VETERANS’ HEALTH CARE - Preliminary Observations on VHA’s Claims Processing Delays and Efforts to Improve the Timeliness of Payments to Community Providers
Due to increases in expenditures and utilization of VA care in the community services in recent years, VHA has had difficulty processing claims in a timely manner. In planning to consolidate its ... existing VA care in the community programs, as required by law, the agency said it will examine strategies for improving the timeliness and accuracy of its payments to community providers.<br ... VHA’s timeliness in processing claims; (3) community providers’ experiences; and (4) VHA’s recent actions and plans to improve its claims processing and payment timeliness. To conduct its ongoing work ... Data processing hold back by technology limitation, workload and administrative burden ... US GAO analyzed all factors of slower processing and user unfriendliness that occur sometimes to the veterans healthcare. The main focus is data processing - and it has been proved that it can ... be failing not only because of technology, but also because of work-process design, staff and organisation.
Full description
General Accountability Office , issued in 2016
Risk cases: 6
Use of consultants and temporary staff
New skills needed in a longer term UK NAO: Used well, consultants and temporary staff can be an important source of specialist skills and capabilities that are uneconomic for departments to maintain in their permanent staff. Since 2009-10, the government has used spending controls to reduce its use of consultants and temporary staff, and by 2014-15 spending had fallen by £1.5 billion. However, spending has increased by between £400 million and £600 million since 2011-12, suggesting that this was more of a short-term reduction than a sustainable strategy. In the longer term, departments will need to develop workforce, skills and capacity plans to reduce their dependence on external skills. They will need to improve their strategic workforce planning to determine where they can deploy existing staff, where they need to recruit, and where they need to engage temporary resources. Without this, departments cannot demonstrate that they are achieving value for money from the use of consultants and temporary staff.
Full description
National Audit Office , issued in 2016
Risk cases: 7
Incorrect payments in social insurance - Control activities of the Swedish Social Insurance Agency
In 2014 the social insurance system accounted for six per cent of GDP. The long-term sustainability of a system of that magnitude requires that the public perceives its purpose to be important ... , that it is well administered and that it is as free of abuse as possible. It must also be financially stable over time, since major fluctuations impact other areas of the central government budget. When ... these things function as they should, the system is perceived to be legitimate and enjoys public confidence.<br/> According to available estimations, almost SEK 20 billion had been paid out incorrectly from ... Balance of priorities needed to reduce incorrect payments ... Role of social insurance in public finance is so substantial that reduction of incorrect payments' volume is matter of huge savings. The Swedish NAO noted positive initiatives by the Social Insurance ... Agency in this regard. However they found also, that serious problems can stem from giving higher priority to the speed of payment and customers satisfaction. They both are undoubtedly important features ... of each system, still, the prevention of incorrect payments needs strategic support to be really effective.
Full description
Swedish National Audit Office , issued in 2016
Risk cases: 3
Homelessness
Homelessness grows despite increased spendings to reduce it British NAO analyses the root-causes of unsuccessful effort to reduce homelessness in England. They point at a side effect of the Goverment reform of welfare reform and at lack of full impact assessment.
Full description
National Audit Office , issued in 2016
Risk cases: 3
FEMA Needs to Address Management Weaknesses to Improve Its Systems
Controls in emergency management GAO audited the agency of the Department of Homeland Security, responsible for federal efforts to mitigate, respond to, and recover from disasters. American auditors recommend that the agency fully define its investment board’s roles and responsibilities and procedures for selecting and overseeing investments, update its strategic plan and complete plans for IT modernization, and establish time frames for completing workforce planning efforts. The agency should also establish policies and guidance for implementing key IT management controls.
Full description
General Accountability Office , issued in 2016
Risk cases: 4
Federal Agencies Need to Address Aging Legacy Systems
Be aware of legacy IT risks The US government spends about 75 percent of the total amount budgeted for information technology on operations and maintenance. GAO reviewed Office of Management and Budget and 26 agencies, covering years 2010 through 2017 and recommends to develop a goal for spending measure and finalize guidance to identify and prioritize legacy IT needing to be modernized or replaced.
Full description
General Accountability Office , issued in 2016
Risk cases: 3
The Shared Services Centre
The necessary environment for the efficient management of the Shared Service Center is lacking The department's administration of the Shared Services Centre (SSC) has been effective for sharing resources between the departments and delivering selected back-office services to a small client base. However, the governance arrangements established to oversight the SSC have not positioned it well for the future and the departments have not yet determined if the arrangement is efficient and resulting in savings. ANAO found instances where the advisory board of SSC was not consulted or involved in decisions relating to the strategic direction, financial arrangements and expenditure priorities. Information reported to the board did not focus on areas of strategic importance and the quality and completeness of this information could be improved. The mechanisms established for setting out responsibilities and obligations and ensuring transparency for services delivered by the SSC was weak. Service standards and levels were not fixed and can change. The delineation of responsibilities between the SSC and its clients was not clear and there was no commitment by the SSC to certify the quality of its control framework.
Full description
The Australian National Audit Office , issued in 2016
Risk cases: 2