Reports Search Reports Spatial Search Risk-cases Search Risk-cases Graph Traversal
14 results found in 8 ms Page 1 of 2
RURAL BROADBAND DEPLOYMENT: Improved Consistency with Leading Practices Could Enhance Management of Loan and Grant Programs
Green Book can help in broadband development US GAO applied its COSO based Green Book to review consistency of support programs for rural information infrastructure.
Full description
US Government Accountability Office , issued in 2017
Risk cases: 7
Does the state administration effectively use the stored information?
State administration could use the accumulated information more effectively Latvian auditors found that government institutions have a good cooperation in the area of data use, but there are still several areas wherein a person still has to perform the function of a 'courier'. Many channels of data exchange and distribution used in state administration create a fragmented and complicated environment for maintenance of ICT, while responsible ministry does not become actively involved and does not coordinate cooperation of institutions.
Full description
State Audit Office of the Republic of Latvia , issued in 2017
Risk cases: 4
Audit of the asset preservation and management activities of state-owned (partly state-owned) economic organisations – HungaroControl Hungarian Air Navigation Services Pte.Ltd.Co.
Compliance review of an air traffic services provider Lack of formal approval of the 2014 annual report was an issue found by Hungarian auditors in HungaroControl, a state-owned company, which provides training for air traffic personnel and carries out air navigation research and development.
Full description
State Audit Office of Hungary , issued in 2017
Risk cases: 1
Correlations between the operational risks of companies in the majority ownership of local governments and the financial situation of the local governments
Risks related to local governments-owned companies The Hungarian SAI analysed four risk areas, taking 19 aspects and the specificities of Hungary’s settlement patterns into consideration. The four areas defined were the following: performance of public tasks, exercise of proprietary rights, financial stability of local governments, and short and medium-term stability of the financial management of companies.
Full description
State Audit Office of Hungary , issued in 2017
Risk cases: 1
Housing in England: overview
Efforts to support housing Even if housebuilding in England has not kept pace with need and there has been a reduction in social rented homes, significant advantages can be enjoyed: an increase in home ownership and in the number of private rented homes. The quality of housing improved in recent years too. The National Audit Office has reviewed critical elements of the housing being one of the government's key priorities. Looking for risks, they found that a potential conflict of objectives can lead to tensions in delivery.
Full description
National Audit Office , issued in 2017
Risk cases: 2
Federal Institute for Risk Assessment purchased unnecessary software
Risk of poor requirements management The Germamn SAI audited the Federal Institute for Risk Assessment that introduce a new software. Time of implementation was nearly three times as long as originally scheduled. The costs also nearly trebled. Moreover, the Institute purchased unnecessary licences for expanding the software
Full description
Bundesrechnungshof , issued in 2017
Risk cases: 2
Digital transformation in government
Support exemplars, provide consistent guidance... and do not lose focus As the NAO states: Government faces significant challenges in providing public services. While many government services are now available online, public administration is struggling to manage more complicated programmes and to improve the complex systems and processes that support public services.
Full description
National Audit Office , issued in 2017
Risk cases: 4
WannaCry Cyber Attack and the NHS
Why the British NHS became a victim of WannaCry The NAO's investigation points at the problem of insufficient powers of the cybersecurity coordinator across the health organisation. As a result no remedial actions were taken, and the cyber attack succeeded thanks to neglected precautions.
Full description
National Audit Office , issued in 2017
Risk cases: 3
Insufficient monitoring of consultancy work in large-scale IT projects
Insufficient monitoring of consultancy work in large-scale IT projects The German Federal Ministry of the Interior did not sufficiently plan, monitor and control consultancy work in two large-scale IT projects, not being thus able to evaluate the amount of work done and pay accordingly. It was recommended by SAI the establishment of a quality management system and its application mandatory for large-scale IT projects
Full description
Bundesrechnungshof , issued in 2017
Risk cases: 1
Population registration - uphill quality work
Quality of population register The Swedish NAO notes that quality requirements for population registration are highand that quality work should concentrate on the errors that have the most seriousconsequences for society. They point then at the need to increase knowledge of the errors, improve IT tools and governance to receive more quality work.
Full description
Swedish National Audit Office , issued in 2017
Risk cases: 4
14 results found. Page 1 of 2 next