The Shared Services Centre
The necessary environment for the efficient management of the Shared Service Center is lacking The department's administration of the Shared Services Centre (SSC) has been effective for sharing resources between the departments and delivering selected back-office services to a small client base. However, the governance arrangements established to oversight the SSC have not positioned it well for the future and the departments have not yet determined if the arrangement is efficient and resulting in savings. ANAO found instances where the advisory board of SSC was not consulted or involved in decisions relating to the strategic direction, financial arrangements and expenditure priorities. Information reported to the board did not focus on areas of strategic importance and the quality and completeness of this information could be improved. The mechanisms established for setting out responsibilities and obligations and ensuring transparency for services delivered by the SSC was weak. Service standards and levels were not fixed and can change. The delineation of responsibilities between the SSC and its clients was not clear and there was no commitment by the SSC to certify the quality of its control framework.
Full description
The Australian National Audit Office , issued in 2016
Risk cases: 2
Cost-intensive data centres stood idle for years
Idle data centres As found by the German SAI, some of costly Federal data centres stood largely idle. The Ministry failed to adequately assess the project risks. The Ministry needs to avoid similar shortcomings in the proposed federal IT consolidation project.
Full description
Bundesrechnungshof , issued in 2016
Risk cases: 1
The National Government Service Centre – Has administration become more effective?
The purpose of this audit has been to investigate whether the Service Centre has made administrative operational support functions taken over from client agencies more effective, and to find ... explanations for the results so far achieved by the Service Centre. The audit has also aspired to illustrate how agencies that do not subscribe to the services regard their potential for doing so ... . These viewpoints have been analysed with a special focus on the conditions that applied to the Service Centre when it was formed and the measures taken by the Government and the Service Centre in the first years. ... ... Has Swedish public administration become more effective? ... The Service Centre – payroll and financial administration IT system for Swedish public agencies under the government – has achieved the target of a subscription rate of 25 per cent of the total ... number of state employees. However, subscription to the Service Centre was initially slower than the Government had predicted and meant lower revenues than expected in autumn 2013. The Service Centre ... of agencies' subscription to the Service Centre’s services was limited to start with. For example, the Service Centre’s operational targets for subscription did not refer to agency size, which is important
Full description
Swedish National Audit Office , issued in 2016
Risk cases: 2
Use of consultants and temporary staff
New skills needed in a longer term UK NAO: Used well, consultants and temporary staff can be an important source of specialist skills and capabilities that are uneconomic for departments to maintain in their permanent staff. Since 2009-10, the government has used spending controls to reduce its use of consultants and temporary staff, and by 2014-15 spending had fallen by £1.5 billion. However, spending has increased by between £400 million and £600 million since 2011-12, suggesting that this was more of a short-term reduction than a sustainable strategy. In the longer term, departments will need to develop workforce, skills and capacity plans to reduce their dependence on external skills. They will need to improve their strategic workforce planning to determine where they can deploy existing staff, where they need to recruit, and where they need to engage temporary resources. Without this, departments cannot demonstrate that they are achieving value for money from the use of consultants and temporary staff.
Full description
National Audit Office , issued in 2016
Risk cases: 7
Performance measurement by regulators
Performance measurement for regulators Primary adressees of this good practice guide - by the British NAO - are regulators, the public institutions established for making sure that an industry or system works legally and fairly. But we are sure that many more can find this guidance useful - including auditors. NAO presents a comprehensible framework for performance measurement and hints how to focus on influence that regulators can use.
Full description
National Audit Office , issued in 2016
Risk cases: 2