Relocation of government jobs
Difficult experience of relocation of jobs The Danish government decided to move almost 4 thousand government jobs away from the metropolitan area. The purpose of the relocation was to attain a better balance and development across Denmark and ensure that government institutions were located close to the citizens and businesses. Study of the SAI Denmark shows that overall, the departments have implemented the whole operation in an appropriate manner. At the same time, however, the relocation had negative consequences for the institutions’ production which has also affected citizens and businesses.
Full description
Difficult experience of relocation of jobs The Danish government decided to move almost 4 thousand government jobs away from the metropolitan area. The purpose of the relocation was to attain a better balance and development across Denmark and ensure that government institutions were located close to the citizens and businesses. Study of the SAI Denmark shows that overall, the departments have implemented the whole operation in an appropriate manner. At the same time, however, the relocation had negative consequences for the institutions’ production which has also affected citizens and businesses.
Full description
National Audit Office of Denmark
, issued in 2017
Risk cases: 4
Federal Institute for Risk Assessment purchased unnecessary software
Risk of poor requirements management The Germamn SAI audited the Federal Institute for Risk Assessment that introduce a new software. Time of implementation was nearly three times as long as originally scheduled. The costs also nearly trebled. Moreover, the Institute purchased unnecessary licences for expanding the software
Full description
Risk of poor requirements management The Germamn SAI audited the Federal Institute for Risk Assessment that introduce a new software. Time of implementation was nearly three times as long as originally scheduled. The costs also nearly trebled. Moreover, the Institute purchased unnecessary licences for expanding the software
Full description
Bundesrechnungshof
, issued in 2017
Risk cases: 2
Population registration - uphill quality work
Quality of population register The Swedish NAO notes that quality requirements for population registration are highand that quality work should concentrate on the errors that have the most seriousconsequences for society. They point then at the need to increase knowledge of the errors, improve IT tools and governance to receive more quality work.
Full description
Quality of population register The Swedish NAO notes that quality requirements for population registration are highand that quality work should concentrate on the errors that have the most seriousconsequences for society. They point then at the need to increase knowledge of the errors, improve IT tools and governance to receive more quality work.
Full description
Swedish National Audit Office
, issued in 2017
Risk cases: 4
Products sold on the European market: unravelling the system of CE marking
Problems with general picture The Netherlands National Court of Audit was interested in finding out whether anyone keeps track of all the actors involved in the process of system of European Union product markings. The interest was aroused by an observation that the vast majority of the questions raised about the system were prompted by incidents and that the questioners did not generally appear to be interested in the operation of the system as a whole...
Full description
Problems with general picture The Netherlands National Court of Audit was interested in finding out whether anyone keeps track of all the actors involved in the process of system of European Union product markings. The interest was aroused by an observation that the vast majority of the questions raised about the system were prompted by incidents and that the questioners did not generally appear to be interested in the operation of the system as a whole...
Full description
The Netherlands Court of Audit
, issued in 2017
Risk cases: 5
RURAL BROADBAND DEPLOYMENT: Improved Consistency with Leading Practices Could Enhance Management of Loan and Grant Programs
Green Book can help in broadband development US GAO applied its COSO based Green Book to review consistency of support programs for rural information infrastructure.
Full description
Green Book can help in broadband development US GAO applied its COSO based Green Book to review consistency of support programs for rural information infrastructure.
Full description
US Government Accountability Office
, issued in 2017
Risk cases: 7
Does the state administration effectively use the stored information?
State administration could use the accumulated information more effectively Latvian auditors found that government institutions have a good cooperation in the area of data use, but there are still several areas wherein a person still has to perform the function of a 'courier'. Many channels of data exchange and distribution used in state administration create a fragmented and complicated environment for maintenance of ICT, while responsible ministry does not become actively involved and does not coordinate cooperation of institutions.
Full description
State administration could use the accumulated information more effectively Latvian auditors found that government institutions have a good cooperation in the area of data use, but there are still several areas wherein a person still has to perform the function of a 'courier'. Many channels of data exchange and distribution used in state administration create a fragmented and complicated environment for maintenance of ICT, while responsible ministry does not become actively involved and does not coordinate cooperation of institutions.
Full description
State Audit Office of the Republic of Latvia
, issued in 2017
Risk cases: 4
Insufficient monitoring of consultancy work in large-scale IT projects
Insufficient monitoring of consultancy work in large-scale IT projects The German Federal Ministry of the Interior did not sufficiently plan, monitor and control consultancy work in two large-scale IT projects, not being thus able to evaluate the amount of work done and pay accordingly. It was recommended by SAI the establishment of a quality management system and its application mandatory for large-scale IT projects
Full description
Insufficient monitoring of consultancy work in large-scale IT projects The German Federal Ministry of the Interior did not sufficiently plan, monitor and control consultancy work in two large-scale IT projects, not being thus able to evaluate the amount of work done and pay accordingly. It was recommended by SAI the establishment of a quality management system and its application mandatory for large-scale IT projects
Full description
Bundesrechnungshof
, issued in 2017
Risk cases: 1
Digital transformation in government
Support exemplars, provide consistent guidance... and do not lose focus As the NAO states: Government faces significant challenges in providing public services. While many government services are now available online, public administration is struggling to manage more complicated programmes and to improve the complex systems and processes that support public services.
Full description
Support exemplars, provide consistent guidance... and do not lose focus As the NAO states: Government faces significant challenges in providing public services. While many government services are now available online, public administration is struggling to manage more complicated programmes and to improve the complex systems and processes that support public services.
Full description
National Audit Office
, issued in 2017
Risk cases: 4
Analysis of alternatively financed building projects of the Federal Institutes ofTechnology
Analysis of alternatively financed building projects Hundreds of millions was invested by third parties in the Swiss Confederation's real estate portfolio and analyses show a net return of over 4% for investors. Early exit from this alternative financing must be examined to get some advantages and greater attention must be paid to the economic effectiveness for future financing models.
Full description
Analysis of alternatively financed building projects Hundreds of millions was invested by third parties in the Swiss Confederation's real estate portfolio and analyses show a net return of over 4% for investors. Early exit from this alternative financing must be examined to get some advantages and greater attention must be paid to the economic effectiveness for future financing models.
Full description
Swiss Federal Audit Office
, issued in 2017
Risk cases: 2
WannaCry Cyber Attack and the NHS
Why the British NHS became a victim of WannaCry The NAO's investigation points at the problem of insufficient powers of the cybersecurity coordinator across the health organisation. As a result no remedial actions were taken, and the cyber attack succeeded thanks to neglected precautions.
Full description
Why the British NHS became a victim of WannaCry The NAO's investigation points at the problem of insufficient powers of the cybersecurity coordinator across the health organisation. As a result no remedial actions were taken, and the cyber attack succeeded thanks to neglected precautions.
Full description
National Audit Office
, issued in 2017
Risk cases: 3