone decision process. Good practices of some DOD programs and five commercial firms were used by GAO to look for new momentum in refining the process.
Full description
US Government Accountability Office
, issued in 2015
Risk cases: $risks.size()
Central government staff costs
Results of staff reductions The British NAO found that departments had significantly reduced numbers of their civil servants and of course salary costs at the same time. But they reduced staff numbers mainly by minimising recruitment, and the age profile of the civil service has changed. NAO pays a lot attention to what effect this has had on the future pipeline of talent and skills. It reminds also that the departments need long-term operating models to work efficiently with the staff reduced.
Full description
Results of staff reductions The British NAO found that departments had significantly reduced numbers of their civil servants and of course salary costs at the same time. But they reduced staff numbers mainly by minimising recruitment, and the age profile of the civil service has changed. NAO pays a lot attention to what effect this has had on the future pipeline of talent and skills. It reminds also that the departments need long-term operating models to work efficiently with the staff reduced.
Full description
National Audit Office
, issued in 2015
Risk cases: 5