Reports Search Reports Spatial Search Risk-cases Search Risk-cases Graph Traversal
17 results found in 7 ms Page 1 of 2
Audit of the key ICT project federal GEVER programme Federal Chancellery
During the first stage, two new GEVER (electronic records and process management) products were procured in an open WTO tender within the framework of the two-product strategy (federal GEVER WTO ... procurement project). CHF 1.6 million was spent on these. The departments and Federal Chancellery (departments/FCh) had to choose one of the two products within three months of the contract being awarded. ... ... Advanced process management system's cost-effectiveness and deadlines at risk ... Ever since 1990, sequential controls and file management have been part of the Federal Administration's IT landscape (GEVER business administration). Significant obstacles have to be overcome ... in order to ensure the successful creation and introduction of GEVER. Previous efforts did not have any widespread success and led to a diverse GEVER landscape. The federal GEVER project has now laid ... the foundations for simplification and centralisation.
Full description
Swiss Federal Audit Office , issued in 2015
Risk cases: 2
Central government staff costs
Results of staff reductions The British NAO found that departments had significantly reduced numbers of their civil servants and of course salary costs at the same time. But they reduced staff numbers mainly by minimising recruitment, and the age profile of the civil service has changed. NAO pays a lot attention to what effect this has had on the future pipeline of talent and skills. It reminds also that the departments need long-term operating models to work efficiently with the staff reduced.
Full description
National Audit Office , issued in 2015
Risk cases: 5
Staff scheduling in government institutions
Scheduling irregular hours work Danish Rigsrevisionen shows in their study problems with staff scheduling in government institutions where employees are required to work irregular hours. Optimized staff scheduling contributed to reducing payroll costs. On the other hand, problems with rearrangement of work, recording working hours, optimisation of staffing levels and analysis of overtime triggers - add up to high costs of workforce. IT is not always used as ally either.
Full description
National Audit Office of Denmark , issued in 2015
Risk cases: 5
Audit of the key ICT project regarding a consumption tax platform Federal Customs Administration (FCA)
The Swiss Federal Audit Office (SFAO) audited the key ICT project concerning a consumption tax platform from May to June 2015. The programme was launched in January 2014 with a budget of CHF 13.5 ... million. The instructing parties were the management of the Federal Customs Administration (FCA), the Swiss Alcohol Board (SAB) and the Federal Office of Information Technology, Systems ... and Telecommunication (FOITT). ... ... First attempt to ITC consumption tax project ... SAI Switzerland analised problems steming from insufficient specification of a complex ICT system project concerning a consumption tax platform. The project's budget turned out to cover only 70 ... % of the expected functions. Suspension of the project and restarting preparations stage followed.
Full description
Swiss Federal Audit Office , issued in 2015
Risk cases: 1
Audit on the broadband internet infrastructure access
Poland has been granted over PLN 4 billion from the European Regional Development Fund to build the broadband internet access infrastructure. As part of three operational programmes 90 percent ... of assumed financing was contracted, namely PLN 3.9 billion. By the end of 2015, Poland should complete the investment and account for the expenses. According to NIK there is a risk that the infrastructure ... construction will not be completed by the deadline and the EU funds may not be used to the full. ... ... Simpler regulations and better supervision needed ... Polish SAI audited a project, which aim had been to develop broadband internet network across the country. They revealed that legal obstacles, idleness and lack of supervision were the main causes ... of delays. Some of the projects are in danger of not being completed on time and some of the EU funds may not be fully used.
Full description
Supreme Audit Office of Poland , issued in 2015
Risk cases: 2
Conflicts of interest
First, recognise the conflicts of interest are a real risk the British NAO gathered a significant amount of intelligence on conflicts, particularly in the health and education sectors. These are areas of government where services are increasingly commissioned and delivered by parties at arm’s-length to departments. Conflicts of interest can occur naturally as a product of the way a system is designed and most often arise from operational situations.
Full description
National Audit Office , issued in 2015
Risk cases: 8
Open Data Trend Report 2015
How to activate the open data policy The Dutch SAI looks for ways to improve open data practice in the Netherlands. They point at experience of two leading countries: UK and US, and advise to: prepare a concrete action plan, to increase number of mandatory published data, to develop government-wide data inventory and to put open data to work.
Full description
Netherlands Court of Audits , issued in 2015
Risk cases: 4
Extract from the report to the Public Accounts Committee on the access to IT systems that support the provision of essential services to the Danish society
The report is focused on the significant risk that is associated with inadequate management and control of domain administrator privileges, which makes it possible for unauthorized persons to obtain ... access to the IT systems and data of the institutions. Rigsrevisionen has not examined for what specific purposes unauthorized access to the institutions’ systems and data can be used. ... ... Inadequate management and control of domain administrator privileges ... The Danish report concerns the measures - taken by six government institutions of various branches of State activities - to protect IT systems and data that support the provision of essential ... services to the Danish society from unauthorized access, obtained on the basis of domain administrator privileges.
Full description
National Audit Office of Denmark , issued in 2015
Risk cases: 4
Effectiveness of development of broadband network or high-speed internet
The National Audit Office audited whether the state has made every effort to ensure that everyone can have unlimited access to fast internet connection by 2020. The National Audit Office also ... analysed whether the network of fibre-optical cables or the basic broadband network, which is built with European Union support and should guarantee high-speed internet connection, has helped to achieve ... this goal. ... ... ... Slower broadband paid by customers ... and institutions. Private companies have not entirely met the Government's expectations. The Estonian SAI has looked for an answer: Why? ... The Estonian Information Society Development Plan foresees that high-speed internet of 30 Mbit/s should be accessible to all people in Estonia by 2020 and that 60% of the population will be using ... superfast internet of over 100 Mbit/s. To achieve these goals, the state, with the help of European Union support, decided to establish a broadband network which is not further than 1.5 km from 98% of homes
Full description
National Audit Office of Estonia , issued in 2015
Risk cases: 3
ACQUISITION REFORM: DOD Should Streamline Its Decision-Making Process for Weapon Systems to Reduce Inefficiencies
Refinement of decision-making processes The US Department of Defense (DOD) has long sought to improve the efficiency of its weapon system acquisition process, including the time and effort needed to complete the milestone decision process. Good practices of some DOD programs and five commercial firms were used by GAO to look for new momentum in refining the process.
Full description
US Government Accountability Office , issued in 2015
Risk cases: $risks.size()
17 results found. Page 1 of 2 next