Audit of the key ICT project federal GEVER programme Federal Chancellery
During the first stage, two new GEVER (electronic records and process management) products were procured in an open WTO tender within the framework of the two-product strategy (federal GEVER WTO ... procurement project). CHF 1.6 million was spent on these. The departments and Federal Chancellery (departments/FCh) had to choose one of the two products within three months of the contract being awarded. ... ... Advanced process management system's cost-effectiveness and deadlines at risk ... Ever since 1990, sequential controls and file management have been part of the Federal Administration's IT landscape (GEVER business administration). Significant obstacles have to be overcome ... in order to ensure the successful creation and introduction of GEVER. Previous efforts did not have any widespread success and led to a diverse GEVER landscape. The federal GEVER project has now laid ... the foundations for simplification and centralisation.
Full description
Swiss Federal Audit Office , issued in 2015
Risk cases: 2
Audit of the key ICT project regarding a consumption tax platform Federal Customs Administration (FCA)
The Swiss Federal Audit Office (SFAO) audited the key ICT project concerning a consumption tax platform from May to June 2015. The programme was launched in January 2014 with a budget of CHF 13.5 ... million. The instructing parties were the management of the Federal Customs Administration (FCA), the Swiss Alcohol Board (SAB) and the Federal Office of Information Technology, Systems ... and Telecommunication (FOITT). ... ... First attempt to ITC consumption tax project ... SAI Switzerland analised problems steming from insufficient specification of a complex ICT system project concerning a consumption tax platform. The project's budget turned out to cover only 70 ... % of the expected functions. Suspension of the project and restarting preparations stage followed.
Full description
Swiss Federal Audit Office , issued in 2015
Risk cases: 1
Parallel Audit on Biometric Passports - Overall Results (anonymised)
A biometric passport (or ePassport) contains biometric information which serves to authenticate the identity of travellers. Biometric passport management is the process of establishing ... and implementing the regulation on standards for security features and biometrics in passports and travel documents issued by the member states. The aim is to develop and maintain efficient and secure biometric ... passport production procedures (see page 5). ... EUROSAI ITWG: Parallel Audit on Biometric Passports ... Swiss SAI summed up results of audits concluded in seven countries (Belgium, Latvia, Lithuania, Norway, Portugal, Switzerland). The evaluation of the reported results showed that the overall passport ... process is generally under control while a couple of high-risk findings were identified in the non-process-specific assessments. In the non-process-specific assessments, most of the countries found ... deficiencies and weaknesses related to the IS/IT system and the IT management. Medium risks have been identified in the area of laws and regulations, cost-benefit realisation and transparency, as well
Full description
Swiss Federal Audit Office , issued in 2015
Risk cases: 4
Audit of the procurement of ICT products with the potential to be standard products
ICT procurement system reviewed SFAO points out what is critical in ICT procurement. Requirements management is extremely important, as well as procurement strategies for relevant product groups. Legal rules should protect investments and support competition, but they can still be insufficient without appropriate reporting - if you want your system to adapt to changes.
Full description
Swiss Federal Audit Office , issued in 2015
Risk cases: 4
Coordinated Audit on Information Technology Governance
IT governance needs awareness and SAIs' support The OLACEFS auditors found that the greatest challenge for the SAIs is to raise the awareness of the audit institutions about the importance of IT governance and the benefits that could be obtained by improving its degree of maturity. The audit was conducted by 11 SAIs and coordinated by TCU of Brasil. They concluded: 'It is important, even urgent, to invest resources to implement or enhance: the IT committees; the IT planning process; strategic IT planning; monitoring the IT contracting process; the business continuity plan; the designation of a responsible person or unit to manage security information; a risk management process; an asset inventory process; an information security committee; and a policy for access control.'
Full description
Latin American andCaribbean Organization of Supreme Audit Institutions , issued in 2015
Risk cases: 5
Open Data Trend Report 2015
How to activate the open data policy The Dutch SAI looks for ways to improve open data practice in the Netherlands. They point at experience of two leading countries: UK and US, and advise to: prepare a concrete action plan, to increase number of mandatory published data, to develop government-wide data inventory and to put open data to work.
Full description
Netherlands Court of Audits , issued in 2015
Risk cases: 4
ACQUISITION REFORM: DOD Should Streamline Its Decision-Making Process for Weapon Systems to Reduce Inefficiencies
Refinement of decision-making processes The US Department of Defense (DOD) has long sought to improve the efficiency of its weapon system acquisition process, including the time and effort needed to complete the milestone decision process. Good practices of some DOD programs and five commercial firms were used by GAO to look for new momentum in refining the process.
Full description
US Government Accountability Office , issued in 2015
Risk cases: $risks.size()
ACQUISITION REFORM: DOD Should Streamline Its Decision-Making Process for Weapon Systems to Reduce Inefficiencies
Refinement of decision-making processes The US Department of Defense (DOD) has long sought to improve the efficiency of its weapon system acquisition process, including the time and effort needed to complete the milestone decision process. Good practices of some DOD programs and five commercial firms were used by GAO to look for new momentum in refining the process.
Full description
US Government Accountability Office , issued in 2015
Risk cases: $risks.size()
ACQUISITION REFORM: DOD Should Streamline Its Decision-Making Process for Weapon Systems to Reduce Inefficiencies
Refinement of decision-making processes The US Department of Defense (DOD) has long sought to improve the efficiency of its weapon system acquisition process, including the time and effort needed to complete the milestone decision process. Good practices of some DOD programs and five commercial firms were used by GAO to look for new momentum in refining the process.
Full description
US Government Accountability Office , issued in 2015
Risk cases: $risks.size()
ACQUISITION REFORM: DOD Should Streamline Its Decision-Making Process for Weapon Systems to Reduce Inefficiencies
Refinement of decision-making processes The US Department of Defense (DOD) has long sought to improve the efficiency of its weapon system acquisition process, including the time and effort needed to complete the milestone decision process. Good practices of some DOD programs and five commercial firms were used by GAO to look for new momentum in refining the process.
Full description
US Government Accountability Office , issued in 2015